That the Committee agree to: 1. approve the request from Worcestershire Football Association for loan funding of up to £750,000 towards the completion of the development of the County Sports Playing Field at Claines Lane; and 2. delegate to the Corporate Director, Finance and Resources and the Deputy Director, Governance authority to finalise the finance and legal arrangements governing the proposed loan.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1That the Committee approves the request from Worcestershire Football Association for loan funding of up to £750,000 towards the completion of the development of the County Sports Playing Field at Claines Lane; and
1.2To delegate to the Corporate Director, Finance and Resources and the Deputy Director, Governance authority to finalise the finance and legal arrangements governing the proposed loan.
Background
2.1Worcestershire Football Association has received planning consent for the development of the County Sports Playing Field at Claines Lane, Worcester. The development will include demolition of the existing clubhouse and changing rooms on the site and the construction of a new clubhouse and changing rooms, incorporating office space. The FA is also planning the replacement of a grass pitch with a floodlit artificial grass pitch, a new 100 seat stand and new flood lights to an existing main grass pitch. The plans also include improvements to landscaping and access pathways.
2.2Planning approval was granted at the Planning committee meeting of 13 December 2018. Since that date, the FA has progressed the development through various stages, including making applications to funding bodies to finance the project. As part of this process the FA has approached the Council with a request for loan funding of up to £750,000. In support of the application the FA has submitted a funding request which is attached at Appendix A. This indicates that the loan requested is a maximum amount and would be drawn down only if, and as, required.
2.3The FA has provided a cashflow statement to indicate anticipated levels of income to secure future repayments which is provided in a confidential Appendix B, which also includes details of the estimated costs of the project and a breakdown of funding secured to date. Income guarantees will be sought as further risk mitigation and any loan will be secured against the assets of the facility.
3. Preferred Option
3.1To agree in principle to award a capital loan of up to £750,000 to support the completion of the development. The loan will be secured through a legal charge over the property. 4. Alternative Options Considered
4.1To not provide loan funding. The FA has sought and obtained funding from a variety of sources and is using its own capital resources, as set out in Appendix B. If the FA is unable to find the remaining £750,000 needed, the scheme may be put at risk.
4.2To provide capital grant. The Council could provide grant from capital receipts or from its revenue reserves. However, those reserves which could be provided for this purpose are fully committed. The use of loan funding will enable the Council to recover its costs in the form of capital receipts and provides a small element of surplus to cover its risks.
5. Implications
5.1Financial and Budgetary Implications
The scheme is proposed by Worcestershire FA and there would, therefore, be no direct costs arising to the Council. However costs would accrue to the Council in the event that the FA did not meet the terms of the proposed loan and the Council became owners of the facility in default. Options for consideration, and the expected costs thereof, would be investigated at the point that such a decision was required, but would include, at least, the revenue implications of any borrowing undertaken. This is estimated to be £33,400 per annum at current PWLB rates if the full amount were borrowed but such costs can be mitigated by the use of capital receipts and other forms of direct financing.
The level of income to be derived is based on a loan value that meets the viability threshold for the development. The proposed rate is based on current PWLB rates and would provide a small margin for risk.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.