That the Committee agree to: 1. approve a variation to the lease of 54, 55 and 56 Foregate Street on the terms set out in the private report in support of The Arches – Worcester project; and 2. delegate authority to the Corporate Director - Finance and Resources and the Corporate Director – Planning and ... view the full minutes text for item 35.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1approves a variation to the lease of 54, 55 and 56 Foregate Street on the terms set out in the private report in support of The Arches – Worcester project; and
1.2delegates authority to the Corporate Director - Finance and Resources and the Corporate Director – Planning and Governance in consultation with the Chair and Vice Chairs of the Committee to conclude negotiations and enter into all necessary legal agreements to complete the proposed variations and related works.
Background
2.1In February 2019 the Department of Culture Media and Sport awarded a grant of £3m from the Cultural Development Fund (CDF), administered through the Arts Council, towards the Arches project with a further £1.6m to be secured through local contributions. The Arches project aims to regenerate the railway arches from Foregate Street down to the river and create a cultural destination, enhancing the existing creative offer of the city and delivering new festivals and creative industries into the city. The physical regeneration aspects of the project, managed through the project’s infrastructure workstream, have been divided into 3 phases:
Phase 1 – Refurbishment of 5 arches which are subject to an existing lease to the University of Worcester at the rear of the Hive, to offer lettings spaces to creative industries and a performance space, together with associated public realm to open up a pedestrian and cycle route.
Phase 2 – Refurbishment of 2 arches along Netherton Court to provide further accommodation with associated public realm to open up a pedestrian and cycle route.
Phase 3 - Demolition of 56 Foregate Street and public realm improvements to open up the proposed pedestrian and cycle route from the City Centre to the River Severn. 2.2 The implementation of Phase 3 of the infrastructure works required the acquisition of the leasehold interests in 56 Foregate Street (shown edged in red on the attached plan) in order to demolish the building on the site and achieve the project objective of creating a pedestrian and cycle route into Foregate Street.
2.3To facilitate this, at its meeting of 9 February 2021 the Committee approved the acquisition of the long leasehold interest in 54, 55 and 56 Foregate Street from Darvist Ltd. The acquisition of the lease with over 40 years to run was undertaken by the Council acting in its own capacity, not the Arches - Worcester partnership board, and was funded solely by Council resources. The income generated from letting of 54 and 55 Foregate street is forecast to be sufficient to cover the ongoing revenue costs of the acquisition, including the borrowing costs, based on current available information
2.4The freehold interest of all three sites remains with Network Rail but these properties are part of the national portfolio of railway arches which are leased to The Arch Co. The Council consequently needs to obtain the consent of Network Rail and the Council’s landlord The Arch Co. to any subsequent works including the proposed demolition of 56 Foregate Street.
2.5Within the demise of the properties acquired by the Council are two arches which are currently obscured by 56 Foregate Street and are not usable because of the limited access (shown edged in black in the attached plan, covering Nos. 54 and 56 foregate street and the area to the rear of No. 56). The demolition works will uncover these two arches and enable them to be brought into use as potentially income-generating assets. It has therefore been proposed that these two arches will form phase 2 of the project, thus obviating the need to acquire and convert two further arches.
3. Cultural Development Fund considerations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.