Worcester City Council
Policy and Resources Committee, Tuesday 24 March 2026 at 7.00pm

Scala Arts Centre: Corn Exchange and Additional Assets

Agreed Committee 2 papers

AI summaryWorcester City Council's Policy and Resources Committee approved Corn Exchange and No 6 Angel Place works at the Scala Arts Centre, delegating contract authority to officers within maximum budgets of £3.592m and £302.5k.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedContracts for Corn Exchange and No 6 Angel Place works
Money£3.592m and £302.5kMaximum budgets for Corn Exchange and No 6 Angel Place
What happens nextEnter construction contractsVia delegated authority to Corporate Directors
Who it affectsCathedral wardScala Arts Centre and Corn Exchange site

What was decided

The Committee noted the tendered price from Speller Metcalfe Malvern Ltd and agreed to proceed with the Corn Exchange construction contract, delegating authority to the Corporate Directors, in consultation with the Chair and Vice Chairs, to award it up to a maximum budget to be confirmed at the meeting. Report 2.2, 2.8, P22

The Committee delegated authority to the same officers to procure and enter a construction contract for works to No 6 Angel Place, the Scala co-working space, up to a maximum budget to be confirmed at the meeting. Report 2.10, P23

The Committee authorised the use of Council financial resources to fund the balance of the Corn Exchange contract, client contingency sum and No 6 Angel Place works above the Cultural Funding grant. Report 2.11, P18

Why

Officers reviewed SMML's tendered price of £2,726,164.33 with external cost consultants Equals and architects BFF, and were satisfied the pricing was sufficiently robust to recommend to Committee. Report 2.2, 2.3

The Government Cultural Funding grant is insufficient to cover the full budgets; the £2.056m shortfall will be met from unallocated capital receipts, Towns Fund Grant and other revenue funding. Report 2.11, 2.12, P18

Experience with provisional sums on the Phase 1 Scala construction contract gave officers assurance that SMML's approach does not expose the Council to an unacceptable level of budget uncertainty. Report 2.5

What happens next

Award the Corn Exchange construction contract to Speller Metcalfe Malvern Ltd under delegated authority once the maximum budget sum is confirmed at the meeting. Report 2.2, 2.8

Procure a minor or intermediate works contractor for No 6 Angel Place under delegated authority. Report 2.9, 2.10

Design principles for Angel Place to be considered by the Place and Economic Development Committee, with budget implications referred back to Policy and Resources Committee.

The money

  • £2,726,164.33 Corn Exchange tendered price from Speller Metcalfe Malvern Ltd Report 2.2
  • £290k Provisional sums within the Corn Exchange tendered price Report 2.5
  • £3.592m Maximum budget for Corn Exchange construction contract, fees, kitchen fit-out and 10% client contingency Report P10, 2.8, P22
  • £256k Purchase cost of No 6 Angel Place, including fees and taxes Report 2.9
  • £302.5k Maximum budget for No 6 Angel Place refurbishment, including 10% client contingency Report 2.10, P23
  • £559k Total purchase and fit-out cost of No 6 Angel Place Report 2.10
  • £1.867m Budget shortfall on Corn Exchange after Cultural Funding grant Report 2.11
  • £0.189m Budget shortfall on No 6 Angel Place after Cultural Funding grant Report 2.11

Options considered

  • Chosen: Proceed with development of Corn Exchange and No 6 Angel Place up to maximum budget sums of £3.592m and £0.303m. Preferred option recommended by officers to deliver the Scala Arts Centre project Report 3.1, P20, P22, P23
  • Rejected: No alternative options. No other alternative options are recommended, as set out in the main report Report 4.1, P25

Implications

  • Financial: A £2.056m shortfall against the Cultural Funding grant must be met from Council capital receipts, Towns Fund Grant and other revenue funding. Report 2.11, 2.12, P18
  • Legal: Contract award authority is delegated to the two Corporate Directors in consultation with the Chair and Vice Chairs of the Committee.
  • Equalities: Equality implications are as set out in the main report. Report 5.4, P32
  • Staffing: Human resources implications are as set out in the main report. Report 5.6, P35

Who and where

  • Cathedral ward Report P39
  • Scala Arts Centre users and future co-working space tenants at No 6 Angel Place Report P12, 2.9

Timeline

  • 16th March: Main report published at Agenda item 9 Report 2.1
  • 19th March: Corn Exchange tendered price received from Speller Metcalfe Malvern Ltd Report 2.2
  • 24 March 2026: Policy and Resources Committee decision

Plain English for the jargon

  • SMML: Speller Metcalfe Malvern Ltd, the Council's appointed contractor
  • Cultural Funding grant: Government grant received by the Council for developing these Scala assets
  • Provisional sums: Items that cannot be fully priced until works have commenced, due to dependencies and unknown variables
  • Client contingency: A sum held back, recommended at 10%, to cover post-contract price variations
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item81

Resolved

That the Committee agree to: 1. note the progress in developing detailed designs and costings for the construction works to the Corn Exchange and notes that the tendered price is due from Speller Metcalfe Malvern Ltd on 19 March; 2. delegate authority to the Corporate Director – Economic Development, Planning and Governance and the Corporate Director - Finance and Resources, in consultation with the Chair and Vice Chairs of the Committee, to enter into a construction contract with Speller Metcalfe Malvern Ltd to proceed immediately with Phase 2 of the project, namely works to the Corn Exchange, up to a maximum budget sum to be confirmed at the Committee meeting; 3. note the outline scope of works for No 6 Angel Place (Scala co-working space) still being developed; 4. delegate authority to the Corporate Director- Economic Development, Planning and Governance and the Corporate Director – Finance and Resources, in consultation with the Chair and Vice Chairs of the Committee, to undertake a procurement and enter into a construction contract for works to No 6 Angel ... view the full minutes text for item 81.
Word for word from the decision Worcester published for this meeting. Source: committee.worcester.gov.uk

Follow this further

Built from Worcester's papers

What the report saysPro

Report to Policy and Resources Committee

Recommendation

1.1As set out in the main report. The recommended budget sums are in section 3 of this report.

