Advice of the Advisory Panel That the Executive Member for City Strategy be advised to agree to the adjustments set out in Annex 1 and 2 subject to the approval of the Executive to the proposed funding changes. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City Strategy and 17 July 2006 the Advisory Panel
Report of the Director of City Strategy
CITY STRATEGY CAPITAL PROGRAMME 2006/07 – CONSOLIDATED TO INCLUDE CARRY-OVERS FROM 2005/06
Summary 1. The purpose of this report is to consolidate the 2006/07 programme to include the carry-over schemes that were not completed in 2005/06, and to make adjustments to schemes and blocks to reflect individual underspends and overspends within the programme. The report asks the Executive Member for City Strategy to approve the amendments to the 2006/07 budget as set out below.
2. The Planning and Transport Capital Programme has been renamed as the City Strategy Capital Programme to reflect the new Council structure.
Background 3. The City Strategy Capital Programme budget for 2006/07 of £10,464k was agreed by the Executive Member in April 2006, and includes the Local Transport Plan Capital Programme allocation of £6,378k, and other elements allocated funds through the Council’s budget process. These figures do not include overprogramming, which was set at £1,900k (including £270k of structural maintenance reserve schemes) in the 2006/07 budget report.
4. The 2005/06 Planning and Transport Capital Programme contained a level of overprogramming of £3,358k at consolidated report stage of 2005/06 to give some flexibility in the programme should slippage in some schemes occur. Because of this it was never intended, nor indeed would it have been possible, to deliver all the schemes programmed in 2005/06. The full programme agreed at Quarter 3 by Members in February 2006 for 2005/06 was £10,504k with a budget of £10,104k. There was therefore £400k worth of work outstanding that could not have been funded by the LTP in 2005/06.
5. For this reason it was necessary when planning the 2006/07 programme in early 2006 to take account of schemes that we already knew would slip from 2005/06.
6. The provisional outturn report for 2005/06 was agreed by the Executive Member in June 2006. After including the accruals for schemes undertaken at the end of the year but not paid for until 2006/07, there was an overspend on the LTP funded schemes of £197k, which was funded through the use of developer contributions for part of the Malton Road Bus Priorities schemes.
7. There was an underspend on the non LTP funded programme of £30.6k, which it is proposed to carry forward into 2006/07 together with £25k of funding for Special Bridge Maintenance slipped at Quarter 2.
8. There are a number of schemes which were included in the 2005/06 programme which were not as complete as originally anticipated when the 2006/07 programme was prepared. An allowance for the completion of these schemes needs to be made in the 2006/07 programme, and the proposals are detailed in this report.
9. In addition there are a number of schemes which it is proposed to bring forward into the programme from future years to enable preliminary design work to be undertaken, and allow flexibility in the programme should progress on other schemes be slower than anticipated. These include improvements to the Blossom St/Queen Street junction for pedestrians, cyclists and public transport, and preliminary design works for a funding bid for the items included in the LTP strategy but not possible to fund from the current LTP settlement.
Carryovers into 2006/07 10. Known slippage in 2005/06 arising from previous monitoring reports or late changes in the programme were included in the 2006/07 programme when it was presented for Members consideration in April 2006. An indicative figure (£100k) for further carry-over due to remaining overprogramming was also included.
11. An important part of capital programme management is to ensure that any underspends or overspends within particular schemes or spending blocks at outturn are considered and the 2006/07 budget adjusted accordingly. Following the final outturn, the carry-overs can now be built in to the existing approved programme for 2006/07.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.