Contracts Which Have Exceeded the Agreed Contract Sum by More than 10%
AgreedScrutiny1 paper
Customers, Performance, Resources and Governance Scrutiny Committee agreed this item on Wednesday 22 April 2015. Below is the council's own wording, with the papers it was decided on.
AGREED – ( i ) That Officers review the specifications provided and the process undertaken to appoint asbestos consultants. (ii) That the payment of standing time for certain types of contract be reviewed. (iii) That the Employment, Business and Investment Scrutiny Committee be recommended to consider the value delivered by the Vibrant Viable Places (VVP) funding, taking into account the use of additional funding at GATE. (iv) That the reclamation of overspend arising from the contract at Cefn Mawr , from the asbestos consultant, be investigated.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Customers, Performance, Resources and Governance Scrutiny Committee
Purpose of the report
To advise Members of contracts which have exceeded the agreed contract sum by more than 10%, subject to a minimum over-spend of £10,000, in accordance with Financial Regulation 10 and Scrutiny Committee’s previous decisions.
Executive summary
2.1Financial Regulation 10.103 requires:
“In any case where the total cost of any work carried out under a contract, including term contracts, exceeds by more than 10% the approved contract sum, subject to a minimum variation of £10,000, a report of such cost including the reasons for the variation, shall, after agreement of the final account, be submitted to the Customers, Performance & Resources Scrutiny Committee.”
2.2The Customers, Performance & Resources Scrutiny Committee also recommended :
a) That all contracts which meet the 10% or £10,000 criteria are reported every six months in a single composite report, but that any contracts where the excess sum is a minimum of 20% of the agreed contract sum subject to a minimum value of £30,000 be reported to the next available meeting of this Committee.
b) That this report also includes details of the monitoring arrangements which are in place and any areas of non-compliance with the reporting of variations to contracts which were identified through random sample checks. c) That, initially, the relevant Head of Department be required to authorise an overspend on the original contract sum, prior to any additional works being carried out.
2.3This report will enable Members to consider any expenditure in excess of 10% of the agreed contract sum and the reasons why they occurred.
2.4The two contracts that have spent in excess of 10% or £10,000 above the agreed contract sum are detailed in Appendix 1a and 1b.
2.5There is no evidence to show that the additional expenditure was formally approved in advance by the relevant Head of Department.
2.6The Head of Finance has reminded all HODs that best practice requires them to sign off any additional expenditure personally, before further expenditure is incurred, having considered the financial and political implications of the instruction to the Assets and Economic Development department and that the Assets and Economic Development department, acting as client, will remind each of the HODs of this requirement as and when circumstances occur in the future.
2.7It is important to note that this is currently best practice advice and is NOT included in the Financial Regulations and that there is a difference between the need to address unforeseen works e.g. poor ground conditions, where the Assets and Economic Development department will not take an instruction from the client department but will action the works out of necessity, compared to "would like to have….as additional spend by the client department".
Recommendation
3.1That Members consider the report and comment on the issues identified in respect of these two contracts.
Reasons for recommendation
To enable Members to challenge the reasons for expenditure in excess of 10% of the agreed contract sums subject to a minimum variation of £10,000.
4. BACKGROUND INFORMATION
4.1Financial Regulation 10 sets out the requirements for obtaining tenders for goods, works and services. Competitive tenders should be obtained unless there is an agreed reason for an exemption. This helps to ensure that value for money is obtained from the contract process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customers, Performance, Resources and Governance Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.