Resolved
That the advice of the Advisory Panel be accepted and endorsed. REASON: In accordance with budgetary and performance monitoring procedures .
City Strategy and Advisory Panel decided this item on Monday 11 September 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
That the advice of the Advisory Panel be accepted and endorsed. REASON: In accordance with budgetary and performance monitoring procedures .
1 This report presents the latest projections for revenue and capital expenditure by Economic Development, as well as performance against target for:
• Best Value performance indicators • Customer First targets (letter and telephone answering) • Staff Management targets (sickness absence & appraisals completed)
2 This is the first monitoring report for 2006/07 combining financial and service performance information for the Economic Department to be brought to City Strategy EMAP.
3 The performance data included is that which is reported as part of the Council plan each year.
Finance Summary
4 Current projections are that Economic Development will be able to contain its expenditure within the approved budget of £1,843k. However, there are a number of areas where members receive a regular update and these are set out below in paragraphs 5 to 8.
York Training Centre
5 As reported to previous meetings the work of the York Training Centre is dependent on external contracts (wholly funded from external income) and is subject to bi-monthly reviews of their trading position. The significant changes introduced in the last financial year, to deal with reducing external finances, have been fully implemented. However, changes in the funding source for 14-16 learners may have an impact on the scale of activities from the autumn term onwards, necessitating a review of the required scale of activity, and of anticipated income. The impact of this will not be known for a few weeks. Any necessary action will be reported to a later meeting of this Panel.
6 Current projections suggest that a break-even position can be achieved at year-end. The position is being monitored monthly and action will also be focused on 2007/08.
External funding
7 Science City York is bringing forward a proposal to make use of £2.63m of Northern Way funding available through Yorkshire Forward. The proposal would enhance the activities of SCY by creating a series of “Spokes” linked to the existing “Hub” to enable the project to deliver specialist services in at least four sites across the city. A final decision on support for the project can be expected before Christmas.
Markets
8 Members will be aware that over the last two financial years there has been a shortfall in income following reductions in stall take up. It is currently forecast that this will continue resulting in a budget shortfall of c £20k. It is anticipated however that this will be offset by additional income from speciality markets.
Performance Overview
9 Performance indicators for the Economic Development service plan are attached as Annex 1.
10 Where necessary more detailed information is given on the performance of certain indicators on an exception basis below.
Performance indicator Q1 2005/06 Q1 Target Performance Performance 05/06 outturn 06/07 06/07 vs trend vs target CCP3: Percentage of stall take-ups in 72.6% 65.3% 68.7% 75% Newgate Market.
11 CCP3 (The percentage of stall take-ups in Newgate Market) is currently performing below the comparative period in 2005/06 and below the 2006/07 target of 75%. However the indicator is performing above the 2005/06 outturn of 65.3% and has shown improvement in April, May and June by achieving 60%, 71% and 75% respectively. 12 Stall allocations are also dependent on favourable weather conditions. An action plan has been agreed to attract more traders – including additional advertising, customer research, a new market brochure, a customer charter and an enhanced maintenance programme. There will also be action to attract new casual traders to come and stand on the market.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2006/07 First Monitoring Report Economic Development Services: Finance and PerformanceReport | 63 KB | DownloadRead as text |
PDF |
Economic DevelopmentAppendix 1 | 24 KB | Download |
Follow City Strategy and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2009 | MinutesThat the minutes of the last meeting of the Panel held on 27 January 2009 be approved and signed by the Chair and Exe... | Approved | Open |
| 16 Mar 2009 | Core Funding to Voluntary Organisations 2009/10Advice of the Advisory Panel That the Executive Leader be advised to: (i) Maintain the existing grant funding agreeme... | Agreed | Open |
| 16 Mar 2009 | Chief Executive's Monitor 3 Finance & Performance Report 2008/09Advice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... | Noted | Open |
| 16 Mar 2009 | 2008/09 Third Monitoring Report Economic Development and Partnerships - Finance & PerformanceAdvice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... | Noted | Open |
| 16 Mar 2009 | City Strategy Capital Programme - Monitor 3 ReportAdvice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to: (i) Approve th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.