Background

Corn Exchange

2.1The report at Agenda item 9, published on 16th March, explained that a tendered price for works to Corn Exchange was expected from the Council’s appointed contractor, Speller Metcalfe Malvern Limited (SMML), on 19th March.

2.2That tendered price has been received. It is in the sum of £2,726,164.33.

2.3Council officers have undertaken an initial review of the price, taking advice from the project’s external consultants (cost consultants Equals and principal design team BFF Architects). The pricing assumptions from SMML are detailed and provided in a transparent form. Officers are satisfied the pricing information is sufficiently robust in order to be recommended to Committee.

2.4Within this tendered price is the initial works package already approved by Committee.

2.5Within this tendered price is £290k of provisional sums. This means items that cannot be fully priced until works have commenced, because they are subject to other dependencies within the construction programme and unknown variables at this stage. There were provisional sums in the phase 1 Scala construction contract and the Council was content to proceed on this basis; as the contract programme, those provisional sums have been transparently reported and have been confirmed within the identified budget. This experience on phase 1, should help provide assurance that SMML’s approach to provisional sums is reasonable and does not expose the Council, in entering into contract for phase 1 Corn Exchange, to an unacceptable level of budget uncertainty.

2.6The reasons why a tendered price may still be subject to variation, post contract award, are explained in the main report. For these reasons, a client contingency sum is recommended. 2.7 There are additional costs which must be factored into the budgets. These are the professional fees of the design team and cost consultants, as well as the kitchen fit- out. These are as follows:

Expenditure £m Build Cost 2.726 Architects, QS & Project Mgmt 0.209 Kitchen and canopy 0.295 Other fees and items 0.036 Contingency -10% 0.326

Total 3.592

2.8Allowing for a recommended client contingency of 10%, the Council will need to identify a budget of £3.592m to let the Corn Exchange construction contract to SMML and fund the professional fees associated with its management, as well as the kitchen fit-out.

No 6 Angel Place (Scala co-working space)

2.9To provide Scala co-working space, No 6 Angel Place was purchased, costing £256k which included fees and taxes. The main report notes that a budget for works to No 6 Angel Place was being developed so that the Council could put these works out to tender and appoint a minor/intermediate works contractor. The scope of works is set out in the main report.

2.10The proposed budget for the refurbishment works to No 6 Angel Place is £302.5k. This is an estimated construction cost of £275k and a client contingency of 10%. In total, purchase and fit out of 6 Angel Place will cost £559k.

Council funding position

2.11As set out in the main report, the Council has received a Cultural Funding grant allocation from Government for the specific purpose of developing these assets. The available grant is insufficient to cover the full budgets for these works plus client contingency sums. Taking account of expenditure to date from the Cultural Funding grant, the budget shortfall for Corn Exchange is £1.867m and for No 6 Angel Place is £0.189m, £2.056m in total.

2.12The Council has other sources of funding available to be able to proceed. These are as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PR Report: March 2026- Supplemental Report- Corn ExReport 210 KB DownloadRead as text
PDF
Scala Arts Centre: Corn Exchange and Additional AssetsReport 212 KB Download

At this meeting

Whole meeting

Who was there

14 of 15 attended
PA
Councillor Patricia AgarCommittee Member, present
MA
Councillor Mel AllcottCommittee Member, present
SC
Councillor Steve CockeramCommittee Member, present
HC
Councillor Hannah CooperCommittee Member, apologies, sent representative
LD
Councillor Lynn DenhamChair, present
JJ
Councillor Jessie JaggerVice-Chair, apologies
KL
Councillor Karen LewingCommittee Member, present
AM
Councillor Alex MaceVice-Chair, present
RN
Councillor Robyn NorfolkCommittee Member, apologies, sent representative
JR
Councillor Jabbar RiazCommittee Member, present
AS
Councillor Adam ScottCommittee Member, present
PS
Councillor Paul SobczykCommittee Member, present as substitute

All 15 on the meeting page

On this subject at Worcester

Search all
  1. Scala Arts Centre: Corn Exchange and Additional AssetsThis decision
  2. Scala Arts Centre - Corn Exchange Early WorksAgreed
  3. Future High Street Fund Programme - Scala Arts CentreAgreed
  4. Scala Arts Centre - Approval of Business Plan and Operating ModelAgreed

More from Worcester Policy and Resources Committee

All decisions
MeetingDecisionOutcome
30 Jun 2026 MinutesThat the minutes of the meeting held on 19 th May 2026 be approved as a correct record and signed by the Chair. Approved Open
30 Jun 2026 Quarter 4 and Annual Key Performance Indicator Report for 2025/26That the Committee agree to note the Council’s quarter 4 and annual performance for the Key Performance Indicators in... Agreed Open
30 Jun 2026 Provisional 2025/26 Outturn - Financial Monitoring ReportThat the Committee agree to note the following: 1. the Provisional 2025-26 Revenue outturn as detailed in section 2 o... Agreed Open
30 Jun 2026 Medium Term Financial Plan 2027/28 - 2031/32That the Committee agree: 1. to note the update; and 2. the MTFP and budget timetable as set out in paragraph 3.2 of ... Agreed Open
30 Jun 2026 Town Investment Plan UpdateThat the Committee agree to note the contents of this report. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies