Resolved 1. That the Old Medical Centre at Lower Priest Lane , Pershore, be demolished as soon as possible. 2. That the Deputy Managing Director be authorised to submit any applications needed to progress this project, including a Planning Application under Article 3 of the Town and Country Planning General Regulations 1992 should it be necessary or desirable. RECOMMENDED to COUNCIL That an additional £30,000 be added to the Capital Programme for this scheme.
Word for word from the decision Wychavon published for this meeting.Source: mgov.wychavon.gov.uk
This report seeks approval to demolish the Old Medical Centre as it is no longer needed for redevelopment.
Recommendations
2.1That the Old Medical Centre at Lower Priest Lane, Pershore is demolished as soon as possible.
2.2The Deputy Managing Director be authorised to submit any applications needed to progress this project including a Planning Application under Article 3 of the Town and Country Planning General Regulations 1992 should it be necessary or desirable.
2.3That it is recommended to Council that an additional £30,000 is added to the Capital Programme for this scheme.
3. Implications & Impact
3.1Council Priorities and Community Plan Themes
3.1.1 The redevelopment of the site for social housing is a Council priority.
3.2Resource Implications
3.2.1 Financial Implications - contained within the report.
3.2.2 Staffing Implications – these will be minimal. 3.2.3 Risk Implications – the usual range of building risks will be dealt with but the greater risk is that an intruder enters the building and injures themselves.
3.2.4 Legal Implications – some support will be needed in letting the demolition contract.
3.2.5 Property Implications – contained within the report.
3.3Diversity Impact Assessment – not relevant.
Background
4.1The Council acquired the old medical centre site as part of the Pershore Hospital scheme. The intention has always been to redevelop part of the site for social housing but it is now clear that the building is no longer worth retaining for that purpose.
4.2Any housing redevelopment is likely to be at least 12-18 months away due to funding delays which given the ongoing vandalism of the building is too long to wait. The Council is at risk of an unauthorised person entering the building and injuring themselves, despite the building being made secure. It is therefore recommended that the building is demolished as soon as possible.
4.3The cost of demolishing the building and making good the site is estimated at £30,000. As this is an unforeseen cost, it will be an addition to the Capital Programme.
4.4The Council should be able to recover the cost when the site is redeveloped for social housing. If not, an open market sale of the site could be considered.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingResolved That the minutes of the meeting of the Executive Board held on Wednesday 24 June 2026 be confirmed as a corr...
Health Suite Pershore Leisure CentreResolved 1. That the Executive Board considers the report to refurbish the Pershore leisure centre health suite and t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.