South Worcestershire Five Year Housing Land Supply 2021
DecidedCommittee2 papers
Place and Economic Development Committee decided this item on Monday 6 September 2021. Below is the council's own wording, with the papers it was decided on.
That the Committee: 1. notes the p ublication of the South Worcestershire Councils 2021 Five Year Housing Land Supply (5YHLS) Report and Appendices on 22 September 2021, which details that Officers consider for the period 1 April 2021 to 31 March 2026 a robust 5YHLS against the Standard Method housing requirement can be demonstrated; and 2. notes that on account of the South Worcestershire Councils being able to demonstrate a 5YHLS, all policies in the South Worcestershire Development Plan (SWDP) relating to the supply of housing should be given full weight in the determination of planning applications (excluding the elements of SWDP3 which are no longer appropriate given the utilisation of the Standard Method housing requirement and associated change in approach to 5YHLS).
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Place and Economic Development Committee, 4 pages
Recommendation
That the Place and Economic Development Committee:
1.1Notes the publication of the South Worcestershire Councils 2021 Five Year Housing Land Supply (5YHLS) Report and Appendices on 22 September 2021, which details that Officers consider for the period 1 April 2021 to 31 March 2026 a robust 5YHLS against the Standard Method housing requirement can be demonstrated.
1.2Notes that on account of the South Worcestershire Councils being able to demonstrate a 5YHLS, all policies in the South Worcestershire Development Plan (SWDP) relating to the supply of housing should be given full weight in the determination of planning applications (excluding the elements of SWDP3 which are no longer appropriate given the utilisation of the Standard Method housing requirement and associated change in approach to 5YHLS).
Background
2.1Local Planning Authorities have been required to demonstrate a 5YHLS since the publication of Planning Policy Statement 3 “Housing” (November 2006). The objective was to substantially increase the supply of housing across the country as advocated in the former Government’s Barker Review.
2.2The publication of the National Planning Policy Framework (NPPF; March 2012) resulted in the cessation of all Planning Policy Statements. However, the requirement to maintain a 5YHLS remains a key component of the NPPF, as updated (Paragraphs 74-77 refer) and boosting the supply of housing remains an important Government objective.
3. South Worcestershire Councils Five Year Housing Land Supply
3.1The adoption of the South Worcestershire Development Plan (SWDP) in February 2016 established, at SWDP3, five separate sub-areas (Malvern Hills, Worcester City, Wychavon, Wider Worcester Area Malvern Hills and Wider Worcester Area Wychavon) for dealing with housing, employment and retail provision, redistributing the requirements according to land availability and natural and environmental constraints. Since the adoption of the SWDP, the South Worcestershire Councils have published five separate 5YHLS Reports on an annual basis (Wider Worcester Area Malvern Hills since 2018/19 as required by SWDP3) against the annual housing requirements detailed in SWDP3.
3.2The SWDP is now more than five years old. As set out in the NPPF at Paragraph 74, in such circumstances the calculation of the 5YHLS position should be based on the local housing need calculated using the Standard Method rather than any housing requirement adopted in the Local Plan. Given this, a single joint approach to 5YHLS is being adopted by the South Worcestershire Councils from 2021 onwards. Any other approach to 5YHLS in South Worcestershire from 2021 onwards would not be appropriate as it would require the redistribution of either the Standard Method calculation for each Local Authority to the five sub-areas or the supply for each of the five sub-areas back to each Local Authority. It should be noted that it is the intention of the SWDP Review to formally establish a single joint approach to 5YHLS, and that the South Worcestershire Councils are considered as a single entity in the calculation of the Housing Delivery Test, with a 2020 measurement of 157% published in January 2021.
3.3The Standard Method calculation sets a baseline using the 2014-based household projections and makes an affordability adjustment according to the most recent median workplace-based affordability ratios, setting a cap of 40% above the average annual housing requirement figure set out in the existing policies and adding a 35% uplift to Greater London and the other 19 most populated urban centres. The latest Standard Method calculation for the South Worcestershire Councils is 1,283 dwellings per annum, as set out in Table 1 below.
Table 1 - South Worcestershire Councils Standard Method Calculation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Economic Development Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.