Resolved (1) That the Board noted the report. (2) That the flood alleviation scheme being considered for Little Beckford be abandoned as a result of the Parish Council failing to commit to making a contribution towards the cost of the scheme and resources remain in the Capital Flood Alleviation Programme.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
1.1This reports sets out the results of the requests to Parish Councils for contributions towards the cost of the flood alleviation works within their Parishes in line with Council Policy.
Recommendation
2.1That the Board notes the report.
2.2That the flood alleviation scheme being considered for Little Beckford be abandoned as a result of the Parish Council failing to commit to making a contribution towards the cost of the scheme and resources remain in the CFAP.
3. Implications and Impact
3.1Council Priorities and Community Plan Themes
The Capital Flood Alleviation Programme supports Priority 1 – Healthy and safe communities with a good quality environment and Priority 3 - Reaching out to everyone. In accordance with the Council’s Flood defence Policy Manual.
Financial implications
There are no additional financial implications as planned works will be financed from provision for flood alleviation within the approved Capital Programme. (VA)
E:\moderngov\data\published\Intranet\C00000314\M00001966\AI00006867\13CapitalFloodAlleviationresultsofcontribution0. doc Page 1 of 1 3.3 Staffing Implications – none at this stage
3.4Risks – Properties will still be at risk of flooding
3.5Legal - None foreseen at this stage – would have been dealt with during the progression of the scheme.
3.6Property - None
Background
4.1Contributions were requested from the four Parish Councils where notional schemes had been identified as being possible and approved by the Executive Board on 1st November 2005. The costs of the notional scheme and amount of contribution requested from each parish council is shown in the Table 1 below.
Table 1
Parish Estimated Amount of Date Confirmed and Council cost of Contribution Requested Date Notional requested Scheme Harvington £120,000 £9,760.95 9th January Yes - 20TH 2006 March 2006 Tibberton £50,000 £4104.45 9th January Yes - 4th May 2006 2006 Bishampton £50,000 £5,716.35 9th January Yes - 6TH March 2006 2006 Beckford £40,000 £4,194.00 9th January NO 2006
4.2The amount of contribution has been calculated in the same way as for all previous schemes i.e. £5.00 at Band D for three years.
4.3In addition to the original letter to Beckford Parish Council dated 9th January 2006 following requests for additional information from the Parish Council further letters in response were written on 26th January, 25th April, 16th May and finally on 19th June 2006. At the time of preparing this report no indication had been received to confirm that a contribution will be made. To date a response to the letter of 19th June has not been received.
4.4Abandoning the flood alleviation scheme will obviously not alleviate the risk of flooding but it will reduce pressure on the CFAP budget and enable a future programme option to be reduced. It is therefore recommended that the Beckford Scheme be abandoned and financial resources remain in the programme.
E:\moderngov\data\published\Intranet\C00000314\M00001966\AI00006867\13CapitalFloodAlleviationresultsofcontribution0. doc Page 2 of 2
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies