2023/24 Capital Programme Outturn and 2024/25 Quarter 1 Programme Update

Noted Executive 4 papers

Executive Board noted this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

RESOLVED – (i) That the capital outturn for 2023/24 be noted. (ii) That the quarter 1 programme for 2024/25, as detailed in appendices 1, 2 and 3 of report COFI/22/24, be approved. Reason for decisions This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.
Word for word from the decision Wrexham published for this meeting. Source: moderngov.wrexham.gov.uk

Follow this further

Built from Wrexham's papers

What the report saysPro

Report to Executive Board

Purpose of the report

To advise Members of the 2023/24 Capital Programme outturn and to review the 2024/25 Capital programme position as at the end of quarter 1 2024/25.

Executive summary

2.1The total capital expenditure in 2023/24 including the Housing Revenue Account (HRA) was £73,056k as detailed in Appendix 1. This is £13,334k less than the total approved by the Executive Board at its meeting on 6 February 2024 (COFI/05/24). The reasons for the net decrease are:

 A net decrease in spend of £15,271k on non HRA projects including re-phasing of spend to future years.  A net increase in spend in the HRA capital programme of £1,937k.

2.2Each scheme within the Capital Programme is fully funded by borrowing supported by the Welsh Government, grants and contributions, capital receipts, prudential borrowing and interest free loans from Salix.

2.3Following the announcement of the final local government settlement on 27 February 2024 the Welsh Government General Capital Funding for 2024/25 is £7,018k a decrease of £28k from the 2023/24 allocation.

2.4The 2024/25 Programme includes an additional £300k in respect of highways infrastructure that was agreed as part of the revenue budget proposals approved in the final budget report. 3 RECOMMENDATIONS

3.1The capital outturn for 2023/24 is noted.

3.2The quarter 1 programme for 2024/25 as detailed in appendices 1, 2 and 3 is approved.

Reason for recommendations

(i) This report follows an earlier monitoring report in February in compliance with Financial Regulation 3.13 that requires that the Chief Officer Finance & ICT monitors and reports to Members on the Capital Programme.

4. BACKGROUND INFORMATION

Capital Programme 2023/24

4.1The Executive Board approved the last revision of the capital programme 2023/24 to 2024/25 on 6 February 2024 (COFI/05/24). Appendix 1 provides a summary of expenditure by service, the financing of that expenditure and the variance between the actual programme and the previously approved position.

4.2The actual expenditure on all capital schemes was £73,056k, a net decrease of £13,334k compared with the projected expenditure reported to the Executive Board in February 2024. The significant changes are as follows;

Rephasing of Schemes to 2024/25

4.3Changes to the phasing of expenditure have resulted in £4,911k of spending originally planned in 2023/24 to be rescheduled to 2024/25. Projects where significant re-phasing has occurred are set out below:

 ICT Infrastructure/Modernisation (-£170k). Replacement programme realignment.

 Pontcysyllte Aqueduct & WHS (-£1,106k). The scheme is being reprofiled with the UK Government.

 Football Museum for Wales (-£171k).Timing of invoices paid.

 Property Investment Development Grants (-£163k). Project slippage on specific developments.

 Public Realm (-£300k). Payment for works not completed until 2024/25.

 School Capital Maintenance (-£281k). These projects were not able to be completed in 2023/24 due to the volume of works undertaken in this year.

 Universal Primary Free School Meal grant (-£719k). Works delayed due to resource capacity and re scheduled during the summer 2024.

 Community Focused Schools (-£376k). The two year programme and profile over the financial years has changed.  Highway Infrastructure Improvements (-£505k). Timing of completion of works towards the end of the financial year.

 Local Places for Nature Scheme (-£210k). Two year programme and profile amended.

 EV Charging Hubs (-£610k). Works delayed due to infrastructure complexities.

Other Changes

4.4Other variations between the revised capital programme reported in February and the actual expenditure account for a net decrease in planned spending of £10,360k. The main reasons are as follows:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2023/24 Capital Programme Outturn and 2024/25 Quarter 1 Programme UpdateReport 439 KB DownloadRead as text
PDF
Appendix 1Appendix 1 128 KB Download
PDF
Appendix 2Appendix 2 118 KB Download
PDF
Appendix 3Appendix 3 78 KB Download

At this meeting

Whole meeting

Who was there

10 of 23 attended
YC
Y Cynghorydd David A BithellVice-Chair, present
YC
Y Cynghorydd Terry EvansCommittee Member, present
YC
Y Cynghorydd Hugh JonesCommittee Member, present
YC
Y Cynghorydd Beverley Parry-JonesCommittee Member, present
YC
Y Cynghorydd John PritchardCommittee Member, present
YC
Y Cynghorydd Mark PritchardChair, present
YC
Y Cynghorydd Paul RobertsCommittee Member, present
YC
Y Cynghorydd Robert WalshCommittee Member, present
YC
Y Cynghorydd Nigel WilliamsCommittee Member, present
YC
Y Cynghorydd Phil WynnCommittee Member, present
YC
Y Cynghorydd Bryan ApsleyGuest, in attendance, virtual
YC
Y Cynghorydd Trevor BatesGuest, in attendance, virtual

All 23 on the meeting page

On this subject at Wrexham

Search all
  1. 2023/24 Capital Programme Outturn and 2024/25 Quarter 1 Programme UpdateThis decision
  2. 2025/26 Capital Programme Outturn and 2026/27 Quarter 1 Programme UpdateNoted
  3. Education Capital Investment - Sustainable Communities for Learning ProgrammeNoted
  4. Capital Programme and Treasury Management Quarter 3 Review 2025/26Noted
  5. 2024/25 Capital Programme Outturn and 2025/26 Quarter 1 Programme UpdateApproved
  6. Capital Programme and Treasury Management quarter 3 review 2024/25Approved

More from Wrexham Executive Board

All decisions
MeetingDecisionOutcome
15 Sep 2026 Council Plan - Annual Performance Report 2025/26 and Year 4 Target SettingRESOLVED – ( i ) That the ‘Council Plan Annual Performance Report 2025/26’ as outlined in Appendix A of report CE/14/... Approved Open
15 Sep 2026 Brymbo Sports& Social Complex, Heritage Way, Tanyfron, Wrexham, LL11 5TGRESOLVED – ( i ) That the grant of a new lease be authorised, for a minimum term of 75 years, at a nominal rent of £1... Decided Open
15 Sep 2026 Local Development Plan Delivery AgreementRESOLVED – ( i ) That the Wrexham be approved for submission to the Welsh Government for their approval. (ii) That th... Approved Open
15 Sep 2026 Update: Wrexham UK City of Culture 2029 BidRESOLVED – That the Executive Board continue to demonstrate their full support for Wrexham's bid to become UK City of... Decided Open
15 Sep 2026 Proposal to consult on establishing a new special school for pupils with Additional Learning Needs (ALN) in Gwersyllt - Consultation FeedbackRESOLVED – ( i ) That the consultation feedback contained in the post consultation feedback report regarding the prop... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies