Resolved
That the Committee approve the Internal Audit Plan for 2025/26 without amendments.
Audit and Governance Committee approved this item on Tuesday 17 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee approve the Internal Audit Plan for 2025/26 without amendments.
1.1The Internal Audit Plan for 2025/26 be approved, with or without amendments.
2.1The aims and objectives of the Worcestershire Internal Audit Shared Service are to:
• examine, evaluate and report on the adequacy and effectiveness of internal control, governance and risk management across the council and recommend arrangements to address weaknesses as appropriate; • examine, evaluate and report on arrangements to ensure compliance with legislation and the council’s objectives, policies and procedures; • examine, evaluate and report on procedures to check that the council’s assets and interests are adequately protected and effectively managed; • undertake independent investigations into allegations of fraud and irregularity in accordance with council policies and procedures and relevant legislation; and • advise upon the control and risk implications of new systems or other organisation changes, e.g. transformation.
2.2Formulation of the Annual Plan
WIASS operates an Internal Audit Charter which sets out the standards to which it operates for this Council. The Internal Audit Plan for 2025/26, which is included at Appendix 1, is a risk-based plan which considers the adequacy of the Council’s risk management, governance, performance management, other assurance processes as well as organisational objectives and priorities. It has been based upon the risk priorities per the Corporate and Service risk registers. Large spend budget areas have also been considered, along with alignment to the City Plan. The Internal Audit Plan for 2025/26 has been agreed with the s151 Officer and Corporate Leadership Team and is brought before Committee in draft form. It has been formulated with the aim of supporting the Council to meet its strategic purposes, delivers it’s promises and has directly linked the various aspects to identify the ‘golden thread’ regarding the objectives and risk identification to service delivery. It is brought before the Audit and Governance Committee in draft format as the involvement of the Committee is considered an important facet of good corporate governance, contributing to the internal control assurance given in the Council’s Annual Governance Statement. 2.3 Internal Audit recognises that there are other review functions which may provide other sources of assurance, both internally and externally, (e.g. Cyber Essentials, external audit testing) over aspects of the Council’s operations. Where possible internal audit will seek to place reliance on such work thus increasing the coverage without adding additional costs.
2.4By bringing a plan of work before the Audit and Governance Committee it allows Members to have a positive input into the audit work programme and make suggestions as to where they feel audit resources may be required under direction of the s151 Officer and within the finite resource available. Due to the continuing changing environment that exists in Local Government the plan must be seen as a framework for internal audit work for the forthcoming year. There is a need for improved flexibility in the plan due to a constantly changing risk profile. To ensure flexibility there is the possibility that the plan will be updated during the year to address such challenges and any emerging risks. It is planned that a regular review will take place to ensure the audit plan remains risk focussed, and any required changes can be considered. This is in line with the requirements of the Global Internal Audit Standards (GIAS). Any changes will be submitted to the Audit and Governance Committee for consideration and approval, in line with its role as Gatekeeper.
2.5Resource Allocation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Plan 2025-26Appendix 1 | 4 pages | Download |
PDF |
Internal Audit Plan For 2025/26Report | 3 pages | DownloadRead as text |
Follow Audit and Governance Committee at Worcester and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | MinutesThat the of the meeting held on 17 th March 2026 be approved as a correct record and signed by the Chair. | Approved | Open |
| 16 Jun 2026 | External Audit Plan 2025/26That the Committee agree to note the External Audit Plan for 2025/26. | Agreed | Open |
| 16 Jun 2026 | Item Involving The Disclosure of Exempt InformationThat under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting for th... | Decided | Open |
| 16 Jun 2026 | Corporate Risk Management Report - Quarter 4, 2025-26That the Committee agree to note the updated assessment of corporate risks at the end of Quarter 4 as shown in the la... | Agreed | Open |
| 16 Jun 2026 | Treasury Management Annual Report 2025/26That the Committee: 1. agree to note the 2025/26 Annual Report; 2. agree to refer the Annual Report to full Council f... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.