AI summaryWrexham's Executive Board approves arrangements to draw down its share of the UK Local Growth Fund for 2026/27, with project decisions delegated to the Interim Chief Officer for Economy and Planning.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedCyngor Gwynedd stays lead, delegation to officer
Money£5,817,302 for Wrexham projects17.9% of £33,781,826 after 4% fee
What happens nextProjects selected and spent by 31 March 2027No carry-forward permitted for year one
Who it affectsWCBC projects and partners in 2026/27Then CJCs take over from 2027/28
What was decided
Cyngor Gwynedd will continue as the lead body for the Local Growth Fund in North Wales during the 2026/27 transition period. Report 3.1, 2.7, 2.10
Authority is delegated to the Interim Chief Officer for Economy and Planning, in agreement with the Leader and Deputy Leader, to set Wrexham's priorities and select council led projects. Report 3.2, 3.4, 4.9
The matter is being treated as urgent business under Section 5 (Rule 5.8.10(m)) of the Council's Constitution. Report 3.5
Why
To make sure Wrexham's share is spent on strategic council led projects within the very short 2026/27 window. Report P25, 2.15, 4.4
To avoid returning unspent money to Welsh Government, which may not be reallocated to the county in later years. Report P26, 2.15, 4.4
Because 70% of the fund is capital, deliverable council led projects are being prioritised over opening an external application round. Report 2.9, 2.16, 3.3, 4.8
What happens next
Officers will complete the project pipeline and due diligence checks for council led projects that can be delivered by 31 March 2027. Report 4.8, 2.15
Cyngor Gwynedd and the six North Wales counties will finalise a legal agreement, based on the Shared Prosperity Fund model, for year one delivery. Report 2.11, 4.7
A Regional Investment Plan must be approved before any funds are committed; from 2027/28 the programme will move to Corporate Joint Committees (North Wales Ambition). Report 2.8, 2.14, 4.3
The money
£547 million UK Local Growth Fund allocated to Wales over three years 2026/27 to 2028/29 Report 2.1
£33,781,826 Indicative North Wales regional allocation for 2026/27 Report 2.9, 4.2
17.9% WCBC share of the regional allocation, using the Shared Prosperity Fund method Report 2.13, 4.1
£6,059,690 Indicative Wrexham allocation for 2026/27 Report 4.2
4% Management and administration fee taken from the regional allocation Report 4.2, 5.2
£242,388 Wrexham's management and administration fee Report 4.2
£5,817,302 Wrexham amount remaining for project allocation after the management fee Report 4.2
70% Share of the fund provided as capital in 2026/27 Report 2.9, 2.16, 3.3
Options considered
Chosen: Approve Wrexham's LGF arrangements and delegate project selection to the Interim Chief Officer for Economy and Planning, in agreement with the Leader and Deputy Leader.. Enables council led projects with permissions in place to be mobilised quickly so delivery finishes by 31 March 2027. Report 7.1, 3.3, 4.9
Rejected: Decline the recommendations and open an external application and appraisal process.. Would threaten the allocation of funds and delivery of projects within the 2026/27 window. Report 7.2, P49
Implications
Financial: A 4% management and administration fee is taken from the regional allocation, covering staffing and running costs. Report 4.2, 5.2, 5.4
Legal: A new legal agreement between Cyngor Gwynedd and the six North Wales counties will govern year one delivery, making each county accountable for its decisions and any financial liabilities. Report 2.11, 4.7
Equalities: An Integrated Impact Assessment (IIA823872098) covers the Well-being of Future Generations Act, equality, socio-economic and Welsh language duties, and the climate and ecological emergency declaration. Report 5.5, P42
Climate: A carbon impact assessment will be completed once projects are selected, as it cannot be finished in full at this stage.
Risk: All year one funding must be spent by 31 March 2027 with no scope to carry projects into years 2 and 3, which could make strategic projects harder to deliver in such a short period. Report 4.4, P44
Other: The fund's three themes are business support, skills and employment support for growth, and enabling local growth infrastructure, contributing to the Council Plan 2023-28. Report P6, P7, P8, 5.1
Who and where
Wrexham County Borough Council as the accountable body for its 17.9% share Report 4.1, 2.13, 2.11
Organisations and partners delivering council led projects in Wrexham during 2026/27 Report 3.3, 4.8
The six North Wales councils working through Cyngor Gwynedd as lead, with Ambition North Wales and Welsh Government on the Collaboration Board Report 2.10, 2.12
Residents and businesses in Wrexham, as the fund targets productivity growth and economic inequalities Report 2.3, 2.4, P6, P7, P8
Timeline
November and December 2025: Welsh Government consultation on the UK Local Growth Fund in Wales Report 2.2, 4.5
March 2026: Welsh Government provided the North Wales regional allocation figure Report 4.2
2026/27: Transition year, with Cyngor Gwynedd as lead local authority and funding to be spent by 31 March 2027 Report 2.7, 2.10, 2.15, 4.4
31 March 2027: Deadline for spending all 2026/27 Local Growth Fund allocations Report 2.15, 4.4
From 2027/28: Most funding to be allocated to Corporate Joint Committees (North Wales Ambition) under a three-year regional delivery plan Report 2.8, 4.3
2028/29: Final year of the three-year UK Local Growth Fund programme for Wales Report 2.1
Plain English for the jargon
Local Growth Fund: The UK Government fund that succeeds the Shared Prosperity Fund, with £547 million allocated to Wales over 2026/27 to 2028/29.
