Date: 10th July 2024 AUDIT & GOVERNANCE COMMITTEE APPENDIX A
SUMMARY OF INTERNAL AUDIT PLAN
Audit Area Planned Days
Financial 55
Corporate Risks including Governance 101
Service Delivery and Operational Risks 56
Sub total 212
Plan management, advice and support 37
Completion & finalisation of audits which were in progress as at 1st April 2024 26
Sub total 63
Total Audit Days 275 WORCESTER CITY COUNCIL
Date: 10th July 2024 AUDIT & GOVERNANCE COMMITTEE AUDIT AREA STRATEGY LINK CORPORATE RISK BUDGET COMMENTS INDICATIVE REGISTER REF (DAYS) REPORTING DATE
Financial Audits
Debtors Underpins City Plan Financial Resources 10 September requirements 2024
Main Ledger Underpins City Plan Financial Resources 9 September requirements 2024
Payroll Underpins City Plan Financial Resources 6 September requirements 2024
Council Tax Underpins City Plan Financial Resources 6 September requirements 2024
Benefits Underpins City Plan Financial Resources 6 September requirements 2024 WORCESTER CITY COUNCIL
Date: 10th July 2024 AUDIT & GOVERNANCE COMMITTEE AUDIT AREA STRATEGY LINK CORPORATE RISK BUDGET COMMENTS INDICATIVE REGISTER REF (DAYS) REPORTING DATE
NNDR Underpins City Plan Financial Resources 6 September requirements 2024
Completeness of Income Underpins City Plan Financial 12 November & grant maximisation requirements Resources/ Local 2024 Government Funding
Sub Total - Financial 55
Corporate Risks including Governance
Workforce Planning and Underpins City Plan Staff Resources 8 Consultancy review, March 2025 Development requirements opportunity for Staff Resilience comparison of approaches with other WIASS partners.
Fraud Investigations Underpins City Plan Financial Resources 10 N/A including NFI requirements WORCESTER CITY COUNCIL
Date: 10th July 2024 AUDIT & GOVERNANCE COMMITTEE AUDIT AREA STRATEGY LINK CORPORATE RISK BUDGET COMMENTS INDICATIVE REGISTER REF (DAYS) REPORTING DATE
Data Protection, Underpins City Plan ICT Security 15 Consultancy support November Retention & Classification requirements to assist the Council 2024 in completing its ICO Accountability self assessment and tracker.
Fraud Risk Review Underpins City Plan Financial Resources 12 March 2025 requirements
Project Management Underpins City Plan Cuts across multiple 12 To include use of March 2025 requirements risks depending on consultants, as the nature of the requested by the projects Audit & Governance Committee
Procurement Underpins City Plan Financial Resources 12 To include assurance June 2025 requirements that the Council is following new rules which come into force in 2024. WORCESTER CITY COUNCIL
Date: 10th July 2024 AUDIT & GOVERNANCE COMMITTEE AUDIT AREA STRATEGY LINK CORPORATE RISK BUDGET COMMENTS INDICATIVE REGISTER REF (DAYS) REPORTING DATE
Best Value Assurance Underpins City Plan Financial 10 A review of the June 2025 requirements Resources/ Local accuracy and Government completeness of Funding qualitative and quantitative data included in the Best Value/ “Are We Safe” report.
Grant Certifications Stronger and Financial 10 As and when N/A Connected Resources/ Local required. Communities Government Funding
Corporate Health & Underpins City Plan Health & Safety 12 To include a review of November Safety requirements Guildhall risk 2024 Lone Working assessments and safe working practices.
Sub-Total – Corporate Risks including Governance 101 WORCESTER CITY COUNCIL
Date: 10th July 2024 AUDIT & GOVERNANCE COMMITTEE AUDIT AREA STRATEGY LINK CORPORATE RISK BUDGET COMMENTS INDICATIVE REGISTER REF (DAYS) REPORTING DATE
Service Delivery and Operational Risks
Asset Maintenance – Sustaining and Failure to maintain 10 March 2025 Statutory Inspections improving our and assess assets assets
Agency Costs – Value for Underpins City Plan Financial Resources 12 March 2025 Money Review requirements
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appx A WCC Draft Internal Audit Plan 2024-25Report | 7 pages | DownloadRead as text |
PDF |
Internal Audit Plan for 2024/25Report | 3 pages | Download |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.