Contracts which have Exceeded the Agreed Contract Sum by more than 5%
AgreedScrutiny1 paper
Customers, Performance, Resources and Governance Scrutiny Committee agreed this item on Thursday 3 May 2018. Below is the council's own wording, with the papers it was decided on.
AGREED – ( i ) That future reports detail Departmental compliance with the requirement for them to contribute to the central contractor database. (ii) That future reports focus solely on jobs meeting the criteria, when the estimated cost at detailed “rip out” survey stage is compared to final cost. (iii) That the new framework for dealing with voids and the establishment of a voids commissioning team be welcomed (iv) That matters to address the internal audit red/amber in respect of highways maintenance contract management arrangements be welcomed.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
Report to Customers, Performance, Resources and Governance Scrutiny Committee
Purpose of the report
To allow Members to consider a six monthly report, which details contracts, which have exceeded the agreed contract sum by more than a specified percentage or amount.
Executive summary
2.1The Customers, Performance, Resources and Governance Scrutiny Committee (CPRGSC) has previously requested six monthly reports which identify contracts where the total cost of work carried out under the contract, compared to the original order value, is:
a) Over 5% with more than a £10,000 overspend b) Over 20% subject to a minimum overspend of £30,000 (detailed report to next meeting) c) Increases in order value of more than 10% subject to a minimum overspend of £5,000 in respect of highways maintenance works and Council house voids. 2.2 The previous report on this matter was presented to the Customers, Performance, Resources and Governance Scrutiny Committee (CPRGSC) on the 22 November 2017 (HF/113/17s). Actions taken to address concerns raised at that meeting are detailed within the content of this report.
2.3This report will enable Members to consider the number of individual contracts or orders that have met the above criteria and whether there was compliance with Contract Procedure Rules (CPR). These can be summarised as follows:
a) There were no contract overspends of more than 5% subject to a minimum of £10,000, in respect of capital and Housing Revenue Account (HRA) contracts (1 October 2017 to 28 February 2018). b) Out of 66 Highways maintenance orders, 13 jobs (19.70%) exceeded the original order value by more than 10%, subject to a minimum overspend of £5,000 (1 September 17 to 31 January 2018 to take account of an eight-week notification period). Of these 13 jobs, 12 were completed between 1 April 17 and 31 August 17 but had not previously been reported, due to the omission of final account values and only one job completed between 1 September 17 and 31 January 2018, met the criteria. c) Out of 290 housing voids completed during the period 1 October 2017 to 28 February 2018, at initial survey stage 37 voids (12.75%) exceeded the original order value by more 10%, subject to a minimum overspend of £5,000. However, when the same properties are compared against revised order values established following completion of “rip out” surveys the number exceeding the original order value by more 10%, subject to a minimum overspend of £5,000 was reduced to seven voids. It is suggested that future reports focus solely on jobs meeting the criteria, when the estimated cost at detailed “rip out” survey stage is compared to final cost.
2.4Contract values can increase from the original submitted tender sum or order value for a number of reasons. These include where additional works have been commissioned as extra budget has been identified, unforeseen works incurring additional expenditure or increased grant funding has been made available.
2.5In the case of highways maintenance and Council house voids, it is not always possible to compile an accurate specification of the required works at the initial survey stage, as intrusive surveys cannot always be carried out. The reasons for price variations should be monitored and any trends or recurring areas identified. In all cases, the officer’s professional judgement should be exercised.
2.6CPR require that all variations from the original tender or order should be certified in advance by the relevant Head of Department or designated Senior Manager and cost variances managed through the contract monitoring and management process. This helps to ensure that value for money is achieved.
Recommendation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Customers, Performance, Resources and Governance Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.