AI summaryExecutive Board recommends Council approve Evesham full heat pump decarbonisation and Pershore boiler replacement with solar, advancing both to next design stage with an extra £3,200,000 from general balances.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedOption 2 for Evesham, Option 7 for Pershore, to RIBA 4
Money£3,200,000 extra from general balancesOn top of £4,000,000 already set aside
What happens nextRIBA 4 design phaseExpected to take 12 to 14 weeks
Who it affectsEvesham and Pershore leisure centresMechanical, electrical, water and fabric upgrades
What was decided
Executive Board will recommend to Council that Option 2 for Evesham Leisure Centre and Option 7 for Pershore Leisure Centre advance to the next RIBA 4 design phase. Report P10
Council is asked to approve an extra £3,200,000 from general balances for the capital programme, alongside the £4,000,000 already allocated, to fund upgrades to mechanical, electrical, water systems and building fabric. Report P11
Delegated authority is given to the Deputy Chief Executive and Director of Economy and Environment, in consultation with the relevant portfolio holders, to agree the final package of measures after RIBA 4 concludes. Report P12
Why
The two leisure centres are the council's largest sources of emissions, with Evesham at 33% and Pershore at 21% of the total, and much of the mechanical and electrical infrastructure is around 18 to 24 years old and beyond typical life expectancy. Report P5, 1.2, 4.2, 4.3
For Evesham, the chosen full heat pump option delivers the largest carbon saving at 72% and adds resilience to the site's known combined heat and power unit problems. Report 7.2, P36, P37
For Pershore, the chosen like for like boiler option with maximum solar panels avoids major electrical reinforcement works, fits within the flood plain constraints, and leaves room for future electrification, while the building already benefits from local hydroelectric generation. Report 8.2, 8.3, 8.4
What happens next
Commission RIBA 4 detailed technical design, expected to take 12 to 14 weeks, before going to procurement for a contractor. Report P57
Maintain leisure centre operations throughout the construction period, using phased works and temporary services, with completion targeted for 2028 to align with the We Are Wychavon carbon promise deadline of 31 March 2028. Report 9.3, 14.2, 6.3
Engage early with National Grid on the Evesham substation upgrade, which is the main programme risk and could take 12 months, and pursue new planning applications where the design has changed since previous permissions. Report 9.4, P59, P60
The money
£3,200,000 Additional allocation from general balances to the capital programme Report P11
£4,000,000 Already allocated from regeneration reserve for sustainability upgrades Report 1.3, P19
£4,501,906 Total project cost for Evesham Option 2 (chosen) Report P29, P36
£2,985,014 Total project cost for Evesham Option 7 (not chosen) Report P29
£4,127,851 Total project cost for Pershore Option 2 (not chosen) Report P30, P38
£2,590,719 Total project cost for Pershore Option 7 (chosen) Report P30, P38
-£25,384 Estimated annual operational cost difference for Evesham Option 2 versus existing Report P37
-£19,173 Estimated annual operational cost difference for Pershore Option 7 versus existing Report P39
Options considered
Chosen: Evesham Option 2: full decarbonisation with air source heat pumps and maximum roof solar. Largest carbon saving at 72% (525 tCO2) and addresses the site's largest emissions contribution Report P10, P15, 7.2, P37
Rejected: Evesham Option 4: blended heat pump and gas boiler system with maximum solar. Lower carbon saving at 49% (354 tCO2) and still requires electrical reinforcement Report P15, P29, P37
Rejected: Evesham Option 7: like for like gas boiler replacement with maximum solar only. Lowest carbon saving at 6% (43 tCO2), considered insufficient for the priority site Report P15, P29, P37
Rejected: Pershore Option 2: full decarbonisation with air source heat pumps and maximum solar. Requires major electrical reinforcement and has lower relative impact than Evesham Report 8.2, P30, P39
Rejected: Pershore Option 4: blended heat pump and gas boiler system with maximum solar. Still requires electrical reinforcement with only 48% carbon saving Report P15, P30, P39
Chosen: Pershore Option 7: like for like gas boiler replacement with maximum solar only. Lower programme risk, allows future electrification, includes flood resilient relocated plant, 7% carbon saving (52 tCO2) Report P10, 8.2, 8.3, 8.4, P39
Implications
Financial: An additional £3,200,000 is drawn from general balances, on top of the £4,000,000 already set aside, to cover the total project costs of £4,501,906 at Evesham and £2,590,719 at Pershore. Report P11, P29, P30, P58
Climate: Implementing both projects would cut around 580 tCO2e per year from council emissions, lifting the overall reduction from baseline to about 60%, against a 2030 target of 75%. Report 10.2, 10.3, P52
Risk: The main delivery risk is the 12 month National Grid substation upgrade needed for Evesham, while Pershore's flood plain location and energy price volatility also affect viability and costs. Report 9.4, P59, P60, P61, P62
Legal: Previous planning permissions for heat pumps and solar at both sites may need to be reapplied for because of changes in scale and layout, including a new external containerised plant room at Pershore within the flood plain. Report P60
Equalities: No impacts on equalities have been identified through the impact assessment process. Report 14.3
Other: The project supports the We Are Wychavon promise to significantly cut leisure centre emissions by 31 March 2028. Report 14.2
Wychavon Leisure, as operator with expiring energy contracts in 2028 Report 6.3
Council tax payers, as funding comes from general balances Report P11, P58
Timeline
2025: Initial report commissioned and RIBA Stage 2 design work undertaken for options appraisal
February 2026: Council approved up to £4,000,000 from regeneration reserve for sustainability upgrades Report 1.3, P19
24 June 2026: Executive Board recommends preferred options and additional funding to Council Report P1
12 to 14 weeks after approval: RIBA 4 detailed technical design phase to be completed Report P57
2028: Targeted project completion, aligned with We Are Wychavon carbon promise deadline of 31 March 2028 and expiry of Wychavon Leisure energy contracts Report 6.3, 14.2
2030: Intelligently Green target to reduce council emissions by 75% from 2018/19 baseline of 3,066 tCO2e Report P52
Plain English for the jargon
RIBA Stage: Royal Institute of British Architects design phase, from initial concepts (Stage 2) through detailed design (Stage 4) to construction
ASHP: Air source heat pump, an electrically powered heating system that extracts heat from outside air
tCO2e: Tonnes of carbon dioxide equivalent, a standard unit for comparing greenhouse gas emissions
DNO: Distribution Network Operator, here referring to National Grid which manages the local electricity network
CHP: Combined Heat and Power unit that generates electricity and heat together
PV array: Photovoltaic solar panel installation mounted on the roof
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
Resolved That Executive Board recommend to Council that: Option 2 for Evesham Leisure Centre and Option 7 for Pershore Leisure Centre are advanced to the next RIBA 4 design phase, as described in the respective RIBA Stage 03 Reports (Appendix 1 & 2). Council approves allocating an additional £3,200,000 to the capital programme from general balances (further to the £4,000,000 already allocated for sustainability upgrades) to deliver upgrades to the buildings’ mechanical, electrical, water systems and building fabric, in order to ensure the ongoing operation of the leisure centres. Delegated authority be given to the Deputy Chief Executive and Director of Economy and Environment, in consultation with the Executive Board Member for Environment and the Executive Board Member for Resources, Investment and Innovation, to agree final package of measures following conclusion of the RIBA 4 design phase.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
Evesham & Pershore Leisure Centres Sustainability Upgrades – RIBA 3 Report Relevant wards: Evesham North & Pershore Portfolio holder: Cllr Beverley Hardman, Executive Board Member for Environment
Head of Service: Ian Edwards, Director of Economy & Environment
Contact officer: Matt Barker, Carbon Reduction Manager If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 The We Are Wychavon and Intelligently Green plans both set out commitments to significantly reduce Greenhouse Gas emissions from our leisure centres. The leisure centres are the biggest single sources of emissions for the council, with Evesham contributing 33% of the total and Pershore 21%. Therefore, decarbonising these buildings is key to achieving our target to reduce the council’s own emission by 75% by 2030.
1.2In addition, a significant proportion of both building’s mechanical and electrical infrastructure is approximately 18+ years old and has exceeded or is approaching its typical life expectancy. Whilst much of the equipment remains operational, condition surveys and validation assessments have identified a growing requirement for asset renewal, replacement and future lifecycle planning
1.3At the meeting of the Council in February 2026, a resolution was approved to use up to £4,000,000 from regeneration reserve for upgrades at Evesham and Pershore leisure centres to install sustainability upgrades to energy systems. This was to deliver a package of measures that was to be decided pending further detailed design work.
1.4This report sets out the outcome of the detailed design work, the RIBA 3 stage phase of the design, for each of the three heating system upgrade options considered, as well as required building condition and infrastructure upgrades. Each option is presented with an assessment of the expected capital costs, operational cost impact and carbon emission savings.
2. Recommendations 2.1 It is recommended that Executive recommend to Council that:
• Option 2 for Evesham Leisure Centre and Option 7 for Pershore Leisure Centre are advanced to the next RIBA 4 design phase, as described in the respective RIBA Stage 03 Reports (Appendix 1 & 2).
• Council approves allocating an additional £3,200,000 to the capital programme from general balances (further to the £4,000,000 already allocated for sustainability upgrades) to deliver upgrades to the buildings’ mechanical, electrical, water systems and building fabric, in order to ensure the ongoing operation of the leisure centres.
• Delegated authority be given to the Deputy Chief Executive and Director of Economy and Environment, in consultation with the Executive Board Member for Environment and the Executive Board Member for Resources, Investment and Innovation, to agree final package of measures following conclusion of the RIBA 4 design phase.
3. Background 3.1 In 2025 a report was commissioned to gain an understanding of the different options available to upgrade the energy related systems at both Evesham and Pershore leisure centres. As a result, design work to RIBA Stage 2 level was undertaken to appraise the potential suitable heating technologies that could be implemented at both sites, as well as other energy efficiency and renewable energy measures. The subsequent report set out the options available and provided high level analysis of the capital cost of each, as well as the carbon saving and operational cost impacts.
3.2For each leisure centre 7 different options were included presenting varying levels of decarbonisation packages:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.