Children and Young People's Services and Advisory Panel approved this item on Thursday 8 June 2006. Below is the council's own wording, with the papers it was decided on.
Members considered a report which presented the final out-turn position of the 2005/06 Education Capital Programme. It included details of: · changes to existing schemes to allow the more effective management and monitoring of the future Capital Programme · new externally funded schemes and sought approval for their addition to the 2006/07 to 2008/09 Education Capital Programme · the financial slippage to or from future financial years Advice of the Advisory Panel: That the Executive Member be advised to; · note the capital programme outturn for 2005/06 as highlighted in the report and summarised in Annex A. · approve the slippage to and from financial years to allow the effective monitoring of the schemes. · agree the revised capital programme as shown at Annex A, subject to the approval of the Executive. Decision of the Executive Member:
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Summary
1 The purpose of this report is to: • inform Members of the final out-turn position of the 2005/06 Capital Programme • advise Members of changes to existing schemes to allow the more effective management and monitoring of the future Capital Programme • inform Members of any new externally funded schemes and seek approval for their addition to the 2006/07 to 2008/09 Education Capital Programme • inform Members of any financial slippage to or from future financial years.
2 The report sets out the capital outturn for 2005/06 against the approved budget. The individual scheme variances are detailed in Annex 1, but in summary the outturn of the 2005/06 Education Capital Programme is £7.982m, against the current approved budget of £9.082m, an underspend of £1.100m (12.1%).
Background to the 2005/06 Capital Programme
3 The original capital programme for the financial year 2005/06 was approved at Council on 22 February 2005. Since then a number of amendments to the programme have been approved as part of the 2004/05 out-turn report and the two in year monitoring reports. This results in a current approved Education capital programme for 2005/06 which shows gross capital expenditure of £9.082m with £8.300m of other funding, giving a net capital programme cost to the authority of £0.782m. Table 1 below details the approved changes to the 2005/06 capital programme since the original programme was approved in February 2005.
Table 1- Current Approved Education Capital Gross Other Net Programme Spend Funding Spend £m £m £m Original Capital Programme 2005/06 11.422 (10.545) 0.877 Slippage and adjustments re 2004/05 Outturn report 0.086 (0.115) (0.029) Adjustments at Urgency Committee 12/07/05 (0.003) 0.003 0.000 Adjustments from first Monitoring Report (0.210) 0.210 0.000 Adjustments from second Monitoring Report (2.213) 2.147 (0.066) Current Approved Capital Programme 2005/06 9.082 (8.300) 0.782 Consultation
4 Not applicable
Options and Analysis
2005/06 Capital Programme Outturn
5 The outturn of the 2005/06 Education Capital Programme is £7.982m, financed from £7.408m of external funding, resulting in a net cost to the Council of £0.574m.
6 Budget slippage in to 2006/07 is £1.345m. This is comprised of £1.514m of slippage on schemes from 2005/06 to 2006/07, which is reduced by “reverse” slippage on schemes from 2006/07 to 2005/06 of £0.169m.
7 The schemes where there are significant variances between the current approved capital budget for 2005/06 and the final outturn are discussed in paragraphs 8 to 18 below.
Fulford Secondary School Targeted Capital 8 The second phase of the Fulford project is complete and has been well received. Some final issues around heating and the amount of the final retention remain to be settled in 2006/07, necessitating the slippage of £40k, however the project overall is expected to deliver a saving of approximately £37k.
Applefields Special School Targeted Capital 9 The project is substantially complete and running well, but there is still some outstanding expenditure required on internal equipment, external ground works and the retention on the main contract totalling £188k.
Huntington Secondary School Improvements 10 Extended negotiations on the scope and cost of the project mean that work on site did not commence until April 2006. The bulk of the expenditure will therefore now take place in 2006/07 requiring slippage of £546k.
NDS Modernisation 11 The overall modernisation programme requires combined slippage of £442k. The individual projects within this programme which have resulted in this slippage are discussed in paragraphs 12 to 18 below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.