Resolved
Resolved That the Public Convenience cleansing contract with Mitie Cleaning Midlands is extended by two months to 31 st May 2007.
Executive Board decided this item on Tuesday 11 July 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved That the Public Convenience cleansing contract with Mitie Cleaning Midlands is extended by two months to 31 st May 2007.
1.1The Executive Board agreed last year to put the Council’s Public Convenience cleansing contract out to a new competitive tender with a new contract in place from March 2007. A Contracts Team has now been successfully established and a detailed timetable for the Public Convenience cleansing tender established. In order to meet procurement regulations and good practice (including a 3 months mobilisation after contract award) it is recommended that the new contract starts on 1 June 2007. Consequently agreement is sought to extend the current contract with Mitie Cleaning Midlands to 31st May 2007.
2.1That the Public Convenience cleansing contract with Mitie Cleaning Midlands is extended by two months to 31st May 2007.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes – Priority 3 Goal 2 : Use our money effectively and efficiently.
3.2Resource Implications
Financial Implications – The negotiated contract extension will, as in previous years, have to take account of retail price index and national minimum wage increases. This plus the results of the competitive tendering process will be incorporated into the overall budget setting exercise for 2007/08.
Staffing Implications – Existing staff with procurement support from Worcester City Council as agreed by Executive Board on 16th May 2006.
Risks – The risk of not taking this recommendations is that the Council would be exposed to challenge from the Audit Commission E:\moderngov\data\published\Intranet\C00000314\M00001966\AI00006873\11PublicConveniencesExtend0.doc and other contractors of not meeting it’s Best Value duties under UK and European laws.
Legal – set out in the report.
Property – The continuation of a high standard of cleansing service benefits the planned repairs and maintenance regime and in many cases reduces the likelihood of vandalism of our assets.
4.1Officers working with specialist procurement support from Worcester City Council (approved 16th May 2006) have now identified a detailed timetable for the re-tendering of the Public Convenience Cleansing contract. This programme takes into account procurement regulations and good practice. Key dates include the following :
• Notice published in OJEU – 4th September 2006.
• Closing date for responses to OJEU – 12th October 2006.
• Appraisal of responses and the creation of a shortlist completed – 21st October 2006.
• Executive Board approval of shortlist – 14th November 2006.
• Issuing of tenders – 15th November 2006.
• Closing date for tenders - 29th December 2006.
• Tender evaluation and selection completed – 17th January 2007.
• Executive Board approval of tender – 6th February 2007.
• Contract Award – 7th February 2007.
• Mandatory standstill period – 23rd February 2007.
• Issue contract award 24th February 2007.
4.2An additional 3 months has been added to allow the successful contractor to mobilise their resources to deliver the contract. This particularly takes into account the recruitment and training of staff. Consequently it is recommended that the new contract should start from 1st June 2007. In order to meet this timetable it is recommended that the existing contract with Mitie Cleaning Midlands is extended from 31st March 2007 to 31st May 2007.
E:\moderngov\data\published\Intranet\C00000314\M00001966\AI00006873\11PublicConveniencesExtend0.doc
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Public Convenience Cleansing ContractReport | 2 pages | DownloadRead as text |
Follow Executive Board at Wychavon and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... | Decided | Open |
| 16 Sep 2026 | Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... | Approved | Open |
| 16 Sep 2026 | Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... | Approved | Open |
| 16 Sep 2026 | Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
| 16 Sep 2026 | Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.