Procurement of Building Maintenance and Minor Works Measured Term Contract and Electrical Services Measured Term Contract

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Tuesday 4 June 2019. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

That the Committee agree to: 1. approve the tendering of 2 new measured term contracts in respect of Building Maintenance and Minor Works, and Electrical Services; 2. approve the outline award criteria for these contracts as set out in the report; and 3. delegate approval of the award of each contract to the Corporate Director - Finance and Resources.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 4 pages

Recommendation

1.1To approve the tendering of 2 new measured term contracts in respect of Building Maintenance and Minor Works, and Electrical Services;

1.2To approve the outline award criteria for these contracts as set out in the report; and

1.3To delegate approval of the award of each contract to the Corporate Director Finance and Resources.

Background

2.1At its meeting on 20 March 2018, the Committee agreed to bring property services in-house with effect from 1 April 2019. The Committee delegated authority to the Managing Director, in consultation with the Chair and the Vice-chairs of the Policy and Resources Committee, to finalise all financial and contractual arrangements for the smooth transition of property services from Place Partnership to an in-house service. The transfer of the property service has been completed successfully and the new Property and Asset Management service has been in operation since 1 April 2019.

2.2Prior to 31 March 2019, supply contracts were held by Place Partnership Ltd (PPL) on behalf of the Council and other PPL clients to facilitate the management and maintenance of the Council’s and others’ estates. Some of these had been procured historically and novated to Place on the formation of the company. It was not possible to novate these to the City Council and procurement exemptions have been obtained to agree limited 12-month term contracts with 3 existing suppliers for the continuation of general building maintenance, electrical and mechanical services.

2.3Therefore new contracts need to be procured to be operative with effect from 1 April 2020. The Council’s procurement regulations require that for purchases over the European Union threshold Committee approval is required:

 To advertise a contract;  To approve the evaluation model; and  To award a contract 2.4 A review of previous years’ repairs and maintenance expenditure indicates that the likely value of these contracts is in the order of £200,000 pa for general building, £80,000 pa for electrical services and £35,000 pa for mechanical services. The current EU threshold for services contracts is £181,302 euros.

2.5The procurement provides the opportunity for the Council to reset its expectations of quality and service and performance management under any new contract and develop longer term partnering relationships with suppliers in accordance with recognised construction industry thinking.

3. Preferred Option

3.1Following a review of options undertaken with Procurement officers, it is recommended that the Council’s interests are best served by the procurement of separate measured term contracts for general building maintenance and minor works, electrical services and mechanical services.

3.2A common contract term of five years, extendable by a further 2 years dependent on performance, has been proposed for the Building Maintenance and Electrical Services contracts in order to balance the ability to widen contractor interest and best value for money, with the ability for the Council to be able to review performance and make alternative arrangements if necessary.

3.3At this length, the contract values for Building Maintenance and Minor Works and Electrical Services will require them to be procured through the OJEU process.

3.4This approach will balance the objectives of sustaining the local economy by allowing local suppliers with the necessary capacity to meet the Council’s requirements to be able to bid, including the current providers. There will be no guaranteed minimum payments to the suppliers and whilst the Council will be at liberty to award work elsewhere, the use of the term contracts will be maximised on the grounds of efficiency and quality.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Building Maintenance and Minor Works Measured Term Contract and Electrical Services Measured Term ContractReport 4 pages DownloadRead as text

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies