AI summaryWrexham's Executive Board has approved a light touch review of the Highway Safety Inspection Policy and Highway Winter Service Policy, continuing both in their current format with minor changes.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoth policies continued with minor changes
MoneyNo new moneyNo new funding allocated by this decision
What happens nextPolicies continue in forceWinter service runs 1 October to 30 April
Who it affectsHighway usersAll users of 1,140km of carriageways in Wrexham
What was decided
The Executive Board agreed to continue supporting the reviewed Highway Safety Inspection Policy, which is mostly unchanged but now includes an annual walked inspection on roads with both carriageway and footway. Report 3.1, 2.1
The Executive Board also agreed to continue supporting the Highway Winter Service Policy, which remains unchanged from the last review. Report 3.1, 2.7
The Board noted this is a light touch review with minor changes, and that current performance supports continuing the policies in their present format. Report P16
Why
The Highway Safety Inspection Policy is based on All-Wales standards and provides a proportionate, risk-based approach to inspection and repair, supported by long-standing case law on highway defects. Report 2.3, 2.4
Performance to date, including improvements since the introduction of hot boxes in 2023, has reduced the need to revisit recently repaired areas, justifying continuation of the current approach. Report 2.5, P16
Both policies were reviewed at the Homes and Environment Scrutiny Committee on 22 April 2026, which recommended them for approval subject to several proposed changes. Report 2.11, 6.1, P40
What happens next
Two additional hot boxes procured in 2026 will bolster the existing fleet for reactive repair work. Report 2.6
The Winter Service Policy continues to run from 1 October to 30 April, with a 22 week driver standby period from 1 November to 31 March. Report 2.8, P171
Scrutiny Committee recommendations, including a future report on utility and planning-related highway policies, an All-Member Workshop on winter maintenance, and adding 'what 3 words' to reporting forms, are to be considered. Report P40
The money
£992 million Total replacement value of carriageway asset (April 2018 estimate) Report 4.1
£1.2m Additional investment in 2020/21 budget for reactive and planned repairs Report 5.2
£250,000 per annum Approximate additional resource for 2022 policy amendment, found within existing budget Report 5.2
5,000 tonnes Salt stock retained, replenished more frequently under 2023 arrangements Report 4.9
approximately 9,000 tonnes Increased salt storage capacity after 2023/24 works Report 4.10
approximately 620 salt bins Salt bins located across the county Report P195
Options considered
Chosen: Continue to support both policies in their current format with minor changes. Light touch review; performance to date supports current approach Report 3.1, P16
Implications
Legal: No legal implications associated with this report. Report 5.3
Staffing: No staffing implications associated with this report. Report 5.4
Financial: No new budget allocation; existing 2022 funding of approximately £250,000 per annum continues within existing budget. Report 5.2
Risk: No risks identified related to the purpose of this report. Report 5.6
Other: No Impact Assessment required, as the report does not present a proposal for decision. Report 5.5
Who and where
All users of Wrexham's 1,140km carriageway network, from strategic routes carrying over 20,000 daily traffic to minor rural lanes Report 2.2, P54
Residents and businesses on approximately 620 salt bin routes not covered by gritting priorities Report P195, P200
Neighbouring authorities (Flintshire, Denbighshire) and trunk road agents through cross-boundary gritting arrangements Report P182, P183, P184, P185
Timeline
2018: Total carriageway asset replacement value estimated at £992 million (April) Report 4.1
2020/21: Additional investment of £1.2m for environment and highways repairs Report 5.2
2022: Executive Board approved renewed Highway Safety Inspection Policy based on All-Wales standard Report 2.3, 4.3, 5.1
2023: Hot boxes introduced; salt stock arrangements changed to 5,000 tonnes with regular rotation Report 2.5, 4.9
2023/24: Salt store improved, increasing capacity to approximately 9,000 tonnes Report 4.10
1 October to 30 April: Winter maintenance period each year (extended if weather requires) Report 2.8
1 November to 31 March: 22 week winter service driver standby period Report P171
2026: Two additional hot boxes procured to bolster reactive repair stock Report 2.6
22 April 2026: Policies reviewed at Homes and Environment Scrutiny Committee Report 2.11, 6.1
12 May 2026: Executive Board approves both policies
Plain English for the jargon
Hot box: Equipment used to carry out improved repairs using heated material rather than cold tar, introduced in 2023.
