Resolved
RESOLVED – That t he Committee is satisfied with the processes and controls in place to manage budgets and contracts and will take this item as an annual report in the future.
Customers, Performance, Resources and Governance Scrutiny Committee decided this item on Thursday 2 May 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That t he Committee is satisfied with the processes and controls in place to manage budgets and contracts and will take this item as an annual report in the future.
To allow Members to consider a six monthly report, which details contracts, which have exceeded the agreed contract sum by more than a specified percentage or amount.
2.1The Customers, Performance, Resources and Governance Scrutiny Committee (CPRGSC) has previously requested six monthly reports which identify contracts where the total cost of work carried out under the contract, compared to the original order value, is:
a) Over 5% with more than a £10,000 overspend b) Over 20% subject to a minimum overspend of £30,000 (detailed report to next meeting) c) Increases in order value of more than 10% subject to a minimum overspend of £5,000 in respect of highways maintenance works and Council house voids.
2.2The previous report on this matter was presented to the Customers, Performance, Resources and Governance Scrutiny Committee (CPRGSC) on the 24 October 2018 (HF/110/18s), where the Committee noted the “improvement and tightening up on contract management” 1.
1 http://vmmoderngov/ieListDocuments.aspx?CId=138&MId=4281&Ver=4 2.3 This report will enable Members to consider the number of individual contracts or orders that have met the above criteria and whether there was compliance with Contract Procedure Rules (CPR). These can be summarised as follows:
a) There were no contract overspends of more than 5% subject to a minimum of £10,000, in respect of Capital and Housing Revenue Account (HRA) contracts (1 August 2018 to 31 December 2018). b) Out of 39 Highways maintenance orders, one job (2.56%) exceeded the original order value by more than 10%, subject to a minimum overspend of £5,000 (1 July 2018 to 30 November 2018 to take account of an eight-week notification period). c) Out of 98 housing voids completed during the period 1 August 2018 to 31 December 2018, where a final account has been completed, 13 voids (13.27%) exceeded the original order value by more than 10%; subject to a minimum overspend of £5,000.
2.4Contract values can increase from the original submitted tender sum or order value for a number of reasons. These include where additional works have been commissioned as extra budget has been identified, unforeseen works incurring additional expenditure or increased grant funding has been made available.
2.5In the case of highways maintenance and council house voids, it is not always possible to compile an accurate specification of the required works at the initial survey stage, as intrusive surveys cannot always be carried out. The reasons for price variations should be monitored and any trends or recurring areas identified. In all cases, the officer’s professional judgement should be exercised.
2.6CPR require that all variations from the original tender or order should be certified in advance by the relevant Head of Department or designated Senior Manager and cost variances managed through the contract monitoring and management process. This helps to ensure that value for money is achieved.
3. RECOMMENDATION That Members of the Committee formulate their conclusions and recommendations based on the information in the report and the discussion at the meeting.
To enable Members to challenge the reasons for the increase in order value in respect of highways maintenance works and council house voids in excess of 10%, subject to a minimum variation of £5,000.
4. BACKGROUND INFORMATION
4.1CPR set out the requirements for obtaining tenders for goods, works and services. Competitive tenders should be obtained unless there is an agreed reason for an exemption. This helps to ensure that value for money is obtained from the contract process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Contracts which have exceeded the Agreed Contract Sum by more than 5%Report | 153 KB | DownloadRead as text |
Follow Customers, Performance, Resources and Governance Scrutiny Committee at Wrexham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Confirmation of MinutesAGREED – That the Minutes of the Meetings held on 5 and 25 June 2026 be confirmed and signed as a correct record. | Agreed | Open |
| 3 Sep 2026 | Work ProgrammeAGREED – That the work programme be agreed subject to the aforementioned amendmens. | Agreed | Open |
| 3 Sep 2026 | ICT and Digital Strategy 2024-2027AGREED – That the Committee i. Congratulate everyone involved in achieving the national Granicus award in respect of ... | Agreed | Open |
| 25 Jun 2026 | Confirmation of MinutesAGREED – That the minutes of the meeting held on 14 May 2026 be confirmed and signed as a correct record. | Agreed | Open |
| 25 Jun 2026 | Work ProgrammeAGREED – That the work programme be agreed subject to the above amendments. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.