That the Committee agree to: 1. note the contents of the Report including the outcomes of the recent pre-market engagement exercises and the ongoing funding discussions with Homes England in respect of the former swimming pool site at Sansome Walk (“the Site”); 2. approve the key objectives for the scheme and the procurement method and evaluation criteria set out in sections 3 and 4 as the basis to select a development partner to deliver a residential scheme at the Site following completion of Site demolition and remediation works; 3. delegate authority to the Corporate Director Finance and Resources and the Corporate Director Place in consultation with the Chair and Vice Chairs of the Committee to undertake a procurement process in accordance with recommendation 1.2 above; and 4. receive a further report for approval, on the outcome of the procurement process and ongoing funding negotiations, before any contracts are concluded, in order to determine the final arrangements for the delivery of a residential scheme on the Site.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Policy and Resources Committee, 10 pages
Recommendation
That the Committee:
1.1notes the contents of the Report including the outcomes of the recent pre- market engagement exercises and the ongoing funding discussions with Homes England in respect of the former swimming pool site at Sansome Walk (“the Site”);
1.2approves the key objectives for the scheme and the procurement method and evaluation criteria set out in sections 3 and 4 as the basis to select a development partner to deliver a residential scheme at the Site following completion of Site demolition and remediation works;
1.3delegates authority to the Corporate Director Finance and Resources and the Corporate Director Place in consultation with the Chair and Vice Chairs of the Committee to undertake a procurement process in accordance with recommendation 1.2 above;
1.4receives a further report for approval, on the outcome of the procurement process and ongoing funding negotiations, before any contracts are concluded, in order to determine the final arrangements for the delivery of a residential scheme on the Site.
Background
2.1At its meeting on 31 July 2019 the Committee gave authority for a series of actions relating to the demolition and remediation of the Sansome Walk Site. Officers are now implementing those actions. A procurement is scheduled to commence in the new year for a demolition and remediation contractor. The Committee has reserved for itself the future decision as to whether the Council or a development partner should undertake the remediation stage of the works.
2.2Negotiations have continued with Homes England about potential grant support towards the Site remediation costs. However the announcement of the General Election, introducing the purdah period, has meant that Homes England are now unable to confirm their decision on the grant until probably early in the new year. 2.3 Following the Committee’s previous decision that this Site should be redeveloped for residential use, the Council now needs to appoint a residential development partner. This must be done in time to input into the commitments which may be required from Homes England as well as to input into the Committee’s decision as to whether the Council or the developer should manage the remediation stage of the works contract.
2.4This report proposes the key objectives for the scheme together with a procurement route and evaluation method to select that development partner. The report seeks delegated authority to commence a procurement process, with the final decision to be referred to Committee for approval once developer bids have been considered and a firmer position on Homes England funding has been secured.
3. Scheme objectives and evaluation criteria
3.1Bearing in mind the current void position of the Site and the issues and risks identified in previous reports to the Committee, it is considered that the overall objectives from a redevelopment of the Site are as follows (in no specific order):
(a) safe remediation
(b) avoid further unnecessary delay
(c) return the Site to use
(d) maximise the potential to lever in third party funding
(e) support one or more strategic aims of the Council.
3.2In appraising what is possible to be achieved, it should be noted that the redevelopment of the Site offers a number of opportunities. Firstly, there is the existing Land Release Fund grant secured from One Public Estates, which is a contribution towards demolition costs, and the potential for a grant from Homes England under its Local Authority Accelerated Construction (LAAC) programme as a contribution towards remediation costs. These third party funding sources can be viewed as making a positive contribution to the overall financial viability of the scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.