Executive Board, Tuesday 24 November 2009

Car Parking at Evesham Leisure Centre

Approved Executive 1 paper

Executive Board approved this item on Tuesday 24 November 2009. Below is the council's own wording, with the papers it was decided on.

Item83

Resolved

Resolved 1. That the revised parking charges for the Evesham Leisure Centre Car Park as set out in paragraph 4.5 of this report be approved with effect from the 1 st January 2010, being:- Up to 2 hours 50p Up to 3 hours £2.10 Up to 4 hours £2.80 Up to 7 hours £3.00 2. That the Head of Legal & Support Services be authorised to take all necessary steps to implement the new charges.
Word for word from the decision Wychavon published for this meeting. Source: mgov.wychavon.gov.uk

Follow this further

Built from Wychavon's papers

What the report saysPro

Report to Executive Board, 2 pages

Summary

Members will be aware from a number of press articles that the introduction of normal parking charges from the 1st January 2010 continues to generate considerable opposition from leisure centre users. Following discussions with Wychavon Leisure a potential compromise has been identified which reduces the parking charges to users whilst minimising the financial cost to the council.

Recommendations

2.1That the revised parking charges for the Evesham Leisure Centre Car Park as set out in paragraph 4.5 of this report are approved with effect from the 1st January 2010.

2.2That the Head of Legal & Support Services be authorised to take all necessary steps to implement the new charges.

3. Implications & Impact

3.1Council Priorities and Community Plan Themes

3.1.1 The proposed change to the parking charges will support the Council’s leisure and health objectives.

3.2Resource Implications

3.2.1 Financial Implications - contained within the report. 3.2.2 Staffing Implications – these will be minimal.

3.2.3 Risk Implications – there is a small risk that customers at the leisure centre will limit their stay to ensure they benefit from reduced parking charges.

3.2.4 Legal Implications – there will be additional workload for legal staff as a consequence of this report.

3.2.5 Property Implications – none.

3.3Diversity Impact Assessment – not relevant.

Background

4.1Although the Council has considered the charging structure at the new Evesham Leisure Centre fairly recently we continue to receive a large number of complaints from leisure centre users about the proposed increase from 10p to 70p per hour which is due to occur on the 1st January 2010. Many users have stated they will be prevented from using the facility due to the increased charges and others are considering discontinuing their memberships and reverting to a lower level of casual use.

4.2Wychavon Leisure are also concerned about the proposed increase as the launch of the new leisure centre has been very positively received within the town and levels of usage has increased substantially.

4.3A number of options have been discussed with Wychavon Leisure to see how the needs of the users might be addressed whilst limiting the financial impact on the Council. Options discussed include the introduction of a discounted season ticket, lowering the parking tariffs, introducing a 90 minute band and operating a refund scheme.

4.4Each option has financial consequences for the council as this year’s budget assumes around £30k of parking income from the leisure centre car park and over £100k in 2010/11. Operating a refund scheme is not affordable for Wychavon Leisure without the Council providing considerable financial support.

4.5After much debate with Wychavon Leisure our recommended approach is to reduce the parking charges to £0.50 for the first two hours and then to revert to normal (£0.70 per hour) charges thereafter. This will allow the majority of users to park for a very affordable price as most sessions last less than 90 minutes. By introducing this concession the Council and Wychavon Leisure both hope to increase use of the centre sufficiently to enable the overall grant to Wychavon Leisure to be significantly reduced in future years.

This concession could cost the Council around £50,000 per annum when compared to the charges previously proposed. It is difficult however to be certain of this figure as users may well change their behaviour and limit their use of the leisure centre to less than 2 hours. In order to mitigate the cost of this proposal to the Council, Wychavon Leisure has agreed to reduce their grant from £300,000 to £250,000 in 2010/2011.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Car Parking at Evesham Leisure CentreReport 2 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Wychavon

Search all
  1. Car Parking at Evesham Leisure CentreThis decision
  2. 20/00501/OUT Outline application with some matters reserved for residential development of up to 35 residential units with new access from Village Street, car parking, open space and landscaping; reservation of land for community use at land South of Village Street, HarvingtonAgreed
  3. Planning Application Ref 20/00940/CU. Land At, Willersey Road, Badsey. Change of Use to allow for provision of burial ground, erection of sheds for allotments and car parking to serve burial ground, allotments and community orchard. Badsey and Aldington Parish CouncilApproved
  4. Planning Application Ref 19/00382/FUL. Plots 9 And 10 Keytec East Business Park, Atlas Way, Pershore. Erection of 2 new industrial units complete with associated service yards, car parking and improved landscaping. Crown House Developments LtdAgreed
  5. Report of the Car Parking Task and Finish GroupAgreed
  6. Car Parking Task and Finish Group ReportDecided

More from Wychavon Executive Board

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr... Decided Open
16 Sep 2026 Budget 2027/28Resolved That Executive Board Approves the budget timetable for the 2027/28 budget process, attached at Appendix A, i... Approved Open
16 Sep 2026 Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t... Approved Open
16 Sep 2026 Street Naming and NumberingResolved That the revised ‘ Policy’, as presented in Appendix 1, be adopted. Approved Open
16 Sep 2026 Street Naming and Numbering for Wychavon TownResolved That the street naming and numbering for the development of Wychavon Town, delineated by the allocation in t... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies