Worcester City Council
Policy and Resources Committee, Tuesday 4 June 2019 at 7.00pm

Worcester City Centre Masterplan - Adoption

Approved Committee 1 paper

Policy and Resources Committee approved this item on Tuesday 4 June 2019. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the Committee recommend to Council to adopt the City Centre Masterplan, incorporating the amendments circulated at the meeting.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 5 pages

Recommendation

1.1That the Committee recommend to Council to adopt the City centre masterplan.

Background

2.1The City Council approved the funding for the production of a City centre masterplan (masterplan) in March 2017 and consequently the Worcestershire LEP also agreed to make a contribution. A new masterplan was identified as the appropriate response to a number of key town planning, economic plans and development projects that had progressed since the David Locke Associates stage one Master Plan was completed in July 2012.

2.2A masterplan project group was created of senior members and senior officers (Chair and Vice Chair of Place and Economic Development Sub-Committee, Worcester City Council Managing Director, Chief Executive of the Worcestershire LEP and Worcestershire County Council – Economy & Highways) to oversee the masterplan development.

2.3A competitive procurement process occurred in which NODE were successfully appointed as masterplan consultants. The consultants brief was, in summary, as follows:

Overall Master Plan Aims:

 A successful and growing “first division” Cathedral and University City, with more homes, businesses and jobs  A City with prestige tourist, education and retail attractions  A place that maintains its “city in the country” feel, its valued heritage assets and environmental quality

Overall Master Plan Objectives:

 the centre’s mixed-use regeneration sites  a new strong and high-class and growing City centre commercial offer  an improved City centre retail/cultural offer  on-going growth of the university and college  an urban design context for future growth that recognises its “university and cathedral” character  a step change in infrastructure and transport investment that focuses growth in the City centre 2.4 The masterplan presents a long term vision for the City centre. It is therefore important that it is based upon broad political, stakeholder and resident support to ensure that it can fulfil its roles as a planning document and as a means to engage with the investment market, government agencies and external stakeholders.

2.5Throughout the masterplan development process a number of engagement exercises have occurred including:

 Creation of a project board which included Officers of Worcester City Council, Worcestershire County Council and Worcestershire Local Enterprise Partnership as well as chair and vice chair of Worcester City Council Place and Economic Development Committee (PED).

 Stakeholder workshops which focused on ‘seeing the wider picture’, ‘putting plans in place’ and ‘delivering the vision’ were undertaken and were attended by numerous stakeholders including Historic England, Civic Society, Canals and Rivers Trust, Environment Agency, West Mercia Police, Network Rail, University of Worcester, Worcester Cathedral along with land owners and other interested parties.

 Member briefings after stakeholder workshops and Member workshop.

 One to One meetings with a number of key stakeholders including Heart of Worcestershire College, Worcester BID along with land owners.

2.6These engagement exercises aided the direction and production of the draft masterplan, which was launched to public and stakeholder consultation on the 9th October 2018.

2.7The consultation process on the draft masterplan document finished in December 2018 and included:

 public and business engagement events (Crowngate and Guildhall)  public questionnaire (City Council website)  stakeholder engagement consultations.

2.8A report was presented to, and noted by, the Place and Economic Development Committee, at its meeting in January 2019 presenting the results of consultation and suggested amendments to the masterplan in response.

2.9The key amendments to the draft masterplan relate to:

 Maintaining the same provision of car parking spaces, controlled by the City Council, within the City centre

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Worcester City Centre Masterplan: AdoptionReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Worcester City Centre Masterplan - AdoptionThis decision
  2. Application 26/00440/LB - Worcester City Museum and Art Gallery, Foregate StreetDecided
  3. Worcester City Strength in Community StrategyAgreed
  4. Worcester City District Collaborative - Six Monthly UpdateNoted
  5. Worcester City Community Engagement Strategy DevelopmentAgreed
  6. Digital Connectivity - Worcester City CentreNoted

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies