Children and Young People's Services and Advisory Panel noted this item on Tuesday 12 June 2007. Below is the council's own wording, with the papers it was decided on.
Advice of the Advisory Panel That the Executive Member be advised: (i) That the capital programme outturn for 2006/07 highlighted in this report and summarised in Annex A be noted. (ii) That the slippage to and from financial years be approved to allow the effective monitoring of the schemes. (iii) That the virements between schemes be approved as detailed in the report and shown in Annex A. (iv) That the revised capital programme as shown in Annex A be agreed, subject to the approval of the Executive. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Agenda Item
Executive Member for Education and Children’s Services and 12 June 2007 Advisory Panel
Report of the Director of Learning, Culture and Children’s Services and the Director of Resources
CAPITAL PROGRAMME OUTTURN 2006/07 Summary
1 The purpose of this report is to: • inform Members of the final out-turn position of the 2006/07 Capital Programme • advise Members of changes to existing schemes to allow the more effective management and monitoring of the future Capital Programme • inform Members of any new externally funded schemes and seek approval for their addition to the 2007/08 to 2009/10 Education Capital Programme • inform Members of any financial slippage to or from future financial years.
2 The report sets out the capital outturn for 2006/07 against the approved budget. The individual scheme variances are detailed in Annex A, but in summary the outturn of the 2006/07 Education Capital Programme is £11.788m, against the current approved budget of £12.879m, an underspend of £1.091m (8.5%).
Background to the 2006/07 Capital Programme
3 The original capital programme for the financial year 2006/07 was approved at Council on 1 March 2006. Since then a number of amendments to the programme have been approved as part of the 2005/06 out-turn report and the two in year monitoring reports. This results in a current approved Education capital programme for 2006/07 which shows gross capital expenditure of £12.879m with £11.792m of other funding, giving a net capital programme cost to the authority of £1.087m. Table 1 below details the approved changes to the 2006/07 capital programme since the original programme was approved in March 2006.
Table 1- Current Approved Education Capital Gross Other Net Programme Spend Funding Spend £m £m £m Original Capital Programme 2006/07 13.132 (12.266) 0.866 Slippage and adjustments re 2005/06 Outturn report 1.345 (1.157) 0.188 Adjustments from first Monitoring Report (1.598) 1.631 0.033
Current Approved Capital Programme 2006/07 12.879 (11.792) 1.087 Consultation
4 Not applicable
Options and Analysis
2006/07 Capital Programme Outturn
5 The outturn of the 2006/07 Education Capital Programme is £11.788m, financed from £11.107m of external funding, resulting in a net cost to the Council of £0.681m.
6 Budget slippage in to 2007/08 is £0.762m. This is comprised of £1.167m of slippage on schemes from 2006/07 to 2007/08, which is reduced by “reverse” slippage on schemes from 2007/08 to 2006/07 of £0.405m.
7 The schemes where there are significant variances between the current approved capital budget for 2006/07 and the final outturn are discussed in paragraphs 8 to 32 below.
8 NDS Condition Funding Unexpected retentions on two schemes have caused a £10k overspend on the remaining part of this now ended DfES funded programme.
Fulford Secondary School Targeted Capital 9 The final retention payments have not yet been agreed, necessitating slippage of the remaining budget of £60k into 2007/08.
Applefields Special School Targeted Capital 10 This scheme has now been completed satisfactorily and has generated a budget saving of £97k.
Huntington Secondary School Improvements 11 The new Teaching and Performing Arts blocks were handed over on 16 April and are in full use by the school and community. We are awaiting preparation of the final account which is likely to result in an increase in the overall scheme costs, and the resolution of an insurance claim concerning an element of the design. A budget of £128k needs to be slipped into 2007/08.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.