Advice of the Advisory Panel That the Executive Member for City Strategy be advised to; (i) Note the report. (ii) Note the main recommendations in the Code of Practice 'Well Lit Highway' 2005, and note and approve the current progress towards meeting these recommendations, as set out in Annex 1. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for 17 July 2006 City Strategy and the Advisory Panel Report of the Director of City Strategy
CODE OF PRACTICE FOR HIGHWAY LIGHTING MANAGEMENT Summary 1. This report provides a brief overview of the code of practice ‘Well Lit Highways November 2004’ and asks Members to note and approve the recommended standards of highway lighting management.
Background 2. The Annual Highway Maintenance Report, 2 May 2006, included a reference to three new Codes of Practice:
• ‘Well-maintained Highways’: Code of Practice for Highway Maintenance Management, July 2005 • ‘Well-lit Highways’ Code of Practice for Highway Lighting Management, November 2004 • ‘Management of Highway Structures’ Code of Practice, September 2005
This report considers the second of these three Codes of Practice.
3. The first Code of Practice for Road Lighting endorsed by the local government associations was published in 1999 and has subsequently been revised by this edition to take account of new and emerging developments in technology, policy and good practice incorporating changes in legislation and standards.
4. The Code covers the provision and maintenance of a street lighting service with reference to legal obligations and best practice within the industry. The code also touches on service level agreements with Distribution Network Operators, and the procurement of contracts within the street lighting arena.
5. The Code emphasises the use of best value systems including asset management and make a series of recommendations to achieve this.
6. The current highway lighting management system is based on the previous Code of Practice along with a number of advances based on technical reports issued by the Institute of Lighting Engineers (ILE) and Institute of Electrical Engineers, built up over a period of time. This can be summarised as: • A prioritisation of works and systems based on ILE technical reports, current design regulations, previous codes or best practice and current recommendations along with local knowledge.
• Visual inspection of the street lighting and illuminated network timed once a month in summer and twice in winter.
• A number of reliable and publicised means by which members of the public and other users can report defects and other concerns regarding the highway; the most popular being the freephone number displayed on all equipment and the York Pride Action Line.
• Reactive attendance of all faults determined by severity or risk. Standard faults are attended within two working days and Emergencies within two hours.
• Routine programmed maintenance in line with best practice (dependant on budgetary constraints).
• Monitoring and approval of specifications and levels in all systems related to current regulations.
7. Improvements to the current system and ways of working are always being evaluated and will be subject to a specific report to be brought before Members in September.
Options 8. Option 1 - Members note the report and approve the measures being taken to comply with the recommendations as set out in Annex 1.
Option 2 - Members note the report and suggest any changes they would like to see be included in relation to the recommendations.
Option 3 - Members note the report and reject compliance with the Code and its recommendations.
Analysis
9. The advantages of option 1 are strong and re-enforce systems already underway but to summarise:-
The inspection and maintenance regimes currently practised by the Council have been developed in accordance with
• The code of practice ‘Well Lit Highways’ and preceding documents • Council policies and objectives • Local knowledge of the Street Lighting network • Financial and staff resources available 10. With the use of the ILE's Technical Report No. 22 relating to column conditions as set out in the Code, proactive management of lighting stock and risk can be improved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.