Priority 1 routes: Main precautionary gritting routes covering trunk roads, A and B class roads, key bus routes and town centre access, totalling 500km or 40% of the network.
Category 1H defect: Critical safety defect requiring response within 2 hours or by end of the next working day.
MetDesk: Weather forecast provider used by Wrexham and other North Wales authorities during the winter period.
Section 58 defence: Legal defence under the Highways Act 1980 allowing a highway authority to show it took reasonable care in maintenance.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item122
Resolved
RESOLVED - That the Executive Board continue to support reviewed policy documents, namely the Highway Safety Inspection Policy (Appendix 1) and the Highway Winter Service Policy (Appendix 2). Reason for decision This is a light touch policy review with minor changes to the policies. Based on the performance to date we will continue to follow the policies in their current format.
Word for word from the decision Wrexham published for this meeting.Source: moderngov.wrexham.gov.uk
To present the Highway Safety Inspection Policy update and a summary of the Environment and Technical Department’s Streetscene Winter Service operations and arrangements to Members of the Executive Board.
Executive summary
Highway Safety Inspection Policy (Appendix 1)
2.1The Highway Safety Inspection Policy (Appendix 1) remains mostly unchanged from the last review. We have included the fact that we conduct an annual walked inspection on all roads where there is a carriageway and footway present. We continue to work to the new All-Wales standards and we are monitoring how this is impacting our carriageways.
2.2The Council manages 1,140km of carriageways. The roads range from busy major roads (typically A and B class roads) to minor rural lanes and residential streets.
2.3In 2022 Executive Board approved a renewed Highways Safety Inspection Policy. This policy was based on an All-Wales standard, and a consistent approach to inspection frequency, intervention levels, categorisations and response times.
2.4The main driver of this policy is to have a highway safety inspection and repair regime that ensures the safety of highway users wherever possible but is proportionate to risk and is achievable. It has been developed based on the principles of risk assessment and the long-established case-law surrounding highway defects. It is considered to provide a practical, proportionate and reasonable approach to the risks and potential consequences.
2.5The introduction of ‘hot boxes’ in 2023 have allowed us to carry out repairs in a way that ensures an improved repair to cold tar when responding to surface defect tickets. We have seen an improvement in the quality of our highway network and are seeing a reduction in the need to return to areas recently repaired.
2.6In 2026 we procured an additional two hot boxes to bolster the current stock. This builds resilience for this method of reactive repair work.
Highway Winter Service Policy (Appendix 2)
2.7The Highway Winter Service Policy remains unchanged from the last review. It sets out the aims and standards to be achieved in respect of the Winter Maintenance service in Wrexham County Borough. It details the facilities and resources available and the method of service provision.
2.8The winter maintenance period commences on 1 October and ends on 30 April (unless there is the need to prolong the period due to weather conditions, this will be considered on an ad-hoc basis). The Authority receives meteorological information from the forecast provider MetDesk and also from the Trunk Road Management Unit.
2.9Since the last review of the policy, work has been completed on improvements to the salt store and the depot from which winter maintenance is delivered. This has allowed us to increase the capacity of salt we are able to store in one location, improving the delivery of the service and speed of deployment.
2.10Additional revenue investment has been given to the department which will ensure a stand-alone vehicle and seasonal resource is ringfenced for filling and replenishing salt bins during the winter maintenance season.
2.11The policies were reviewed at Homes & Environment Scrutiny Committee on 22 April 2026.
Recommendation
3.1That the Executive Board continue to support reviewed policy documents, namely the Highway Safety Inspection Policy (Appendix 1) and the Highway Winter Service Policy (Appendix 2).
Reasons for recommendations
(i) This is a light touch policy review with minor changes to the policies. Based on the performance to date we will continue to follow the policies in their current format.
4. BACKGROUND INFORMATION
Highway Safety Inspection Policy (Appendix 1)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.