Resolved
That the Committee note the report.
Audit and Governance Committee noted this item on Wednesday 8 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee note the report.
1.1That the Committee note the report.
2.1To provide an update on Internal Audit’s progress towards meeting its objectives as set out in the audit plan for 2021/22.
2.2The Council is required under Regulation 6 of the Accounts and Audit Regulations 2018 to “maintain in accordance with proper practices an adequate and effective system of internal audit of its accounting records and of its system of internal control”.
3. Summary of Activity:
3.1A rolling testing programme on Debtors and Payroll has continued throughout Q1 and Q2 and the results will be reported during Q4 for 2021/22.
3.2There have been several audits completed as part of the 2020/21 programme since the last progress report; ICT, GDPR, Debtors, Creditors, Council Tax, NNDR, Benefits, Cash Receipting and are reported at Appendix 3. Two audits that have also been taking place as part of the 2021/22 programme are Grants and Project Management.
3.32020/21 work completed but awaiting management response/sign off is Payroll.
3.4Follow Up work has been continuing regarding Front Line Housing, Car Parking, Welfare Assistance. The results can be found at Appendix 4. Follow up for Sansome Walk is awaiting management sign off.
3.52021/22 Internal Audit Plan.
3.6Audits finalised at the end of October 2021 included: Worcester Regulatory Services
3.7Audits progressing through the draft report stage at the end of October 2021 included: Project Management Treasury Management 3.8 Audits progressing through the final clearance stage at the end of October 2021 included: Grants
3.9Audits being worked on or due to commence during Q3 included: GDPR Debtors Main Ledger Council Tax (outline testing schedule and scoping) NNDR (outline testing schedule and scoping) Benefits (outline testing schedule and scoping) Caring for Communities and People (CCP) Disabled Facilities Grants
3.10As work on the audits indicated above is classed as on-going or awaiting a management response a final ‘Assurance’ level will be assigned on completion along with the appropriate report reported to the next available Committee.
3.11Critical review audits are designed to add value to an evolving Service area. Depending on the transformation that a Service is experiencing at the time of a scheduled review a decision is made regarding the audit approach. Where there is significant change taking place due to transformation, restructuring, significant legislative updates or a comparison required a critical review approach will be used. To assist the service area to move forward, challenge areas will be identified using audit review techniques. The percentage of critical reviews will be confirmed as part of the overall outturn figure for the audit programme. To date, no critical review audits have been undertaken during 2021/22.
4. National Fraud Initiative (NFI)
4.1NFI data set uploads were completed in January 2021. Matches have been received by the Authority and checking will be undertaken in due course. WIASS is now working towards the next significant data set upload for NFI which is scheduled for December 2021. WIASS continues to play a supporting role for all the Partners regarding the NFI exercise.
5. Follow-Up Audits
5.1Follow up reviews are an integral part of the audit process. There is a rolling programme of review that is undertaken to ensure that there is progress with the implementation of the agreed action plans. The outcomes of the follow up reviews are reported in full at Appendix 4, where applicable, so the general direction of travel and the risk exposure can be considered by Committee.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Progress Report 2021/22Report | 95 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.