Future High Streets Programme: Acquisition of Scala Theatre and Public Realm Works

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Tuesday 8 June 2021. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

That the Committee agree to: 1. approve the acquisition of the Scala Theatre on the terms set out in the private report; 2. authorise the Managing Director and the Deputy Director Governance to progress a funding agreement with Worcestershire County Council in respect of public realm works; and 3. authorise the expenditure of £170,000 of Future High Street Fund Grant towards advanced survey and design work for public realm schemes.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 6 pages

Recommendation

That Policy and Resources Committee:

1.1Approves the acquisition of the Scala Theatre on the terms set out in the private report;

1.2Authorises the Managing Director and the Deputy Director Governance to progress a funding agreement with Worcestershire County Council in respect of public realm works; and

1.3Authorises the expenditure of £170,000 of Future High Street Fund Grant towards advanced survey and design work for public realm schemes.

Background

1.1This report seeks authority to progress two of the interventions in the Future High Streets Fund programme: (i) Scala Theatre and (ii) public realm.

3. Acquisition of the Former Scala Theatre

3.1The conversion of the Former Scala Theatre, currently occupied by Shipleys Amusement Centre, to create a new live performance venue in the town centre is key to the Council’s FHSF proposals.

3.2The Council has now completed the acquisition of the adjoining property, the former Corn Exchange, and the feasibility work commissioned confirms that the two properties together are capable of creating a new performance venue of 450 to 500 seats, together with ancillary facilities.

3.3Shipleys are trading successfully from their current premises and have only been prepared to sell if suitable premises are available for the business to relocate to in an equivalent or more advantageous position, and the relocation is not a cost to the business. Furthermore, as their current premises are owned freehold, they have not been willing to consider leased premises as relocation opportunities.

3.4Policy and Resources Committee has agreed the principle of using compulsory purchase powers for the acquisition of property interests required to deliver the FHSF proposals. 3.5 Unlike the former Corn Exchange and 8 Angel Street, which were both on the market for sale, Shipleys cannot be regarded as a willing vendor and the Council’s approach to negotiations has been to agree terms that would be consistent with compensation payable under the compulsory purchase code. On this basis, the Council must have regard to the entitlement that Shipleys will have to the supplements payable on top of market value and ‘disturbance compensation’ covering any costs and/or loss of business reasonably incurred in relocating.

3.6Furthermore, the MHCLG Guidance on Compulsory Purchase process advises that ‘when offering financial compensation in advance of a compulsory purchase order, public sector organisations should, as is the norm, consider value for money in terms of the Exchequer as a whole in order to avoid any repercussive cost impacts or pressures on both the scheme in question and other publicly-funded schemes’.

3.7Acquiring authorities can consider all of the costs involved in the compulsory purchase process when assessing the appropriate payments for purchase of land in advance of compulsory purchase. For instance, the early acquisition may avoid some of the following costs being incurred:

 Legal fees (both for the order making process as a whole and for dealing with individual objectors within a wider order, including compensation claims)

 Wider compulsory purchase order process costs (for example staff resources)

 The overall cost of project delay (for example, caused by delay in gaining entry to the land)

 Any other reasonable linked costs

3.8In order to reach early settlements, acquiring authorities should make reasonable initial offers and be prepared to work constructively with claimants about relocation issues.

3.9A relocation opportunity for the Shipleys businesses has been identified in the city. The Council has indicated that it will pay the reasonable and proper costs of the relocation of the business in accordance with the provisions of the Compulsory Purchase Act 1965 and the Compensation Code, including:

 the agreed costs of fitting out the new premises

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Future High Streets Programme: Acquisition of Scala Theatre and Public Realm WorksReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Worcester

Search all
  1. Future High Streets Programme: Acquisition of Scala Theatre and Public Realm WorksThis decision
  2. Future High Street Fund Programme - Scala Arts CentreAgreed
  3. Future High Street Fund - Property Enhancement SchemeNoted
  4. Future High Street Fund - Programme UpdateAgreed
  5. Future High Street Fund - Wider Programme UpdateAgreed
  6. Future High Street Fund - Performance Arts VenueAgreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open