AI summaryWorcester City Council's Policy and Resources Committee agreed to delegate authority to spend £300k on early enabling works at the Corn Exchange, part of the Scala Arts Centre, with a full contract decision due in March 2026.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelegated to Managing Director
Money£300k from Cultural FundingUp to £300k on enabling works
What happens nextFull contract decision in March 2026Tender price report on 24 March
Who it affectsCorn Exchange, Scala Arts CentreCathedral ward town centre site
What was decided
Delegated authority to the Managing Director to instruct Speller Metcalfe Malvern Limited to carry out an enabling package of early works to the Corn Exchange in the sum of £300k, funded from the Cultural Funding allocation. Report 1.1
Noted the balance of risks in starting the enabling works before the final Contract Variation price is agreed. Report 1.2
Noted that the Committee is scheduled to decide on letting the full works contract in March, subject to acceptable final prices and terms. Report 1.3
Why
The Corn Exchange is an essential asset for the Scala Arts Centre's business model, providing the primary food and beverage offer and a flexible fourth studio space. Report 2.3, 3.3
The Government has specifically allocated Cultural Funding to the Corn Exchange, so commissioning early works keeps the project within that funding window. Report 2.1, 3.3
Delaying until a firm full price is known would push the Corn Exchange handover into early 2027, deferring Scala's opening and affecting income generation. Report 4.1, 2.9
What happens next
The contractor must be instructed on the early works by 27 February to keep the programme on track. Report 2.9
A formal tender for the full Corn Exchange works is expected from the contractor on 19 March 2026. Report 2.9
A further report will come to this Committee on 24 March once the tender price is available. Report 3.5
The money
£300k Maximum budget for enabling early works, delegated to Managing Director Report 1.1, 3.4
£1,724,690 Cultural Funding grant received for the Corn Exchange works Report P23, 5.1
£2.328m Total Cultural Funding allocation for additional Scala assets (Corn Exchange, 6 Angel Place, Angel Place outdoor infrastructure) Report 2.1
£250k-£300k Current estimate of the enabling early works package cost Report 2.10
Options considered
Chosen: Instruct the contractor to start the enabling early works now, within a £300k budget delegated to the Managing Director. Keeps the Corn Exchange handover aligned with the Scala building and avoids delaying Scala's opening Report 3.1, 3.2, 3.3, 3.4
Rejected: Delay instructing the early works until a firm full refurbishment price is known. Would push the Corn Exchange handover into early 2027, deferring Scala's opening and affecting income generation Report 4.1
Implications
Financial: The £300k enabling works will be funded from the £1,724,690 Cultural Funding grant for the Corn Exchange; full financial implications will be set out once tender prices are received. Report P23, P24, 5.1
Risk: Starting enabling works ahead of agreed final Contract Variation pricing creates a risk that overall costs may change; the works are intended to mitigate the risk of project delay. Report 1.2, P27
Legal: Builds on the Committee's earlier decision to allocate Cultural Funding to the Corn Exchange design work; further approval is sought to commission enabling works. Report P26, 5.2
Other: The Council and contractor must plan and undertake the works safely under the Health and Safety Act and the Construction (Design and Management) Regulations. Report 5.7, P34
Equalities: None arising from this decision. Report P30
Staffing: None arising from this decision. Report 5.6, P32
Who and where
Cathedral ward and the wider Worcester town centre Report P36
Scala Arts Centre charity, which depends on the Corn Exchange for its operating model Report 2.3, 2.8
Speller Metcalfe Malvern Limited, the contractor on the main Scala construction contract Report 1.1, 2.2
Timeline
26 March 2024: Planning permission and listed building consent granted for the Scala Arts Centre proposals, including the Corn Exchange
February 2025: Government confirmation of Cultural Funding grant for the Corn Exchange received, putting the desired programme at risk Report 2.7
15 July 2025: Earlier Committee report on development of additional Scala assets Report P37
16 December 2025: Last update to this Committee on the Future High Street Fund programme and Scala Report 2.1, P37
by 27 February: Deadline to instruct the contractor on the enabling works to keep the handover date Report 2.9
19 March 2026: Formal tender for the full Corn Exchange refurbishment works expected from the contractor Report 2.9
24 March: Further report to this Committee on tender price and full works contract Report 3.5
13 November 2026 at the earliest: Earliest possible handover of the Corn Exchange Report 2.9
Plain English for the jargon
Corn Exchange: A heritage building being refurbished as the primary food and beverage venue and flexible fourth studio for the Scala Arts Centre.
Scala Arts Centre: A council-led arts and entertainment venue project in Worcester town centre, part of the Future High Street Fund programme.
Cultural Funding: The grant scheme formerly known as Levelling Up funding, providing £2.328m to Worcester for additional Scala assets.
RIBA 4: Royal Institute of British Architects work stage 4, the detailed design stage; now completed for the Corn Exchange.
Contract Variation: An addition to the main Scala construction contract with Speller Metcalfe Malvern Limited to include the Corn Exchange works.
SMML: Speller Metcalfe Malvern Limited, the contractor holding the main Scala construction contract.
CDM Regulations: Construction (Design and Management) Regulations, setting health and safety duties for construction projects.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item65
Resolved
That the Committee agree to: 1. delegate authority to the Managing Director to instruct Speller Metcalfe Malvern Limited to undertake an enabling package of early works to the Corn Exchange in the sum of £300k, funded from the Cultural Funding allocation for this project; 2. note the balance of risks in undertaking an enabling package of work in advance of agreement of final pricing of the intended Contract Variation for the inclusion of the Corn Exchange; and 3. note that the Committee is scheduled to make the decision on letting the full works contract for the Corn Exchange in March, subject to acceptable final prices and terms being available from the contractor.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1Delegates authority to the Managing Director to instruct Speller Metcalfe Malvern Limited to undertake an enabling package of early works to the Corn Exchange in the sum of £300k, funded from the Cultural Funding allocation for this project;
1.2Notes the balance of risks in undertaking an enabling package of work in advance of agreement of final pricing of the intended Contract Variation for the inclusion of the Corn Exchange; and
1.3Notes that the Committee is scheduled to make the decision on letting the full works contract for the Corn Exchange in March, subject to acceptable final prices and terms being available from the contractor.
Background
2.1Members received an update on progress at the last meeting of this Committee in December 2025. This Committee has previously noted the Government’s confirmation of the Cultural Funding (formerly Levelling Up) allocation of £2.328m to support the development of additional assets for the Scala Arts Centre, namely the Corn Exchange, co-working space in 6 Angel Place and outdoor infrastructure in Angel Place.
2.2The main works construction contract on the Scala building, which the Council has entered into with Speller Metcalfe Malvern Limited (SMML), includes the provision to add additional works, subject to agreement by both parties. This Committee has previously approved the use of Cultural Funding expenditure to commission the further design work necessary on the additional assets (particularly the Corn Exchange) in order to enable these works to be effectively priced by the contractor.
2.3Members will be aware that the Corn Exchange is an essential asset for the sustainability of Scala Arts Centre’s business model. It will provide the primary food and beverage offer for Scala and is also being designed flexibly to become a “fourth studio” with space for events that can work in tandem or independently from the bar function. 2.4 Planning permission and listed building consent were granted on 26 March 2024 as part of the Scala Arts Centre proposals.
2.5The RIBA 4 detailed design for the Corn Exchange has now been completed and subject to client checking, it will be priced by the Contractor.
2.6As the Corn Exchange will be an integral part of the Scala Arts Centre and the viability of the business, it is important that its completion and handover is in line with handover of the Scala building.
2.7Members will be aware that the Government’s confirmation of Cultural Funding grant for the Corn Exchange was not forthcoming until February 2025 and this caused delay and put the desired programme at risk.
2.8The Council’s professional construction management team has worked with the contractor to map out the route to obtaining a final tender price and the contractor has provided a provisional build programme taking into account the need for the Corn Exchange to be available for use at the earliest opportunity by the Scala Arts Centre charity.
2.9Following the evaluation of quotations from the contractor’s supply chain, a formal tender will be submitted to the Council on 19 March 2026. However, handover of the Corn Exchange cannot happen before 13 November 2026 at the earliest and in order to achieve this date the contractor will need to be instructed at risk on an early package of enabling works by 27 February.
2.10The scope of these works consists of strip out, demolitions, structural alterations and design of scaffolding. The exact detail is being prepared and costed but will fall within the scope of existing Listed Building Consents and is estimated to be in the region of £250k- £300k.
3. Preferred Option
3.1The preferred option is to be able to instruct the contractor to progress with an early package of works so that the overall construction programme for the project remains in line with expectations, and a handover date for the Corn Exchange is not delayed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.