Resolved That the Board agrees to delegate authority to the Head of Community Services and Head of Resources, in consultation with the Executive Board Member for Resources, to enter into a Procurement Support arrangement with Worcester City Council based on the terms set out in the report.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1External procurement professional support is required to provide the Council with general procurement advice and in particular to assist with the re-tendering of a number of major contracts, including Waste and recycling, grounds maintenance and public toilet cleaning. This report sets outs details of a proposal for support from the Procurement team at Worcester City Council.
Recommendations
2.1Agree delegated authority be given to the Head of Community Services and Head of Resources in consultation with the Executive Board member for Resources to enter into a Procurement Support arrangement with Worcester City Council based on the terms set out in the report.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes – Effective procurement services are an essential element to an excellently run Council (Priority 3) and in particular ensure we use our money effectively and efficiently (Goal 2).
3.2Resource Implications
- Financial implications – Funding upto £50,000 per year for 2006/07 and 2007/08 identified in the approved budget. The proposal provides value for money as a shared service arrangement, with the Council benefiting from expertise being provided at a significantly reduced rate compared to private sector consultants (srs).
- Staffing implications – External advice will support existing staff resources plus provide training and development support for appropriate Council staff. E:\moderngov\data\published\Intranet\C00000314\M00001959\AI00006468\17Procurement0.doc - Risks – Employment of external professional Procurement support will help reduce risks, achieve efficiency savings and in ensure that the Council conducts procurement activities in line with new EU procurement regulations.
- Legal – same as risks.
- Property - none
Background
4.1Since the early 1990s our key frontline services have been market tested and let to a range of private contractors. Many of these services are now requiring re-tendering in order to demonstrate that best value is achieved. Key contracts include :
- Waste, recycling and street cleaning. New contract start date 1 March 2008.
- Grounds maintenance. New contract start date 1 March 2008.
- Public toilet cleaning. New contract start date 1 March 2007.
It’s been sometime since these contract were originally let and following a review of the in house skills it has been identified that whereas staff have good knowledge of contract monitoring and the development of contract specifications we have a requirement for support on the following :
o Guidance with the development of a detailed procurement work programme foe each of the contracts.
o Compliance with new EU procurement requirements.
o Advice with the advertising of the contracts.
o Support with contract negotiations.
4.2In addition to these contracts the Council has a number of other procurement support needs prompted by the National Procurement Strategy and the Efficiency Agenda. These include implementing SMARTer procurement practices such as e-procurement and identifying and progressing opportunities for collaborative procurement with other authorities/partners in order to realise savings.
4.3Support is required April 2006 until March 2008. The recently approved budget identified financial support towards procurement of upto £50,000 for both 2006/07 and 2007/08.
4.4Worcester City Council employ a small team of professional procurement experts who have been very successful in identifying savings. In addition to supporting the City Council they also offer consultancy services to other local authorities. In particular a significant agreement exists with Bromsgrove DC. This is a current successful form of shared services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.