Place and Economic Development Committee, Monday 3 November 2025 at 7.00pm

Infrastructure Funding Statement 2025 for Monitoring Period 1st April 2024 - 31st March 2025

Noted Committee 2 papers

AI summaryWorcester City Council's Place and Economic Development Committee noted the 2024/25 Infrastructure Funding Statement for publication, covering £592,275 in CIL receipts and £207,011 in new S106 contributions.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee noted IFS for monitoring period 1 April 2024 to 31 March 2025
Money£207,011 S106 received in 2024/25Plus £599,320 S106 spent; £144,000 CIL spent on Splashpad
What happens nextPublish IFS on council websiteStatement to be made publicly available online
Who it affectsDevelopers, residents, parish councilsAll parties affected by CIL and S106 planning obligations

What was decided

The Committee noted the Infrastructure Funding Statement for the monitoring period 1 April 2024 to 31 March 2025.

The statement is to be published on the Council's website.

Why

Legislation introduced in 2019 requires local authorities to produce an Infrastructure Funding Statement on an annual basis. Report P8

The IFS sets out income and expenditure relating to Community Infrastructure Levy and Section 106 agreements, showing how developer contributions fund infrastructure from new development. Report P8, P9

What happens next

The Infrastructure Funding Statement will be published on the Council's website. Report P3

The S106 Programme Board will continue to meet quarterly to review and allocate developer contributions, with projects over £50,000 requiring Committee approval. Report P51, P101

Primary focus for CIL allocation over the coming year will be delivery of the Worcester City Play Plan. Report P99

The money

  • £592,275 CIL collected by Worcester City Council since 2021/22 Report P12, P29
  • £294,000 CIL allocated towards Gheluvelt Park Splashpad refurbishment Report P12
  • £106,000 CIL allocated towards costs of a Project Delivery Officer Report P12
  • £192,275 Remaining CIL allocated to other elements of the Council's Play Plan Report P12
  • £207,011 S106 monies received from developers in 2024/25, all in public open space contributions Report P14, P45, P50
  • £144,000 CIL spent in 2024/25 towards Gheluvelt Park Splashpad refurbishment Report P33
  • £150,000 Remaining Splashpad allocation at start of 2025/26 Report P33
  • £289,244 Allocated towards construction of Kepax Bridge (Active Travel projects) Report P17
  • £73,251 Allocated towards refurbishment of St Andrews Gardens Report P17
  • £71,865 Allocated towards refurbishment of Gheluvelt Park Splashpad Report P17
  • £1,582,685 S106 balance carried forward at 1 April 2024, including £32,364 for long term maintenance Report P59
  • £592,995 S106 spent in 2024/25 on infrastructure projects from carried forward funds Report P60
  • £1,197,392 S106 balance carried forward as of 1 April 2025 Report P61
  • £599,320 Total S106 expenditure in 2024/25 Report P49, P88, P94
  • £8,000 Myriad Centre S106 contribution towards Residents' Parking Scheme in Henry Street Report P40
  • £87,500 St Clement's Church Hall transport contribution to County Council Report P41
  • £1,300 S106 monitoring fees collected in 2024/25 from 2 new agreements Report P78

Options considered

  • Chosen: Note the Infrastructure Funding Statement for publication. Required to comply with annual IFS publication duties under the 2019 regulations Report P8

Implications

  • Financial: Council received £207,011 in S106 contributions in 2024/25 but spent £599,320 from existing balances, primarily on open space projects like Kepax Bridge and Gheluvelt Splashpad refurbishment. Report P45, P88, P89
  • Financial: A balance of £1,197,392 in S106 monies is carried forward to 2025/26, with £67,725 still unallocated to specific projects. Report P61
  • Legal: Most S106 agreements include a 10-year spending timeframe, after which unspent funds must be returned to developers with interest. Report P51, P76
  • Other: Two S106 agreements signed in 2024/25 included 44 affordable housing units delivered (both 100% affordable developments), though no new S106 agreements in this period included affordable housing. Report P43, P83
  • Other: No CIL receipts were collected during 2024/25; the four CIL liable approvals since introduction include one exempt as a registered charity development. Report P26

Who and where

  • Developers and landowners who have entered into S106 agreements with the Council Report P37, P40, P41
  • Worcestershire County Council, which receives transport and education S106 contributions directly Report P41, P75
  • Parish councils, who receive 15% (or 25% with neighbourhood plan) of CIL receipts from development in their area Report P29
  • Residents benefiting from infrastructure projects funded by developer contributions, including play areas, open space, and active travel schemes Report P9, P61
  • Affordable housing tenants, with 44 affordable units delivered in 2024/25 Report P83

Timeline

  • 16 May 2017: CIL Charging Schedule adopted by Worcester City Council Report P19
  • 4 September 2017: CIL Charging Schedule implemented in Worcester Report P19
  • 1 April 2024 to 31 March 2025: IFS monitoring period covered by the report Report P2
  • 2019: Legislation introduced requiring annual Infrastructure Funding Statements Report P8
  • 23 December 2024: £207,011 received from Taylors Lane development as Open Space contribution Report P55
  • 1 April 2025: S106 balance of £1,197,392 carried forward into 2025/26 Report P61

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a tariff-based charge on new development floorspace used to fund infrastructure
  • S106: Section 106 agreements, legal agreements linked to planning applications to mitigate development impacts
  • IFS: Infrastructure Funding Statement, an annual report on CIL and S106 income and expenditure
  • SWDP: South Worcestershire Development Plan, the planning policy framework for the area
  • MUGA: Multi-Use Games Area, a sports facility for various activities
  • LAHF: Local Authority Housing Fund, a programme for providing affordable housing
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

That the Committee note the Infrastructure Funding Statement for the monitoring period 1 st April 2024 to 31st March 2025 for publication on the Council’s website.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 20 pages

Infrastructure Funding Statement 2024/2025

Worcester City Council Infrastructure Funding Statement 2024/25 For the Monitoring Period 1 April 2024 – 31 March 2025

Published ………

15 Infrastructure Funding Statement 2024/2025

Contents 1. Introduction ............................................................................................................................... 2 1.1. Key Headlines from the IFS ............................................................................................... 2 1.2. Community Infrastructure Levy (CIL) and Section 106 (S106) Agreements...................... 3 2. Community Infrastructure Levy ................................................................................................. 4 2.1. CIL Income in Worcester City ............................................................................................ 4 2.2. CIL Expenditure ................................................................................................................. 5 3. Section 106 Agreements, Collection and Expenditure 2024/25 ................................................ 5 3.1. Notable S106 Agreements Signed ..................................................................................... 5 3.2. Overview of Signed S106 Agreements .............................................................................. 6 3.3. S106 Contributions Received 2024/25 .............................................................................. 6 3.4. S106 Contributions Carried Forward from Previous Years ............................................. 10 3.5. S106 Contributions Transferred ...................................................................................... 15 3.6. S106 Contributions Returned to Developers .................................................................. 15 3.7. S106 Contributions Monitoring Fees .............................................................................. 15 3.8. Non-financial S106 contributions: Affordable Housing .................................................. 15 3.9. Financial S106 contributions: Affordable Housing .......................................................... 16 3.10. S106 Spending ................................................................................................................. 17 4. Governance Arrangements and Spending Priorities ............................................................... 18 4.1. CIL Governance and Spending Priorities ......................................................................... 18 4.2. S106 Governance and Spending Priorities ...................................................................... 18

1 Infrastructure Funding Statement 2024/2025

1. Introduction

The Infrastructure Funding Statement (IFS) sets out the income and expenditure relating to Community Infrastructure Levy (CIL) and Section 106 (S106) agreements for Worcester City Council. Legislation changes introduced in 20191 require Local authorities to produce an IFS on an annual basis.

CIL and S106 income, referred to as planning obligations or developer contributions, are used to help fund the provision of supporting infrastructure arising from new development and to maximise the benefits and opportunities from growth, whether that is from new housing, employment or other types of specific development. Section 2 of this report sets out the applications from which CIL has been collected in the City. Section 3 sets out the S106 agreements entered into during the monitoring period, including the type and financial value of these agreements. Details are provided of the contributions received by the Council along with the money that has been allocated and spent on projects in the City during the monitoring year. Section 4 explains the process of identifying appropriate projects to allocate S106 contributions to and how the Council will identify spending priorities. 1.1. Key Headlines from the IFS

In 2024/25 the headline figures are as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IFS 2024-25 FINALReport 20 pages DownloadRead as text
PDF
Infrastructure Funding Statement 2025 for Monitoring Period 1st April 2024: 31st March 2025Report 2 pages Download

At this meeting

Whole meeting

Who was there

10 of 13 attended
MA
Councillor Mel AllcottCommittee Member, present
JB
Councillor Jenny BarnesCommittee Member, present
KC
Councillor Katie CollierCommittee Member, present
HC
Councillor Hannah CooperVice-Chair, present
JD
Councillor Jill DesayrahCommittee Member, present
AG
Councillor Adrian GregsonCommittee Member, apologies
JJ
Councillor Jessie JaggerCommittee Member, in attendance
EK
Councillor Ed KimberleyCommittee Member, present
AM
Councillor Alex MaceCommittee Member, in attendance
RN
Councillor Robyn NorfolkChair, present
TP
Councillor Tor PingreeCommittee Member, present
ER
Councillor Elena RoundCommittee Member, present

All 13 on the meeting page

On this subject at Worcester

Search all
  1. Infrastructure Funding Statement 2025 for Monitoring Period 1st April 2024 - 31st March 2025This decision
  2. Infrastructure Funding Statement 2023 for the monitoring period 1st April 2022 - 31st March 2023Noted
  3. Infrastructure Funding through PlanningNoted
  4. Infrastructure Funding Statement 2022 for the monitoring period 1st April 2021 - 31st March 2022Noted
  5. Infrastructure Funding Statement 2021 for the Monitoring Period 1st April 2020 - 31st March 2021Noted
  6. Infrastructure Funding Statement 2020 for the Monitoring Period 1st April 2019-31st March 2020Noted

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies