That the Committee agree: 1. to note the contents of the report including the progress made up to and including RIBA Design Stage 3, the appointment of a cremator manufacturer, the feedback from consultation and the development of the project cost estimate and risk register; 2. that, considering the affordability of the current cost estimate, the Council should now proceed with design Scheme C as set out in the report, comprising cremator replacement and related works along with chapel and chapel entrance refurbishment; 3. to recommend to Council an adjustment to the capital programme of up to £6,960,000 to fund the costs of the project, to include the necessary fees & surveys to progress the project through RIBA Stages 4 Technical Design, Stage 5 Construction and Stage 6 Handover; 4. to note that the Medium-Term Financial Plan will need to be adjusted to include an additional minimum revenue pressure of up to £603,500 per annum from 2026/27 onwards to cover the costs of borrowing relating to the project; and 5. to authorise Officers, with the oversight of the Major Programmes Member Reference Group, to undertake the following actions: ( i ) submit an application for planning consent and secure any other regulatory consents necessary to implement the project; (ii) commission further design and professional services to enable the project to progress through to practical completion, including RIBA Design Stages 4 -6; (iii) undertake a procurement and appoint a main works contractor for the project subject to a ... view the full minutes text for item 149.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Policy and Resources Committee, 21 pages
Recommendation
That the Committee –
1.1Notes the contents of the report including the progress made up to and including RIBA Design Stage 3, the appointment of a cremator manufacturer, the feedback from consultation and the development of the project cost estimate and risk register;
1.2Agrees that, considering the affordability of the current cost estimate, the Council should now proceed with design Scheme C as set out in the report, comprising cremator replacement and related works along with chapel and chapel entrance refurbishment;
1.3Recommends to Council an adjustment to the capital programme of up to £6,960,000 to fund the costs of the project, to include the necessary fees & surveys to progress the project through RIBA Stages 4 Technical Design, Stage 5 Construction and Stage 6 Handover;
1.4Notes that the Medium-Term Financial Plan will need to be adjusted to include an additional minimum revenue pressure of up to £603,500 per annum from 2026/27 onwards to cover the costs of borrowing relating to the project;
1.5Authorises officers, with the oversight of the Major Programmes Member Reference Group, to undertake the following actions:
1.6(i) submit an application for planning consent and secure any other regulatory consents necessary to implement the project;
(ii) commission further design and professional services to enable the project to progress through to practical completion, including RIBA Design Stages 4 -6;
(iii) undertake a procurement and appoint a main works contractor for the project subject to a maximum budget of £2,674,000 (ex VAT);
(iv) take all necessary steps to bring to project to a successful completion, subject to there being no material change to the agreed parameters of the project budget, design scheme and anticipated risks as set out in this report. 2. Background
2.1In May 2024 Policy & Resources Committee approved the business case to support the procurement of 2 new electric cremators and recommended to Council an adjustment to the capital programme of up to £5,500,000 to cover the cost of electric cremator replacement and necessary fees & surveys to progress and conclude RIBA Stage 3 Design.
2.2As well as the electric cremator replacement works the scope referred to as ‘Back Of House’ also included associated cremator installation enabling works, cremator hall remodelling, new increased power supply, and Salix eligible grant work including a new heat exchange system for the crematorium building.
2.3This committee noted that the Medium-Term Financial Plan would need to be adjusted to include an additional minimum revenue pressure of up to £300,000 per annum from 2026/27 onwards to cover the costs of borrowing relating to the recommendation in May 2024 as set out in 2.1 above.
2.4Replacement of the existing cremators and ‘Back of House’ works formed part of a broader and aspirational capital project that sought to improve the public facing areas of the crematorium with an extension and significant refurbishment throughout. These works referred to as ‘Front of House formed part of two previous reports presented to Environment Committee on this project (March 2023 & July 2023).
2.5These and the report in May 24 noted the extent of the works to both the ‘Back & Front of House’ would be considered during RIBA Stage 3. Any proposed works would need to recognise and be informed by a comprehensive suite of site and building surveys and intrusive investigations. This information would help to inform the developing design and associate cost estimates.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.