AI summaryWorcester City Council's Policy and Resources Committee agreed to act as Accountable Body for up to £20million of Government Pride in Place funding for Warndon West over 10 years, delegating authority to set up a community board and begin engagement work.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelegations approved for Pride in Place setup
MoneyUp to £20million over 10 yearsPlus £150,000 capacity funding received
What happens nextCommunity engagement Jan to Apr 2026Plan to be submitted by 28th November 2026
Who it affectsWarndon West community and businessesWarndon and Elbury Park ward
What was decided
The Council will act as Accountable Body for the Phase 2 Pride in Place funding for Warndon West and will establish a community-led Neighbourhood Board to decide how the money is spent. Report 1.1, 2.9, P22
Authority was delegated to the Managing Director, in consultation with the Committee Chair, Vice Chairs and the local MP, to finalise the Board's terms of reference, recruit a Chair and members, and to amend the programme area boundary if needed. Report 1.2, 1.3, 2.21
The Committee approved community engagement and public consultation ahead of the Board's establishment, and delegated authority to accept the grant and to spend the initial capacity funding on setup, engagement and plan development. Report 1.4, 1.5, 1.6, P56
Why
Government selected Warndon West as a Phase 2 Pride in Place Area because of its high levels of deprivation and weak social infrastructure, offering up to £20million of long-term investment over 10 years. Report 2.1, 2.2, 2.27
The Council has a formal role as Accountable Body for the funds until delivery can move to a community-led model by year three, and it must ensure funds follow the Nolan Principles, Equality Act 2010 and Managing Public Money rules. Report 2.9, 2.10, 2.11
Officers said delegations are needed because of tight programme deadlines, with the Pride in Place Plan due to Government by 28th November 2026. Report 3.1, P62
What happens next
Community engagement and consultation will run from January to April 2026, including a letter and survey to every property, a website, social media, pop-up events and stakeholder data mapping. Report P36, P37, P38, P42, P57
A Neighbourhood Board Chair and members will be recruited in May 2026, with the Board established in June 2026, supported by a State of Warndon Report. Report 2.26, P58, P59, P60
Board membership, Chair and any boundary change must be confirmed to MHCLG by 17th July 2026, with the Pride in Place Plan due by 28th November 2026 and a further report to this Committee in the Autumn before submission. Report P61, P62
The money
up to £20million total Phase 2 funding per area over 10 years Report 2.1, 2.27
£12.47million capital funding for Warndon West over 10 years Report P71, 2.27
£7.19million revenue funding for Warndon West over 10 years Report P71, 2.27
£150,000 capacity payment received week commencing 26th January 2026 Report 2.28, P72
£135k 50% of 2026/27 revenue funding, released April 2026 Report P74
£120k 2026/27 capital payment at start of financial year Report P74
Options considered
Chosen: Accept the funding and act as Accountable Body with multiple delegations to the Managing Director (preferred option). Needed to meet tight plan submission deadline of 28th November 2026 and use existing council resources to start engagement Report 3.1, 4.3
Rejected: Decline the Pride in Place funding. Warndon West is an area of significant disadvantage with extremely limited funding historically Report 4.1
Rejected: Devolve full early-phase delivery to the community. The Council has a formal accountable body role until handover is agreed by MHCLG, and timelines are too tight without council support Report 4.2, 4.3
Implications
Financial: Up to £20million of investment over 10 years, with spending rules including spending at least 25% of each investment period's allocation and 50% of the cumulative total by end of year 7 (2032/33). Report P71, P76, P77
Legal: The Council has legal responsibility for subsidy control, state aid and procurement, and must ensure funds are managed under the Nolan Principles, Equality Act 2010 and Public Sector Equality Duty. Report 2.10, 2.18
Risk: Tight timescales for plan submission by 28th November 2026; risk of community expectations on speed of delivery after Spring/Summer 2026 consultation; risk of council resourcing and programme management costs over 10 years. Report P82, P83, P84
Equalities: No equality implications identified at this early stage; engagement will use a range of traditional and non-traditional methods to reach as many residents and businesses as possible. Report P87, P88
Staffing: Senior sponsorship, programme management support and financial oversight will be required throughout the 10-year programme, and the fund allows additional capacity to be resourced. Report P85, P90, P91
Other: Interventions and themes cut across all priority themes of the Worcester City Plan 2025 to 2030. Report 5.4
Who and where
Residents, businesses and community organisations in the Warndon West MSOA (4 LSOAs covering Warndon and Elbury Park ward) Report 2.5, 2.6, P96
Worcester City Council as Accountable Body for the funding Report 2.9, P22
The local MP, ward councillors, Worcester Community Trust and Worcestershire County Council members of the working group Report 2.21
Key stakeholders including Worcester City Primary Care Network, West Mercia Police and existing community forums and groups in Warndon West Report P40, P41
Timeline
3rd December 2025: Phase 2 Pride in Place Prospectus published Report 2.4
Week commencing 26th January 2026: Council received £150,000 capacity payment Report P56, P72
January to April 2026: Community engagement and consultation, including engagement with key stakeholder organisations Report P57
March to April 2026: Commence engagement events for Neighbourhood Board membership Report P58
May 2026: Neighbourhood Board Chairperson and Member recruitment process Report P59
June 2026: Establish Neighbourhood Board and develop initial Board Work Programme (June to November 2026) Report 2.26, P60
17th July 2026: Each area to confirm Board arrangements (membership, Chair) and any proposal to alter default boundary Report P61
28th November 2026: Each area to submit Pride in Place Plan to MHCLG for review and approval Report P62
Spring 2027: MHCLG to approve Pride in Place Plans and first substantive delivery funding payment to be made (commencement of delivery phase) Report P63
2026/27 to 2035/36: 10-year investment period for the programme Report 2.27
Plain English for the jargon
MSOA: Middle Layer Super Output Area, an ONS census geography with between 5,000 and 15,000 residents, used as the default programme area boundary
LSOA: Lower Super Output Area, a smaller sub-ward unit of 1,000 to 3,000 residents; four LSOAs make up the Warndon West MSOA
MHCLG: Ministry of Housing, Communities and Local Government, the UK Government department running the Pride in Place programme
Accountable Body: The organisation with legal responsibility for ensuring public funds are properly distributed and managed in line with statutory rules
s151 Officer: The Council's statutory chief finance officer, responsible for the proper administration of the Council's financial affairs
PiP: Pride in Place, a UK Government long-term neighbourhood investment programme
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item66
Resolved
That the Committee agree to: 1. note the contents of the report, and in particular the announcement by Government of Warndon West being chosen as a Phase 2 Pride in Place Area and the Council’s role as Accountable Body for the funding allocation for this programme; 2. delegate authority to the Managing Director in consultation with the Chair and Vice Chairs of this Committee and the MP for Worcester to finalise the “Pride in Warndon West” Board Terms of Reference and to support the recruitment to the Board Chair and Board Membership in accordance with Government guidance and requirements; 3. delegate authority to the Managing Director in consultation with the Chair and Vice Chairs of this Committee, the MP for Worcester and the Pride in Warndon West Board, to make any necessary representation to Government to amend the default geographic boundary for the programme area if required; 4. approve that community engagement and public consultation be undertaken in relation to the Pride in Place Programme ahead of the establishment of the Pride in Wardon West Board; 5. delegate authority to the Managing Director and the s151 Officer, to accept the terms of any grant agreement for the Pride in Place funding from Government; 6. delegate authority to the Managing Director to authorise spend of any initial capacity funding from Government for the purposes of establishing the Board, undertaking community engagement, developing the Pride in Place Plan, programme management, technical expertise for project development and any other activities deemed necessary in accordance with government guidance; and 7. ... view the full minutes text for item 66.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
Report to Policy and Resources Committee, 10 pages
Recommendation
That the Committee:
1.1Notes the contents of the report, and in particular the announcement by Government of Warndon West being chosen as a Phase 2 Pride in Place Area and the Council’s role as Accountable Body for the funding allocation for this programme;
1.2Delegates authority to the Managing Director in consultation with the Chair and Vice Chairs of this Committee and the MP for Worcester to finalise the “Pride in Warndon West” Board Terms of Reference and to support the recruitment to the Board Chair and Board Membership in accordance with Government guidance and requirements;
1.3Delegates authority to the Managing Director in consultation with the Chair and Vice Chairs of this Committee, the MP for Worcester and the Pride in Warndon West Board, to make any necessary representation to Government to amend the default geographic boundary for the programme area if required;
1.4Approves that community engagement and public consultation be undertaken in relation to the Pride in Place Programme ahead of the establishment of the Pride in Wardon West Board;
1.5Delegates authority to the Managing Director and the s151 Officer, to accept the terms of any grant agreement for the Pride in Place funding from Government;
1.6Delegates authority to the Managing Director to authorise spend of any initial capacity funding from Government for the purposes of establishing the Board, undertaking community engagement, developing the Pride in Place Plan, programme management, technical expertise for project development and any other activities deemed necessary in accordance with government guidance; and 1.7 Notes that a further report will be brought to Committee, prior to any submission of the Pride in Place Plan to Government scheduled for the Autumn, in view of the Council’s responsibilities as Accountable Body.
Background
2.1In September 2025, the UK Government launched its Pride in Place (PiP) Phase 2 Programme, expanding on Phase 1 to provide an additional 169 neighbourhoods across the UK with up to £20million of investment (each) over 10 years.
2.2‘Warndon West’ has been selected as a Phase 2 area with selection focussed on those areas with the highest levels of deprivation and weakest social infrastructure. Further details of the Government’s methodology for the selection of places can be found here
2.3PiP is a UK wide programme aiming to invest in disadvantaged neighbourhood across the country. This long-term investment presents a significant opportunity for the Warndon West community to address their local priorities and make lasting, positive change for residents. The strategic objectives of the programme are set out below:
• To build stronger communities - All places should have strong relationships and a collective sense of belonging to their community. This helps bring people together to build community cohesion and resilience, helping people to feel proud of their area and safe in their neighbourhood.
• To create thriving places - Every part of the UK deserves to have vibrant neighbourhoods and communities with busy high streets, a good range of local amenities and high-quality physical infrastructure.
• To empower people to take back control - Talent is spread equally but opportunity is not. Everybody should be empowered and in control of their lives and have a say over the future of their community.
2.4A Phase 2 Pride in Place Prospectus was published on 3rd December 2025 and can be found here.
2.5The boundaries of each Phase 2 area are coterminous with an existing Middle Layer Super Output Area (MSOA). MSOAs are Office for National Statistics (ONS) census geographies with a resident population of between 5,000 and 15,000 people.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.