Shared Prosperity Fund (SPF): The previous UK Government funding programme that the Local Growth Fund replaces, using similar lead local authority arrangements.
Cyngor Gwynedd: Gwynedd Council, acting as the lead local authority for North Wales for the Shared Prosperity Fund and, in 2026/27, for the Local Growth Fund.
Corporate Joint Committee (CJC) / North Wales Ambition: The regional body expected to take over planning and managing Local Growth Fund projects from 2027/28.
Lead local authority: The council that administers and monitors the fund on behalf of the region during the transition period.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item119
Resolved
RESOLVED - (i) That the proposal for Cyngor Gwynedd to continue to act as the lead body within the region for the during this transition period making best use of existing and proven structures and processes be approved. (ii) That delegated authority be given to the Interim Chief Officer for Economy and Planning to provide input into Wrexham’s priorities for the regional local growth fund investment plan and allocation methodology to enable the funding to be drawn down from Welsh Government. (iii) That the Council led projects that are deliverable within this financial year (2026-2027) be prioritised for approval funding given the short timescales for delivery and the large capital percentage (70%). (iv) That delegated authority for project selection be given to the Interim Chief Officer for Economy and Planning, in agreement with the Leader and Deputy Leader, as outlined in paragraph 4.9 of report COEP/33/26. (v) That this matter is being dealt with as an urgent item of business in accordance with Section 5 (Rule 5.8.10(m)) of the Council’s Constitution. Reasons for decisions (i) To ensure that the funding allocated to WCBC from the is allocated and distributed in a timely manner to strategic council led projects that can deliver positive outcomes for the county borough in a short timescale. (ii) To mitigate against having to return any funds to Welsh Government to redistribute in following years, where there is no guarantee at present that any underspend would be allocated back to the relevant county to spend.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
For Members to consider and approve the arrangements for administering and monitoring the UK Government Local Growth Fund.
Executive summary
2.1The Local Growth Fund will be the main successor to the Shared Prosperity Fund (SPF) with a total of £547 million allocated to Wales over three years between 2026/27 and 2028/29. The funding will be routed to the Welsh Government in the first instance.
2.2The Welsh Government consulted on its proposed approach to the UK Local Growth Fund in Wales during November and December 2025 and this formed the basis of the objectives for Wales and the production of the North Wales’ regional transition plan.
2.3The purpose of the Local Growth Fund is to support the UK Government’s growth mission and contribute to its strategic goals of securing higher real incomes and boosting Gross Domestic Product (GDP).
2.4The Welsh Government's proposed objective for the Fund is to support productivity growth and tackle issues that lead to economic inequalities. 2.5 The Fund will operate on three themes as defined by the UK Government:
• Business support
• Skills and employment support for growth
• Enabling local growth infrastructure
2.6The Welsh Government's proposals emphasise regional collaboration and coordination, although the importance of delivering locally is acknowledged. The proposals also provide scope for national activities/interventions where appropriate.
2.7The Welsh Government regards the first year of the Fund (2026/27) as a transition period and for 2026/27 they wish to use the structures already in place to deliver the SPF (lead local authority (Cyngor Gwynedd) working with the other counties within the region) to deliver the Local Growth Fund.
2.8From 2027/28, they intend to allocate most of the funding to the Corporate Joint Committees (CJCs) to plan and manage a portfolio of regional and local projects. This will be part of a three-year regional delivery plan to realise a ten - year vision.
2.9The indicative allocation of the Local Growth Fund for the North Wales region in 2026/27 is £33,781,826 million. 70% of the funding will be in the form of capital.
2.10The Welsh Government wishes lead local authorities to continue in their role for the first year of the Local Growth Fund in order to allow time to prepare for a new system delivered through the Corporate Joint Committees (North Wales Ambition) from 2027/28 onwards. Cyngor Gwynedd is the current lead local authority for the SPF.
2.11A further legal agreement will need to be established between Cyngor Gwynedd and all North Wales counties. The agreement will ensure that individual counties are accountable for their decisions and any financial liabilities arising from them. The agreement will be based on the existing document used for SPF and amended to reflect the requirements of the Welsh Government.
2.12At regional level, it is intended to continue with a Collaboration Board made up of the chief officers of the six counties (together with representation from Ambition North Wales and the Welsh Government) to oversee the delivery of the Local Growth Fund in the North Wales region. The Board will continue to be supported by a Coordination Group of managers in each county who are responsible for the day-to-day operation of the Fund.
2.13Although the Welsh Government is not providing a Local Growth Fund allocation for individual counties, there is a desire to continue with a distribution model based on the same approach as the SPF (reflecting the method used by the Government to allocate 2026/27 funding across the Welsh regions), namely: Conwy 19.4% Denbighshire 20.3% Flintshire 10.4% Gwynedd 19.3% Anglesey 12.7% Wrexham 17.9%. This decision was approved by the North Wales Corporate Joint Committee – Ambition North Wales.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.