Resolved
Resolved That the Board proceed with the scheme for 2 CCTV cameras in Broadway.
Executive Board decided this item on Tuesday 16 May 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the Board proceed with the scheme for 2 CCTV cameras in Broadway.
1.1This report sets out the current situation regarding proposals to instal CCTV cameras in Broadway.
2.1That the Board proceeds with the scheme for 2 CCTV cameras in Broadway.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
Priority 1 – healthy and safe communities with a good quality environment.
3.2Resource Implications
- financial implications - the original programme option for a scheme for 4 cameras was £70,000 including a £7,000 contribution from Broadway businesses and the Parish Council. The contributions have been received and to date none of the total capital sum available has been spent.
The estimated costs of the installation of the two cameras mentioned in section 4 of this report have been set at some £55,400. Whilst this expenditure could be contained within the original sum approved it would not be possible to fully fund the originally intended scheme for the installation of four cameras without additional capital funding in the order of some £25,000 being identified. dmt
- staffing implications – none arising directly from this report. - risks - if the CCTV scheme does not proceed there are risks to our reputation as not delivering the scheme; and a risk that crimes in the areas will not be detected.
- Legal – none arising directly from this report. Officers have applied for planning permission etc in accordance with legal requirements.
- property – none.
4.1As part of the 2004-05 budget a sum of £30,000 capital was allocated to installing 2 CCTV cameras in Broadway. This was the first part of a potentially larger scheme of 4 cameras, estimated to cost £70,000. Businesses and the Parish Council in Broadway committed to contribute £7,000 towards the scheme.
4.2Planning permission was obtained for 2 cameras in September last year, placed at sites which ourselves and the Police consider to be potentially most effective. However, English Heritage had voiced very strong concerns about the proposals and we were involved in discussions with them about the design and scale of the equipment.
4.3We have reduced the height of the columns supporting the cameras, but need to keep a wider base both to prevent them swaying in strong wind, and to house the necessary equipment to control the cameras. We could use a narrower column, but would then have to have a BT street cabinet close by to house the transmission equipment.
4.4We have tried to find a less potentially intrusive design, but have to balance this against the practical issues involved with running a CCTV system.
4.5The costs for the scheme have been confirmed as part of this work. These have come out as follows:
£
Camera equipment, installation inc 20, 300 street works licenses
Works to electricity system 2,000
BT costs 33,100
Total 55,400
4.6The costs are therefore £25,000 above Wychavon’s budget for two cameras.
4.7Whilst looking for a more acceptable design, we also put considerable effort into looking at alternative technical schemes to try and reduce costs. We focussed on transmission costs represented above by the BT element. The scheme as proposed above uses one transmission line per camera to keep control of the camera and see “live” images rather than time lapse. This is consistent with the current system in our town centres.
4.8We explored using radio transmission and alternative BT lines – but the latter relied on more advanced Broadband being rolled out across the District, which it isn’t yet. We could reduce the number of BT lines used, and therefore the cost, but this would not give live images to the same quality as the rest of our system.
4.9We are now at a point where we need to decide how to proceed. Expectations in the village have been raised by the proposal and recent ram raids on commercial properties have raised the profile of the scheme among residents.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Broadway CCTV UpdateReport | 3 pages | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.