City Strategy and Advisory Panel, Monday 11 September 2006 at 5.00pm

Transport Asset Management Plan

Decided Committee 1 paper

City Strategy and Advisory Panel decided this item on Monday 11 September 2006. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

That the advice of the Advisory Panel be accepted and endorsed. REASON: To demonstrate a whole life approach to the maintenance of highway assets.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to City Strategy and Advisory Panel

Meeting of the Executive Members for City 11 September 2006 Strategy and the Advisory Panel Report of the Director of City Strategy

Transport Asset Management Plan Summary 1. This report presents a draft Transport Asset Management Plan, outlining the documents structure and asks members to endorse and approve its publication in its current form.

Background 2. Infrastructure assets have been defined as the stationary systems (or networks) which support the fabric of modern living, and are taken for granted until something fails or no longer provides the expected service e.g. energy supply systems, water utilities and transport networks.

3. The goal of infrastructure asset management is to meet a required level of service in the most cost effective way. Its key elements are:

• Taking a lifecycle approach

• Developing cost effective management strategies for the long term, providing a defined level of service and monitoring performance

• Managing risk associated with asset failure

• Sustainable use of physical resources

• Continuous improvement in asset management practice.

4. There are a number of drivers requiring the Council to produce a Transport Asset Management Plan (TAMP). These include the Local Transport Plan, Whole Government Accounting, The Prudential Code, Best Value, Codes of practices for highway maintenance, street lighting, structures and the introduction of rethinking construction.

5. The TAMP shall also be used as a supporting document for the highway maintenance PFI expression of interest submission in September 2006. If the bid is successful it will also be used to develop a business plan. 6. The plan is written in accordance with the ‘Framework for Highway Asset Management’, published by the County Surveyors’ Society in April 2004 and 2 copies of the draft TAMP have been placed in the Members Library. The framework is outlined below:

Goals, Objectives & Inventory

 Policies Improvement Actions

1. Starting Point 

Condition Demand  Assessment Aspirations 2. Levels of Service 6. Reporting & Monitoring



Performance Lifecycle 

Gaps Planning 3. Option Identification Performance Measurement



Optimisation & Risk Budget Assessment 

Consideration 4. Decision Making



Forward Work Physical Programme Works & Services  

5. Service Delivery

7. The draft September 2006 plan has been compiled to include stages 1, 2 and 3 with the remainder being developed with the new service provider either through a PFI or other form of long-term highways maintenance procurement.

8. Stages 4, 5 and 6 of the plan will take the options identified in stage 3 and relate them to current budget considerations. The process will identify a link between the level of service and budget allocations. 9. Included within the plan are all the constituent elements of the adopted highway plus local transport assets which the Council has a duty to maintain:

• Carriageways and footways including on-street cycle routes

• Structures – bridges, culverts and retaining walls

• Street lighting including illuminated signs and bollards

• Road markings and signs including coloured surfaces

• Verges, trees and street furniture including bus stops, and barriers and safety fencing that are not associated with structures

• Highway drainage

• Traffic signals and urban traffic control including variable message signs

• Public rights of way

• Car parks

• Park and ride sites

10. The aim of the plan is to demonstrate a whole life approach to the maintenance of the highway assets. The principal behind the plan is to detail the required level of service, determining the existing service level and backlog. Also to establish whole life maintenance regimes to maintain the desired level of service.

Consultation 11. The ‘Framework for Highway Asset Management’ and the ‘Guidance Document for Highway Infrastructure Asset Valuation’ are both national publications. Both documents have received wide scale consultation prior to their publication.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Asset Management PlanReport 76 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
SG
Councillor Steve GallowayCabinet Member, present
AR
Councillor Ann Reid MBECabinet Member, present
CV
Councillor Christian VassieChair, present
TS
Councillor Tracey Simpson-LaingVice-Chair, present
AD
Councillor Andy D'AgorneCommittee Member, present
TH
Councillor Tom HolveyCommittee Member, present
KH
Councillor Keith HymanCommittee Member, present
DM
Councillor Dave MerrettCommittee Member, present

More from York City Strategy and Advisory Panel

All decisions
MeetingDecisionOutcome
16 Mar 2009 MinutesThat the minutes of the last meeting of the Panel held on 27 January 2009 be approved and signed by the Chair and Exe... Approved Open
16 Mar 2009 Core Funding to Voluntary Organisations 2009/10Advice of the Advisory Panel That the Executive Leader be advised to: (i) Maintain the existing grant funding agreeme... Agreed Open
16 Mar 2009 Chief Executive's Monitor 3 Finance & Performance Report 2008/09Advice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 2008/09 Third Monitoring Report Economic Development and Partnerships - Finance & PerformanceAdvice of the Advisory Panel The Advisory Panel advises the Executive Leader to note the financial and performance po... Noted Open
16 Mar 2009 City Strategy Capital Programme - Monitor 3 ReportAdvice of the Advisory Panel That the Advisory Panel advise the Executive Member for City Strategy to: (i) Approve th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies