AI summaryWorcester City Council approves draft Developer Contributions Supplementary Planning Document for a five-week public consultation, with adoption expected by end of June 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDraft SPD goes to 5-week public consultation
MoneyNo significant costPreparation costs met from existing budgets
What happens nextPublic consultation then adoptionAdoption expected by end of June 2026
Who it affectsAll wardsDevelopers, applicants and planning decision makers
What was decided
The committee approved the draft Developer Contributions Supplementary Planning Document, set out in Appendix 1, for a five-week public consultation. Report 1.1, 3.1
The committee authorised the Head of Planning and Economic Development, in consultation with the Chair and Vice Chairs of the Policy and Resources Committee, to make any necessary minor amendments to the draft before publication. Report 1.2
Why
The SPD provides detailed guidance to support policies in the Local Plan and is a material consideration when determining planning applications. Report 2.1, 2.2, 2.6
The current Developer Contributions SPD was adopted in July 2018 against the South Worcestershire Development Plan 2016 and needs updating to align with the South Worcestershire Development Plan Review, expected to be adopted in Spring 2026. Report 2.3, 2.4
A government deadline of the end of June 2026 has been set for adoption of SPDs under the current plan making framework, leaving a limited window to review the document. Report 4.1
What happens next
Hold a five-week public consultation on the draft Developer Contributions SPD. Report 1.1, 2.4
The Head of Planning and Economic Development may make minor amendments to the draft before publication, in consultation with the Chair and Vice Chairs of the Policy and Resources Committee. Report 1.2
Adopt the SPD as a Supplementary Planning Document to the South Worcestershire Development Plan Review by the end of June 2026, subject to any required amendments. Report 2.4
Options considered
Chosen: Progress the Developer Contributions SPD to statutory public consultation. Aligns with government deadline of end of June 2026 and ensures the SPD remains a material consideration in planning decisions. Report 3.1, 4.1
Rejected: Do not continue with the preparation of the SPD. Limited window of opportunity to review the SPD before the end of June 2026 deadline set by Government. Report 4.1
Implications
Legal: The consultation on the SPD will meet the relevant legal and regulatory requirements for producing a Supplementary Planning Document. Report 5.2
Risk: Not producing and adopting the SPD risks the local planning authority being open to challenge on how developer contributions are sought, which could incur time and costs through planning appeals. Report 5.3
Staffing: Officer time will be required to administer the public consultation, review responses and make amendments, carried out using existing resources. Report 5.6
Other: The collection of developer contributions will help support infrastructure delivery, contributing to themes in the Council's City Plan including education facilities, affordable housing, green spaces, community facilities and active travel routes. Report P17
Equalities: There are no equality implications relating to the production and implementation of this SPD. Report 5.5
Financial: Once adopted, the SPD will help ensure sufficient funds are collected to help meet infrastructure requirements arising from new development. Report 5.1
Who and where
Developers, planning agents and applicants for planning permission in Worcester Report 2.5
Planning decision makers at Worcester City Council Report 2.2, 2.6
Residents of Worcester, who may benefit from infrastructure provided through developer contributions Report 5.8
Timeline
July 2018: Current Developer Contributions SPD adopted against the South Worcestershire Development Plan 2016 Report 2.3
Spring 2026: South Worcestershire Development Plan Review expected to be adopted at Council Report 2.4
5 weeks from publication: Public consultation on the draft Developer Contributions SPD Report 1.1, 2.4
end of June 2026: Expected adoption of the Developer Contributions SPD as a Supplementary Planning Document to the SWDPR, subject to any required amendments Report 2.4
end of June 2026: Government deadline for adoption of SPDs under the current plan making framework Report 4.1
Plain English for the jargon
Supplementary Planning Document (SPD): A document providing detailed guidance and support for policies in the Local Plan, which is a material consideration in planning decisions once adopted.
Section 106 agreement: A legal agreement under section 106 of the Town and Country Planning Act used to secure planning obligations from developers.
Section 278 agreement: An agreement under section 278 of the Highways Act used to secure works to the public highway as part of a development.
Section 38 agreement: An agreement under section 38 of the Highways Act for the adoption of new highways by the local authority.
Community Infrastructure Levy (CIL): A charge that local authorities can levy on new development to fund infrastructure.
South Worcestershire Development Plan Review (SWDPR): The reviewed local plan covering South Worcestershire, expected to be adopted in Spring 2026.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item79
Resolved
That the Committee: 1. approve the draft Developer Contributions Supplementary Planning document, as set out in Appendix 1, for a 5-week public consultation; and 2. authorise the Head of Planning and Economic Development, in consultation with the Chair and Vice Chairs of Policy and Resources Committee to make any necessary minor amendments to the draft prior to publication.
Word for word from the decision Worcester published for this meeting.Source: committee.worcester.gov.uk
1.1Approves the draft Developer Contributions Supplementary Planning document, as set out in Appendix 1, for a 5-week public consultation; and
1.2Authorises the Head of Planning and Economic Development, in consultation with the Chair and Vice Chairs of Policy and Resources Committee to make any necessary minor amendments to the draft Developer Contributions Supplementary Planning Document prior to publication.
Background
2.1Supplementary Planning Documents (SPDs) provide detailed guidance and support for policies in the Local Plan. SPDs assist in the implementation of planning policies for specific areas and once adopted are a material consideration in the planning decisions.
2.2Developer contributions are financial or in-kind contributions required from developers to mitigate the impacts of new developments to ensure they are sustainable and acceptable in planning terms. The Developer Contributions SPD will be a material consideration for planning applications and will give background information to both decision-makers and applicants for planning permission on the approach, nature and sums sought for securing mitigation through planning conditions, planning obligations (Section 106, Section 278 and Section 38 agreements) and Community Infrastructure Levy.
2.3The current Developer Contributions SPD was adopted in July 2018, against the South Worcestershire Development Plan 2016 and sets out guidance relating to the collection of developer contributions, to be used when determining planning applications.
2.4With the South Worcestershire Development Plan Review (SWDPR) expected to be adopted at Council in Spring 2026, the draft Developer Contributions SPD for (Appendix 1) has been redrafted to build upon and provide more detailed advice or guidance in relation to the policies in the SWDPR. The Developer Contributions SPD outlines how funding or infrastructure will be secured from developers to mitigate the impact of new developments both individually and cumulatively. This can be via on-site provision or contributions. The SPD is now ready for public consultation for five weeks and is expected to be adopted as a Supplementary Planning Document (SPD) to the SWDPR subject to any required amendments by the end of June 2026.
2.5The aims of the draft Developer Contributions SPD are to provide developers, planning agents and applicants with: • An overview of the Council’s planning policy approach to securing mitigation through planning conditions, planning obligations (Section 106, Section 278 and Section 38 agreements) and Community Infrastructure Levy (CIL); • Clarification about the relationship between planning obligations secured through s106 legal agreements and CIL; and • Guidance on the type, nature and scale of planning obligations that may be sought, and the basis for the sums sought.
2.6The Developer Contributions SPD will be a material consideration in the determination of planning applications and will give background information to both decision-makers and applicants for planning permission on the required on-site or off-site contributions being sought.
3. Preferred Option
3.1The preferred option is to progress the Developer Contributions SPD to statutory public consultation.
Alternative options considered
4.1The Council could decide not to continue with the preparation of the SPD, however a deadline for adoption of SPDs under the current plan making framework has been set by Government of the end of June 2026. There is therefore only a limited window of opportunity to review the SPD to ensure that it can continue to be a material consideration in decision making on planning applications.
5. Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.