RESOLVED – (i) That the 2024/25 budgetary forecast position for the year based on the Quarter 1 position be noted. (ii) That a School Transport Task and Finish Group be established, and an update report be brought back to Executive Board in 6 months. Reason for decision To ensure robust budget monitoring arrangements for the financial year and that action is taken to address the budget pressures forecast.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To inform Members of the Council’s 2024/25 current budgetary position for the first quarter of the 2024/25 financial year, including the Housing Revenue Account (HRA).
Executive summary
2.1The Council’s net revenue budget for 2024/25 is £319,571,866. The net revenue budget of £318,669,885 was agreed by Council on 28 February 2024 (COFI/09/24), however following the Local Government Final Settlement, additional funding of £901,981 was received relating to the transfer of specific grants (£299,468) and the reversal of the reduction to the social workforce grant for 2024-25 (£602,513).
2.2This Revenue Budget update report is the first quarterly report for the financial year 2024/25. The report forecasts the year-end position and is underpinned by assumptions and estimates, taking account of actual expenditure to the end of May. Therefore this is an early forecast and allows time for assumptions underpinning projections to be revised as a result of the initial forecast, early in the year, if necessary.
2.3Last year’s final outturn position was a surplus compared to the budget of £532k which recognised the significant work undertaken across the Council during the year to address an early forecast of a significant pressure. However, this overall net surplus contained significant financial pressures across statutory and demand-led services, in particular social care (including specialist placements for children and specialist educational placements), school transport and Streetscene costs. Given the nature of the pressures last year, which are common across local government, and continued growth in demand and cost, it was anticipated that this would continue to have an impact in the current financial year. The current budgetary position is a gross projected budget pressure and this is summarised in Appendix 1. This is the forecast position at this point, if demand and cost pressures continue. It is made clear in this report that this type of pressure is within the scope of a reasonable variance that could be managed within normal operating parameters. In light of this, this report does not make any proposals about specific service mitigations, although all Chief Officers are aware of the position and of the need to manage budgets prudently. If specific mitigations are needed, these will be reported at Q2, when there would still be time and scope to deal with the position. The level of forecast pressure reported at this point is £4m.
2.4The projected position assumes that the 2024/25 pay award is in line with the 5% budget provision. The pay award has not yet been agreed and if the outcome is different from the assumption, the forecast position will change across all services and schools. Increased employer costs in respect of teachers’ pensions are assumed to be funded nationally, as prescribed in the narrative supporting the Local Government Financial Settlement 2024/25.
2.5As with last financial year, identifying and reporting the forecast pressure early in the year allows time to adjust spending assumptions where pressures are forecast in order to bring the budget back into a balanced position. A budget mitigation reserve of £5m was established as part of the budget setting process for 2024/25. Although specific service pressures are forecast at Q1, the position does not assume use of this reserve currently. In the first instance, where service pressures are forecast, services will review spending assumptions, forecasts and priorities in- year with the aim of reducing the forecast pressure.
2.6The budget set for 2024/25 included an in-year saving to be identified of £1.772m. Proposals to deal with this are included in the Change Programme report (ref) and if approved, will be reflected in the next budget monitoring report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.