Resolved

Resolved That the addition of £120,000 to the capital programme for the in 2009/10 be approved.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Council, 4 pages

Summary

This report outlines the current position of the project and seeks approval to appoint the main contractor. A confidential annexe to the report details the financial matters and a further verbal update will be given at the meeting.

The report also seeks approval for additional expenditure on a combined heat and power unit, which forms part of the building’s energy efficiency strategy, and which will be met via a reduction in the grant to Wychavon Leisure Community Association Limited.

Recommendations

2.1That Alfred McAlpine Capital Projects Limited be awarded the contract for the construction of the new Evesham Leisure Centre.

2.2That the maximum contract sum is £9,302,808

2.3That the Managing Director and Head of Legal & Support Services be authorised to sign the Contract and any other documentation needed as a consequence of recommendations 2.1 and 2.2 above.

2.4That the council approves an addition to the capital programme for the Evesham Leisure Centre in 2009/10 of £120,000.

3. Implications & Impact

3.1Council Priorities & Community Plan Themes - The replacement of the existing leisure centre supports a number of council priorities including health and inclusion and is also one of our 2007/08 promises.

3.2Diversity Impact Assessment - A DIA has been carried out on the project and has previously been reported to the council. The new facility includes measures to continue the positive impact of the council’s leisure provision and to increase participation amongst all community groups. 3.3 Financial Implications - The council’s approved budget includes £10.75m for this project. The additional sum requested in recommendation 2.4 will be offset by an annual reduction in the grant to WLCAL of £10,000 per year. This represents an equivalent return of 8.3% to the council.

3.4Staffing - the project will be managed by the Corporate Projects team including the council’s Clerk of Works.

3.5Risks

The council will be exposed to a number of risks in progressing this scheme. Whilst these have been detailed in earlier reports it is worth reiterating the financial risks.

Once the council signs the contract it will be liable for some residual financial risks within the contract mainly centred around totally unforeseen risks such as undiscovered archaeology or ground conditions. There is however a contingency sum within the scheme budget to cover some of these eventualities, and the legal contract and preliminary site investigations further limit these risks.

The council has been able to transfer the risk of price increases in the statutory undertakers prices to the contractor in return for a small increase in the contract sum. This is considered to be to the council’s advantage as it is no longer responsible for cost increases or co- ordination issues.

The council has included a requirement for a Bond for non performance within the contract sum and has also secured a Parent Company Guarantee as Alfred McAlpine Capital Projects are a subsidiary of the main company.

Legal – The council has used external legal advisors to prepare the contract documentation and support negotiations with the contractors.

The council will be using a modified JCT Design and Build Contract with Contractor design.

Property – The new facility will enable the council to consider reuse or disposal of the current site at Davies Road, this will be subject to a future report to the Executive Board.

Background

4.1Following the decision of the council to proceed with this project, and to approve a budget provision of £10.75m in the capital programme, expressions of interest were invited for the main construction works earlier this year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Evesham Leisure CentreReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Evesham Leisure CentreThis decision
  2. Evesham & Pershore Leisure Centres - Sustainability UpgradesApproved
  3. Planning Application Ref W/24/02507/FUL. Evesham Leisure Centre, Abbey Road, Evesham, WR11 4SU. Full planning application for the installation of PV panels and 2no. air source heat pumps. Wychavon District CouncilApproved
  4. Evesham and Pershore Leisure Centres - Public Sector Decarbonisation SchemeApproved
  5. Evesham Leisure Centre Health and Wellbeing extensionDecided
  6. Planning Application Ref W/16/01392/CU. Land Rear of and including part of, Evesham United Football Club, Cheltenham Road, Evesham. Application for change of use from agriculture to D2 Assembly and Leisure. Proposed use of land for sport pitches. Wychavon District CouncilApproved

More from Wychavon Council

All decisions
MeetingDecisionOutcome
30 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the Council meeting, held on 15 July 2026, be approved as an accurate record of proceedi... Approved Open
30 Sep 2026 Community Governance Review - Defford & Besford Parish CouncilResolved That Council approves the following changes to Defford & Besford Parish Council and recommend that a Reorgan... Approved Open
30 Sep 2026 Community Governance Review - Impney Parish CouncilResolved That Council approves the following changes to the border between Dodderhill Parish Council and Droitwich To... Approved Open
30 Sep 2026 WDC response to the Regulation 19 Publication consultation on the Cotswold Local Plan being prepared by Cotswold District CouncilResolved That the Council endorse the representations from Wychavon District Council to the Cotswold District Local P... Decided Open
30 Sep 2026 Recommendations from Executive BoardResolved That Council approve the budget parameters for the 2027/28 budget, as set out in 3.20 of the report. Health ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies