Education Capital Investment - Sustainable Communities for Learning Programme
NotedExecutive6 papers
AI summaryWrexham Executive Board noted progress on the Sustainable Communities for Learning school capital programme and will receive a revised Strategic Outline Plan for Years 4-9 in January 2027.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFurther report and condition survey update due January 2027
Money£27.75mPotential local authority capital contribution assumed in funding plan
What happens nextJanuary 2027Revised Strategic Outline Plan for Years 4-9 of the rolling programme
Who it affectsWrexham school estateNine-year rolling capital investment programme in three phases
What was decided
Members noted progress against the Sustainable Communities for Learning Programme and the updates in the report. Report 3.1
A further report will be submitted in January 2027 with a revised Strategic Outline Plan for Years 4-9, due to Welsh Government in March 2027. Report 3.2
An update on the condition survey of Wrexham schools will be submitted in January 2027.
Why
To enable the local authority to successfully deliver the Sustainable Communities for Learning Programme. Report P17
To continue delivering investment and improvement to the school estate over the next decade. Report P17
To acknowledge the programme's role in improving learning environments and partnership arrangements with schools and communities. Report P18
What happens next
The authority will review projects later in 2026 ahead of a resubmission of the Strategic Outline Programme to Welsh Government in early 2027. Report 2.7
An options appraisal will be carried out for each individual project as part of its business case. Report 7.1, P77
Members will receive a further progress update at the end of each phase to test that the strategic drivers remain appropriate. Report 2.9, 4.16
The money
65% Welsh Government Sustainable Communities for Learning Grant rate for local authority projects Report P63
85% Welsh Government grant rate for faith projects Report P63
75% Welsh Government grant rate for special education projects Report P63
£27.75m Potential local authority capital contribution, totalling all identified sources Report P63
£4.1m Currently in capital receipts Report P64
£2.65m Currently in capital annual provision Report P64
£1m Potential capital through existing Section 106 contributions Report P64
£5m Future capital receipts Report P64
£7m Prudential borrowing Report P64
£8m Future capital annual provision, assuming continuation of current level Report P64
Implications
Financial: Future budgetary implications have been noted and accounted for in future planning; assumptions underpin the funding plan at Appendix 1b. Report 5.2, P63, P64, P65
Legal: The report identifies no legal implications. Report 5.3
Staffing: The Access and School Places Team delivering the programme comprises a Programme Manager (0.8 FTE), a Business Manager (FTE) and two Senior Officers (1 FTE and 0.6 FTE). Report 5.4, P68
Equalities: An Integrated Impact Assessment covers the Well-being of Future Generations Act, Equality Act, Welsh Language Measure and Armed Forces Act duties; further assessments will follow at implementation stages. Report 5.5, P70
Climate: All new projects must be Net Zero Carbon in operation, supporting the council's commitment to be a net carbon free council by 2030. Report 5.6, P49
Risk: Risks include a possible change to the Welsh Government intervention rate, insufficient match funding, deteriorating buildings, statutory consultation delays, market and financial conditions, and conflicting council priorities such as affordable housing. Report 5.7, P73
Who and where
Wrexham pupils across primary, secondary, faith, special and Welsh-medium schools Report P18, P49
Learners with additional learning needs (ALN) Report P23, P49
St Mary's Brymbo (Church in Wales faith school) community, with a new school anticipated to open by September 2028 Report 4.4, P27
St Mary's RC (Roman Catholic faith school) community, with a relocated 315-place school anticipated to open by September 2028 Report 4.5, P28
St Christopher's Special School community, with a new special school anticipated to open by September 2029 Report 4.6, P29
Haulfan Pupil Referral Unit pupils, relocating to the refurbished former Yr Hafod infant site, anticipated to open in September 2026 Report 4.7, P30
Schools and communities engaged through WASH, Primary Heads Federation and Diocesan authorities Report 6.1
Timeline
December 2024: Executive Board approved the Strategic Outline Programme and the nine-year Rolling Programme Report 2.1
2024: Welsh Government approved the strategic principles for years 1-6 and projects in years 1-3 Report 2.5, P10
25 June 2025: Lifelong Learning Scrutiny Committee reviewed the revised School Organisation Framework Report 4.19, 8.1
July 2025: Welsh Government approved the Strategic Outline Case for the Haulfan Pupil Referral Unit Report 4.7
September 2025: Welsh Government approved the Strategic Outline Case for St Mary's Brymbo; Read Construction appointed Report 4.4
October 2025: Refurbishment works started at the former Yr Hafod infant site for Haulfan PRU (Bryn Build appointed) Report 4.7
December 2025: Welsh Government approved Strategic Outline Cases for St Mary's RC and St Christopher's Special School Report 4.5, 4.6
Later in 2026: Review of projects ahead of resubmission of the Strategic Outline Programme Report 2.7
September 2026: Haulfan PRU anticipated to open to pupils Report 4.7
January 2027: Further report on revised Strategic Outline Plan for Years 4-9 and update on the schools condition survey Report 3.2
March 2027: Revised Strategic Outline Programme due to be submitted to Welsh Government
September 2028: St Mary's Brymbo and St Mary's RC anticipated to open to pupils Report 4.4, 4.5
September 2029: St Christopher's Special School anticipated to open to pupils Report 4.6
Plain English for the jargon
SOP: Strategic Outline Programme, the rolling nine-year plan for school capital investment
ALN: Additional Learning Needs
WESP: Welsh in Education Strategic Plan
PRU: Pupil Referral Unit
Band B: Phase of the previous 21st Century Schools Programme, now incorporated as Phase 1 of this programme
FTE: Full-Time Equivalent, a measure of staff hours
Section 106: Planning obligation contributions from developers towards local infrastructure
Gateway Review: Assurance check required by Welsh Government to confirm a programme is deliverable
WASH: Wrexham Association of Secondary Headteachers
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item109
Resolved
RESOLVED – ( i ) That progress against the Sustainable Communities for Learning Programme and the updates within report COEEI/08/26 be noted. (ii ) That a further report be submitted in January 2027 with a revised Strategic Outline Plan for Years 4-9 of the Rolling Programme which is due to be submitted to Welsh Government in March 2027. ( iii) That an update on the condition survey of Wrexham schools be submitted in January 2027. Reasons for Decisions ( i ) To enable the Local Authority to successfully deliver the Sustainable Communities for Learning Programme . (ii) To continue delivering this scale of investment and improvement to the school estate over the next decade. (iii) To acknowledge the importance of the Sustainable Communities for Learning Programme and the fundamental part it plays in improving learning environments for Wrexham pupils, as well as partnership arrangements with schools and their respective communities.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
1.1To provide Executive Board with an update on the Sustainable Communities for Learning Programme.
Executive summary
2.1In December 2024, Executive Board approved the Sustainable Communities for Learning Strategic Outline Programme (SOP) and Education’s proposed capital investment projects in the nine-year Rolling Programme (Appendix 1a).
2.2The nine-year rolling programme consists of a three-phased plan which will see the start of the delivery of several capital investment projects to improve education provision across Wrexham.
2.3Identified areas of focus across the three phases are:
2.3.1 Phase 1 – Projects in this phase include completion of existing Band B projects and refurbishment of the old Yr Hafod infant site for the re- siting of the Haulfan Pupil Referral Unit.
2.3.2 Phase 2 – Projects in this phase include in-county new Additional Learning Needs (ALN) Provision and strategic priorities, including Welsh medium education. 2.3.3 Phase 3 – Projects in this phase focus on School Organisation, the Welsh in Education Strategic Plan (WESP) and ALN.
2.4Education’s capital investment projects are prioritised based on a number of key strategic drivers, including:
Strategic need (e.g. ALN / Welsh medium education) Demographic changes, currently driven by a falling birth rate Proposed housing allocations Building condition Appropriateness of site/location
2.5In 2024, Welsh Government approved:
The strategic principles of the Strategic Outline Plan in years 1-6. Projects in years 1-3 of the nine-year rolling programme.
2.6This report provides an update on Phase 1 Years 1-3 of the Programme (previously committed Band B projects under the 21 st Century Schools Programme).
2.7Projects identified in Phases 2 and 3 of the Programme (years 4-9) are indicative projects only, which may change according to changing directives and or drivers. As such, they should not be taken as a statement of intent. We will be conducting a review of our projects later in 2026, ahead of a resubmission of the Strategic Outline Programme (SOP) in line with Welsh Government’s requirements in early 2027.
2.8Each project within the programme will be fully costed and assessed for affordability as part of a robust business case process carried out by the Local Authority and by Welsh Government. An anticipated funding forecast is attached at Appendix 1b.
2.9At the end of each phase in the programme, we will report back to Members to test that each of the strategic drivers are still appropriate.
Recommendations
3.1Executive Board Members note progress against the Sustainable Communities for Learning Programme and updates within this report.
3.2Executive Board Members receive a further report in January 2027 with a revised Strategic Outline Plan for Years 4-9 of the Rolling Programme which is due to be submitted to Welsh Government in March 2027.
Reasons for recommendations
(i) To enable the Local Authority to successfully deliver the Sustainable Communities for Learning Programme. (ii) To continue delivering this scale of investment and improvement to the school estate over the next decade.
(iii) To acknowledge the importance of the Sustainable Communities for Learning Programme and the fundamental part it plays in improving learning environments for Wrexham pupils, as well as partnership arrangements with schools and their respective communities.
4 BACKGROUND INFORMATION
4.1Over the past decade, the authority has continued to successfully deliver educational transformation projects across the County Borough.
4.2Identified priorities across the three phases of the Sustainable Communities for Learning nine-year rolling programme are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.