The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update June 2019

Noted Committee 1 paper

Place and Economic Development Committee noted this item on Monday 3 June 2019. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the Sub-Committee note the update on The Kiln Co-Working Innovations Space Project.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 3 pages

Recommendation

1.1That the Place and Economic Development Sub-Committee note the update on The Kiln Co-working Innovation Space Project.

Background

2.1The Council has previously agreed that 2 Copenhagen Street should be used as supported co-working innovation space for the creative sector in a partnership project with the Kiln Co-working Community Interest Company (CIC). The Council has agreed to provide £100,000 funding for the project and Worcestershire LEP is providing £195,000 for the Kiln’s internal fit out of the property.

2.2The Policy and Resources Committee agreed a rent free period of two and half years followed by a further period of two years at 50% rent reduction.

2.3The Place and Economic Development Sub-Committee have agreed ‘in principle’ to be a member of The CIC and to have a nominated Worcester City Council member as a non-executive director on The Kiln CIC board.

2.4Detailed surveys and inspections identified a number of structural problems with the building which would need to be addressed before the Kiln fit out. In October 2018 the Policy and Resources Committee approved £300,000 for the structural repairs work.

2.5It was agreed that the Kiln CIC can have temporary use of vacant ground floor space at the Guildhall North Wing until the refurbished accommodation is available.

3. Information

3.1Premises Refurbishment

Croft Building and Conservation were awarded the tender for the main premises refurbishment works. The company started onsite on 11th February and the construction and refurbishment works are progressing well. The strip out, demolition and creation of new wall openings are complete; plastering, painting and electrical works are in progress. A number of new building issues have become apparent during the course of the premises works. However these have been managed within the existing project management and budget or referred to the Property Management team, if identified as out of scope. Procurement of items, which are not part of the main building works tender e.g. furniture, creative décor, air conditioning units, IT infrastructure is almost complete. These items are within the Kiln fit out budget.

The target date for completion of premises refurbishment works is end of July.

3.2Kiln 0.5

The decision to open the Kiln 0.5 co-working space in the Guildhall has created a number of positive outcomes.

Thirty five businesses have used the space since opening, 12 of whom have become members and registered for the hot desk or fixed desk package. A number of other businesses have expressed interest in booking space when 2 Copenhagen Street is open.

The presence on the High Street has helped to raise the profile of the Kiln co- working space and project. It has provided opportunity for the Kiln Co-working CIC to gain experience of operating shared workspace, start generating income and consult with users about the plans for 2 Copenhagen Street.

The project exceeded its target for the WLEP output ‘Number of enterprises receiving non-financial support’ in 2018/19. The actual number achieved was 29 against a target of 10.

3.3Project Management

The premises/design team; business plan team; and project delivery team continue to meet on a regular basis to review progress, risks and issues and agree actions.

A communication and marketing plan is being developed. There are regular updates on social media, as the building works progress and to generate interest. Promotion at networking event is in progress including the recent University of Worcester business start up fair and the WINN ‘Great Things’ event in June.

The official opening of the Kiln is scheduled for September.

3.4Funding and Finance

The Worcestershire LEP claim for £195,000 was completed within deadline and has been approved and paid. Evidence of the Worcester City Council match funding to be submitted by end of June.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Kiln Co-Working Innovation Space, 2 Copenhagen Street: Progress Update June 2019Report 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update June 2019This decision
  2. The Kiln Co-Working Innovation Space Project: Progress UpdateNoted
  3. Loan to Kiln Co-Working Community Interest CompanyNoted
  4. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update October 2019Noted
  5. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress Update 2019Decided
  6. The Kiln Co-Working Innovation Space, 2 Copenhagen Street - Progress UpdateNoted

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies