Place and Economic Development Committee, Monday 3 November 2025 at 7.00pm

Quarter 1 and 2 Performance Report for 2025/26

Noted Committee 2 papers

AI summaryWorcester City Council's Place and Economic Development Committee noted the Q1 and Q2 2025/26 performance report and agreed to push back the Economic Development Strategy to August 2026 and the City Centre Transport Action Plan to March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedEconomic Development Strategy to August 2026, Transport Plan to March 2026
MoneyNot stated
What happens nextBackground report to committee in January 2026For the Economic Development Strategy
Who it affectsBusinesses, residents and visitors to WorcesterThrough town centre, planning, transport and culture projects

What was decided

The Committee noted the quarter 1 and quarter 2 performance report for 2025/26.

The Committee agreed to amend the due date for the Economic Development Strategy to August 2026. Report P18

The Committee agreed to amend the due date for the City Centre Transport Action Plan to March 2026. Report P19

Why

The Economic Development Strategy was initiated in September 2025, with a background report due to the Committee in January 2026 and completion of the strategy and a further report scheduled for Summer 2026. Report P15, P16, P17, P18

The City Centre Transport Action Plan is awaiting a response from the County Council chief executive on a draft transport strategy being presented to County Cabinet, so a later due date is proposed. Report P19

What happens next

Background report on the Economic Development Strategy to go to the PED Committee in January 2026, with completion of the strategy and report to the Committee in Summer 2026. Report P16, P17

Main Modifications to the South Worcestershire Development Plan to be consulted on later in 2025 or early 2026 to make the plan sound and legally compliant. Report P29

The Worcester Show Project Board will review the final budget out-turn and carbon footprint to feed into next year's planning. Report P22

Options considered

  • Chosen: Amend the Economic Development Strategy due date to August 2026. Allows time for member, business and stakeholder engagement before completion and report to PED in Summer 2026. Report P15, P16, P17, P18
  • Chosen: Amend the City Centre Transport Action Plan due date to March 2026. Officers are still waiting for a response from the County Council chief executive on the draft transport strategy before it goes to County Cabinet. Report P19

Implications

  • Financial: Coach parking changes and Park & Ride costs will create a budget pressure for Worcester Victorian Fayre; the Project Board is monitoring this and seeking to reduce it. Report P24
  • Legal: Officers are working on Main Modifications to the South Worcestershire Development Plan to ensure it is sound and legally compliant, following the Inspectors' second Post Hearing Letter of 7 October. Report P28, P29
  • Risk: Worcester City currently has a 2.37 year housing land supply against a five year target of 552 dwellings per annum; the Inspectors confirmed that a five year supply with a 5% buffer should be achievable on adoption. Report P66, P67, P28
  • Risk: Recruitment and skills shortages, access to funding, marketing and premises availability were the main challenges reported by businesses. Report P52

Who and where

  • Worcester city centre businesses, visitors and residents affected by regeneration and public realm works Report P4, P5, P26
  • Local businesses receiving support through UK Shared Prosperity Fund programmes Report P12, P13, P14, P32, P33, P49, P50
  • Museum visitors to the Commandery and the Art Gallery and Museum Report P7, P9, P10, P55, P56
  • Planning applicants and those affected by housing and employment land delivery Report P44, P45, P65, P66, P67, P68, P69, P70, P71
  • Cyclists and pedestrians using the Beryl Bike Share Scheme and new active travel routes Report P21

Timeline

  • 3 Nov 2025: Contract award for the Perdiswell Pump Track is due to be published. Report P25
  • Jan 2026: Background report on the Economic Development Strategy to go to PED Committee; annual city centre footfall figures to be reported. Report P16, P48
  • 5 Jan 2026: Perdiswell Pump Track contractor due to start on site. Report P25
  • Feb 2026: Target completion of Perdiswell Pump Track, with 31 March 2026 as a backstop if winter weather delays groundworks. Report P25
  • 31 Mar 2026: New due date for the City Centre Transport Action Plan. Report P19
  • Summer 2026: Completion of the Economic Development Strategy and report to PED Committee. Report P17
  • Aug 2026: Proposed revised due date for the Economic Development Strategy project. Report P18
  • 2027: New 2 new Worcestershire Soldier exhibition at the Mercian Regiment Museum Worcestershire due to open. Report P8, P9

Plain English for the jargon

  • UKSPF: UK Shared Prosperity Fund, a central government fund for local growth.
  • SWDP / SWDPR: South Worcestershire Development Plan (Review), the local plan covering Worcester City, Malvern Hills and Wychavon.
  • LPA: Local Planning Authority, here Worcester City Council.
  • RAG: Red, Amber, Green status used to rate performance against targets.
  • BID: Business Improvement District, providing footfall and empty units data.
  • WCT: Worcester Community Trust, a partner on community skills projects.
  • MAG: Museum and Art Gallery, Worcester's city museum site.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

That the Committee: 1. note the quarter 1 and quarter 2 performance report for 2025/26; and 2. agree the amendment of the due date for the Economic Development Strategy and City Centre Transport Action Plan.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Place and Economic Development Committee, 16 pages

Appendix 1

Place & Economic Development Performance Report

PED Projects & Actions 2025/26

Future High Streets Fund - Public Realm The remaining works on Angel Street are now programmed Sponsor Sian Stroud to be undertaken towards the end of the Scala works, this is Due Date 31-Mar-2027 to ensure that no conflict occurs with two contractors on site nor damage to newly laid surfaces. Original Due 31-Mar-2025 Date Current Status Expected Outcome

Future High Streets Fund - Angel Place The delivery of the works will come towards the end of the Sponsor Sian Stroud Scala development, as has been indicated previously, as the Due Date 31-Mar-2027 site compound currently occupies a significant area of the northern section of Angel Place. Original Due 31-Mar-2025 Date Initial considerations will be given towards protective Current Status measures to ensure that the space by the Scala is protected and available for use by the future users/events. Initial Expected Outcome surveys have been undertaken which will inform the works.

Town Investment Plan - Heritage and Riverside Destinations Works at the Cathedral are complete with the exception of Sponsor David Blake interpretation and wayfinding infrastructure. All areas are Due Date 31-Dec-2026 open and fully operational, and the Town Investment Plan element of the overall project is therefore complete. Original Due 31-Mar-2025 Date St Andrews Gardens landscaping works are substantially Current Status complete. There is some snagging in terms of establishment of new turf which has not been possible due to weather Expected Outcome conditions during the drought. A handrail to the steps is yet to be installed.

The Museums project has created a new shop and reception at the Commandery as well as a new gallery space that is hosting an interim spotlight exhibition on Victorian Worcester. Preparation is underway for a new British Impressionism Gallery at the Art Gallery and Museum.

Building on the Town Investment Plan project the Council is supporting the Mercian Regiment Museum Worcestershire and the Worcestershire Yeomanry Trust to develop their

2 new Worcestershire Soldier exhibition for this space due to open in 2027 supported by a significant grant by the National Lottery Heritage Fund.

The refurbishment of the Art Gallery & Museum permanent art gallery is underway.

Towns Investment Plan - Community Skills Works to WCT reception areas and BB2 are complete. Sponsor Sian Stroud Due Date 31-Mar-2026 St Peters Village Hall and Fairfield are nearing completion. Original Due 31-Mar-2024 The contingency fund is being developed in line with the Date projects identified within July 2025 P&R report. Current Status Expected Outcome

UKSPF - Community and Place In 2025, due to the Council’s financial position, allocations Sponsor Sian Stroud of UKSPF were made to support larger community Due Date 31-Mar-2026 organisations which had previously been funded through Council base budget. Original Due 30-Mar-2025 Date A separate small grants scheme for community and arts was Current Status established. This is the subject of a separate report on the Committee’s agenda. Expected Outcome

UKSPF - Local Business This is the subject of a separate report on the Committee’s Sponsor Sian Stroud agenda. Due Date 31-Mar-2026 Original Due 30-Mar-2025 Date Current Status Expected Outcome

3 UKSPF - People and Skills Projects are being delivered through funding of Sponsor Sian Stroud Due Date 31-Mar-2026 • Worcestershire Growth Hub • Worcestershire County Council - Careers Worcestershire Original Due 30-Mar-2025 • Worcester Community Trust - Life Skills Date Current Status Expected Outcome

Economic Development Strategy Project initiated in September 2025. Project plan nearing Sponsor Sian Stroud completion. Due Date 31-Mar-2026 Project Plan to include member engagement, business Original Due 30-Jun-2023 engagement and other key stakeholders including BID, Date Growth Hub, Chamber of Commerce. Current Status

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
202526 Q2 PED Performance Final2Report 16 pages DownloadRead as text
PDF
Quarter 1 and 2 Performance Report for 2025/26Report 2 pages Download

At this meeting

Whole meeting

Who was there

10 of 13 attended
MA
Councillor Mel AllcottCommittee Member, present
JB
Councillor Jenny BarnesCommittee Member, present
KC
Councillor Katie CollierCommittee Member, present
HC
Councillor Hannah CooperVice-Chair, present
JD
Councillor Jill DesayrahCommittee Member, present
AG
Councillor Adrian GregsonCommittee Member, apologies
JJ
Councillor Jessie JaggerCommittee Member, in attendance
EK
Councillor Ed KimberleyCommittee Member, present
AM
Councillor Alex MaceCommittee Member, in attendance
RN
Councillor Robyn NorfolkChair, present
TP
Councillor Tor PingreeCommittee Member, present
ER
Councillor Elena RoundCommittee Member, present

All 13 on the meeting page

On this subject at Worcester

Search all
  1. Quarter 1 and 2 Performance Report for 2025/26This decision
  2. Quarter 4 and Annual Key Performance Indicator Report for 2025/26Agreed
  3. Quarter 4 and Annual Performance Report for 2025/26Noted
  4. Quarter 4 and Annual Performance Report for 2025/26Agreed
  5. Quarters 2 and 3 Performance Report 2025-26Decided
  6. Quarter 3 Performance Report For 2025/26Agreed

More from Worcester Place and Economic Development Committee

All decisions
MeetingDecisionOutcome
16 Mar 2026 MinutesThat the minutes of the meeting held on 26 th January 2026 be approved as a correct record and signed by the Chair. Approved Open
16 Mar 2026 Review of the Shrub Hill Quarter Supplementary Planning DocumentThat the Committee: 1. approves the draft Shrub Hill Quarter Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of the Air Quality Supplementary Planning DocumentThat the Committee: 1. approves the draft Air Quality Supplementary Planning Document, as set out in appendix 1, for ... Approved Open
16 Mar 2026 Review of the Affordable Housing Supplementary Planning DocumentThat the Committee: 1. approves the draft Affordable Housing Supplementary Planning Document, as set out in appendix ... Approved Open
16 Mar 2026 Review of A Guide to Shopfronts and Signage Supplementary Planning DocumentThat the Committee: 1. approves the draft Shopfronts Guide Supplementary Planning Document, as set out in appendix 1,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies