Worcester City Council
Policy and Resources Committee, Tuesday 17 December 2024 at 7.00pm

Astwood Crematorium Project - End of RIBA Stage 3 Report

Agreed Committee 1 paper

Policy and Resources Committee agreed this item on Tuesday 17 December 2024. Below is the council's own wording, with the papers it was decided on.

Item149

Resolved

That the Committee agree: 1. to note the contents of the report including the progress made up to and including RIBA Design Stage 3, the appointment of a cremator manufacturer, the feedback from consultation and the development of the project cost estimate and risk register; 2. that, considering the affordability of the current cost estimate, the Council should now proceed with design Scheme C as set out in the report, comprising cremator replacement and related works along with chapel and chapel entrance refurbishment; 3. to recommend to Council an adjustment to the capital programme of up to £6,960,000 to fund the costs of the project, to include the necessary fees & surveys to progress the project through RIBA Stages 4 Technical Design, Stage 5 Construction and Stage 6 Handover; 4. to note that the Medium-Term Financial Plan will need to be adjusted to include an additional minimum revenue pressure of up to £603,500 per annum from 2026/27 onwards to cover the costs of borrowing relating to the project; and 5. to authorise Officers, with the oversight of the Major Programmes Member Reference Group, to undertake the following actions: ( i ) submit an application for planning consent and secure any other regulatory consents necessary to implement the project; (ii) commission further design and professional services to enable the project to progress through to practical completion, including RIBA Design Stages 4 -6; (iii) undertake a procurement and appoint a main works contractor for the project subject to a ... view the full minutes text for item 149.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee, 21 pages

Recommendation

That the Committee –

1.1Notes the contents of the report including the progress made up to and including RIBA Design Stage 3, the appointment of a cremator manufacturer, the feedback from consultation and the development of the project cost estimate and risk register;

1.2Agrees that, considering the affordability of the current cost estimate, the Council should now proceed with design Scheme C as set out in the report, comprising cremator replacement and related works along with chapel and chapel entrance refurbishment;

1.3Recommends to Council an adjustment to the capital programme of up to £6,960,000 to fund the costs of the project, to include the necessary fees & surveys to progress the project through RIBA Stages 4 Technical Design, Stage 5 Construction and Stage 6 Handover;

1.4Notes that the Medium-Term Financial Plan will need to be adjusted to include an additional minimum revenue pressure of up to £603,500 per annum from 2026/27 onwards to cover the costs of borrowing relating to the project;

1.5Authorises officers, with the oversight of the Major Programmes Member Reference Group, to undertake the following actions:

1.6(i) submit an application for planning consent and secure any other regulatory consents necessary to implement the project;

(ii) commission further design and professional services to enable the project to progress through to practical completion, including RIBA Design Stages 4 -6;

(iii) undertake a procurement and appoint a main works contractor for the project subject to a maximum budget of £2,674,000 (ex VAT);

(iv) take all necessary steps to bring to project to a successful completion, subject to there being no material change to the agreed parameters of the project budget, design scheme and anticipated risks as set out in this report. 2. Background

2.1In May 2024 Policy & Resources Committee approved the business case to support the procurement of 2 new electric cremators and recommended to Council an adjustment to the capital programme of up to £5,500,000 to cover the cost of electric cremator replacement and necessary fees & surveys to progress and conclude RIBA Stage 3 Design.

2.2As well as the electric cremator replacement works the scope referred to as ‘Back Of House’ also included associated cremator installation enabling works, cremator hall remodelling, new increased power supply, and Salix eligible grant work including a new heat exchange system for the crematorium building.

2.3This committee noted that the Medium-Term Financial Plan would need to be adjusted to include an additional minimum revenue pressure of up to £300,000 per annum from 2026/27 onwards to cover the costs of borrowing relating to the recommendation in May 2024 as set out in 2.1 above.

2.4Replacement of the existing cremators and ‘Back of House’ works formed part of a broader and aspirational capital project that sought to improve the public facing areas of the crematorium with an extension and significant refurbishment throughout. These works referred to as ‘Front of House formed part of two previous reports presented to Environment Committee on this project (March 2023 & July 2023).

2.5These and the report in May 24 noted the extent of the works to both the ‘Back & Front of House’ would be considered during RIBA Stage 3. Any proposed works would need to recognise and be informed by a comprehensive suite of site and building surveys and intrusive investigations. This information would help to inform the developing design and associate cost estimates.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Astwood Crematorium Project: End of RIBA Stage 3 ReportReport 21 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 16 attended
PA
Councillor Patricia AgarCommittee Member, present
MA
Councillor Mel AllcottCommittee Member, present
JB
Councillor Jenny BarnesCommittee Member, present as substitute
SC
Councillor Steve CockeramCommittee Member, present
LD
Councillor Lynn DenhamChair, present
JD
Councillor Jill DesayrahCommittee Member, present as substitute
AG
Councillor Adrian GregsonCommittee Member, apologies, sent representative
JJ
Councillor Jessie JaggerVice-Chair, present
EK
Councillor Ed KimberleyCommittee Member, present as substitute
KL
Councillor Karen LewingCommittee Member, present
AM
Councillor Alex MaceCommittee Member, present
RN
Councillor Robyn NorfolkCommittee Member, apologies, sent representative

All 16 on the meeting page

On this subject at Worcester

Search all
  1. Astwood Crematorium Project - End of RIBA Stage 3 ReportThis decision
  2. Use of Managing Director's Urgency Powers - Adjustment to Capital Programme for Astwood Crematorium ProjectNoted
  3. Referral Report from Policy and Resources Committee 21st May 2024 - Astwood Crematorium - Replacement of CrematorsAgreed
  4. Astwood Crematorium - Replacement of CrematorsAgreed
  5. Application 20/00685/CLE - Astwood Crematorium, Astwood RoadDecided
  6. Application P15M0099 - Worcester Crematorium, Tintern Avenue, Astwood RoadDecided

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open