(i) That Option 2 be approved and the Corporate Landlord be asked to consider investment options for the Guildhall, in response to the report, as part of the administrative accommodation review. Since the accommodation review had yet to look at long term options for the Guildhall, a report be brought back to the Executive Member for Corporate Services and Advisory Panel within 3 months, which concentrates on short term options which have a “pay back” by 2011. The long term options for the Guildhall complex be considered as a part of the accommodation review.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. This report seeks to update Members on recent observations made in respect of facilities at the Guildhall and the possibility of a case for future investment
Background
2. The Guildhall is central to the City Council’s accommodation and offers an impressive venue for up to two hundred people.
3. The building is available for hire by internal city council departments as well as external hirers and is used for a diverse range of community activities from awards ceremonies, to concerts and a number of antique fairs.
4. Due to its city centre location and the reasonable rate of hire the Guildhall is a very popular venue and demand for hire far surpasses availability. It is also important to point out to Members that in the conditions of hire the Council holds the right to cancel any event if the Council requires use of the venue for an important City Council event. For example a number of external hires have recently been cancelled due to use of the Guildhall for public inquiries.
5. The Guildhall annual income target for 2006/07 is £16K and if this target has been over achieved in the past then this has been re-invested in the hall to purchase essential items of equipment. New chairs were supplied in 2004/05 and a new laptop and panel partitions purchased in 2005/06. It is anticipated that new trestle tables will be purchased in the current financial year.
6. Without doubt the Guildhall has a number of shortfalls but it also should be recognised that this is a Grade 1 Listed Building and therefore refurbishment may be difficult. Briefly these shortfalls are as follows:
• Toilet facilities inadequate in that there are only two toilets for this part of the Guildhall and one of these being on the first floor • A poor heating system which in winter is totally inadequate for a hall of this size • The maximum power that can be supplied from the Guildhall is only 4kw in total • There is no permanent hearing loop only a temporary loop is available which does not work well with the acoustics of the hall • No public address system • There are no facilities for catering. The basement area is unsuitable for food preparation as it frequently floods and the hygiene levels are unsatisfactory
7. The Food and Drink Festival used the Guildhall for a number of events in September 2005 and as a result of this the Director of the festival on behalf of First Stop York has written to the Chief Executive making a number of observations regarding the facilities at the hall and putting forward a case for investment. These observations can be found at Annexe A.
8. The Council is in the process of implementing an administrative accommodation strategy to rationalise it’s current property portfolio from 16 buildings down to just 4. The strategy includes the retention of the Guildhall as the historical centre of the authority and in the short to medium term it is envisaged that the majority of member facilities will continue to be located here
9. As part of the overall strategy the future layout and use of the Guildhall will form part of a study to determine the future accommodation needs of the council. The outcome of the study will inform the overall design brief for the council’s future accommodation which will include a new headquarters building at Hungate.
10. The study is scheduled to be completed at the end of 2006 when the future use of the Guildhall and any associated works will be identified and included as part of the entire accommodation project.
Options
11 Option One - Members may decide that no future investment in the Guildhall is appropriate
12 Option Two – Members may ask the Corporate Landlord to consider investment options for the Guildhall in response to this report as part of the administrative accommodation review.
Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.