The Future of York's Guildhall and Riverside - Project Update Report

Agreed Executive 5 papers

Executive agreed this item on Thursday 30 July 2015. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

That the Executive agree: (i) A commitment to improved public access to and interpretation of the historic core of the complex – The Guildhall Main Hall, the Council Chamber, a new riverside courtyard garden and historic Common Hall Lane, in accordance with the recent Heritage Lottery Fund (HLF) bid. (ii) To continue with ongoing project development work including: the procurement of a multi disciplinary design team to progress design and development work. (iii) To commission a specialist property agent to: establish the value of the commercial riverside elements of the scheme; advise the design team and market test the proposals. Agree the principle of long leases (typically 25 – 99 yrs) on peripheral elements of the complex (the South Range restaurant and the new build cafe/bar on the north end). (iv) To initiate a review of the feasibility work and business case assumptions relating to the office elements of the scheme as presented to Cabinet in December 2014 / and Scrutiny Call-in in January 2015. Requesting an early report back to Executive in September 2015 on the most commercial and viable options for this element of the complex. Reasons: ( i ) In the interests of securing improved public access for residents and visitors, for the future, and maximising the civic and community value of the Guildhall through improved understanding and appreciation of its historic significance, aligning with the Mansion House Opening Doors project. (ii) To ensure that the optimum beneficial re-use of the complex is properly investigated and that project delivery does not suffer unnecessary delay. (iii) In the interests of optimising the value and long term sustainability of a publicly accessible riverside with an attractive commercial offer to complement the inherent historic interest of the complex. (iv) In the interests of securing the optimum future value for the council from one of its most significant property assets and minimising delay to the project delivery. That the Executive agree: (i) A commitment to improved public access to and interpretation of the historic core of the complex – The Guildhall Main Hall, the Council Chamber, a new riverside courtyard garden and historic Common Hall Lane, in accordance with the recent Heritage Lottery Fund (HLF) bid. (ii) To continue with ongoing project development work including: the procurement of a multi disciplinary design team to progress design and development work. (iii) To commission a specialist property agent to: establish the value of the commercial riverside elements of the scheme; advise the design team and market test the proposals. Agree the principle of long leases (typically 25 – 99 yrs) on peripheral elements of the complex (the South Range restaurant and the new build cafe/bar on the north end). (iv) To initiate a review of the feasibility work and business case assumptions relating to the office elements of the scheme as presented to Cabinet in December 2014 / and Scrutiny Call-in in January 2015. Requesting an early report back to Executive in September 2015 on the most commercial and viable options for this element of the complex. 1/2. Reasons: ( i ) In the interests of securing improved public access for residents and visitors, for the future, and maximising the civic and community value of the Guildhall through improved understanding and appreciation of its historic significance, aligning with the Mansion House Opening Doors project. (ii) To ensure that the optimum beneficial re-use of the complex is properly investigated and that project delivery does not suffer unnecessary delay. (iii) In the interests of optimising the value and long term sustainability of a publicly accessible riverside with an attractive commercial offer to complement the inherent historic interest of the complex. (iv) In the interests of securing the optimum future value for the ... view the full minutes text for item 21.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive, 31 pages

Version 11

Notes on completion Summary

Name of your organisation City of York Council

Project title In no more than 15 words, please choose a title which you think best describes your project. This will be seen externally, on our website and by our decision makers so please ensure that you choose a title that you are happy for a wide range of people to see. York Guildhall and Riverside - Telling York's Story from its very heart

Reference number HG-15-00467

Project summary In no more than 150 words, summarise your project. We will use this text to tell people about your project, including our decision takers. York has a unique opportunity to present its story: to narrate the history of the city, its guilds and commercial heritage, city governance and democratic life, on a site which has been pivotal since pre-Roman times. This project will create a new heritage destination, a fully interpreted route through the site including; the Guildhall, highlighting the guilds’ role in the city’s success, medieval riverside rooms and their stories, the site’s archaeology, access to the hugely significant but currently hidden Common Hall Lane, and to the seat of city governance, the Victorian council chamber. The council’s move from the Guildhall necessitates repurposing the site. This provides a once-in-a-generation opportunity to ensure that its heritage is open to the public and remains central to its future. The project will also facilitate adjacent and complementary commercial uses to secure future sustainable income streams and link with the successful Mansion House ‘Opening Doors’ project.

Have you received any advice from us before making your application? Yes

Please tell us who you received advice from. Fiona Spiers and Louise Clare

Is this your first application to the Heritage Lottery Fund? No

Please tell us the reference number and project title of your most recent application. York Guildhall and Riverside - Digital Media Arts Centre - HE-13-22396

1 Version 11

Section one: Your organisation

1a Address of your organisation: Address line 1 Mansion House Address line 2 St Helens Square Address line 3 Town / city York County Postcode YO1 9QL

1b Is the address of your project the same as the address in 1a? No

Enter the address of your project. Please use the post code look up button to find your address so that the Local Authority and Constituency information is generated in the boxes below.

Address line 1 City of York Council Address line 2 The Guildhall Address line 3 Town / city YORK County Postcode YO1 9QN

Local Authority within which the project will take place York

Constituency within which the project will take place York Central

1c Details of main contact person Name David Warburton

Position project manager

Is the address of the main contact person the same as the address in 1a? No

2 Version 11

Enter the address of the main contact person: Address line 1 West Offices Address line 2 Station Rise Address line 3 Town / city York County N Yorks Postcode YO1 6GA

Daytime phone number, including area code 01904551312

Alternative phone number

Email address [email protected]

1d Describe your organisation's main purpose and regular activities City of York Council - Local Authority

1e The legal status of your organisation

Please select one of the following: Local authority

If your organisation is any of the following, please provide the details shown:

Company - give registration number

Registered Charity in England, Scotland or Wales - give registration number

Charity recognised by HM Revenue and Customs in Northern Ireland - give reference number

1f Will your project be delivered by a partnership? No

1g Are you VAT registered? Yes

Please provide your VAT number GB 647 3650 22

3 Version 11

Section two: The heritage In this section tell us about the heritage your project focuses on and why it is valued.

2a What is the heritage your project focuses upon? The project is focused on York's outstanding Guildhall complex.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 1 pages Download
PDF
Appendix 2Appendix 2 1 pages Download
PDF
Background Paper 1 HLF bidReport 31 pages DownloadRead as text
PDF
Background Paper 2 Options AppraisalReport 42 pages Download
PDF
The Future of York's Guildhall and Riverside: Project Update ReportReport 12 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. The Future of York's Guildhall and Riverside - Project Update ReportThis decision
  2. The Determination of an Application by Futuresound Events Ltd for a Premises Licence (Section 18(3) (a) in respect of York Museum Gardens, Museum Street, York (CYC-084107)in respect of York Museum Gardens, Museum Street, York (CYC-084107) (10:12am)Decided
  3. Plans for the Future of the Health and Care System in YorkNoted
  4. Plans for the Future of the Health and Care System in YorkApproved
  5. York's Creative Future: A Culture Strategy for York, 2020-2025Approved
  6. York Learning: Future DirectionApproved

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies