Advice of the Advisory Panel That the Executive Member for City Strategy be advised : a) To note the contents of the report and outcome of the study; b) Approve that the proposals in paragraphs 57, 59, 60, 61 and 62 of this report, together with improvements linked to the Germany Beck development, should form the basis of the improvement strategy for the corridor; c) To agree that cyclists should be encouraged to use Cemetery Road, Kent Street and alongside the Barbican site rather than the section of the corridor north of the Cemetery Road junction; d) To agree that the proposed improvement measures are further developed, public consultation carried out, and the findings reported back to this panel. e) To approve that Officers review at the earliest opportunity the Fishergate gyratory. Decision of the Executive Member for City Strategy Resolved : That the advice of the Advisory Panel be accepted and endorsed. Reasons : a) For background information and for assisting in the decision making process. b) To improve transport conditions along the corridor for high priority user groups and to minimise environmental impact on the corridor. c) To indicate the cycling strategy for the northern end of the corridor. d) To seek the public views on the proposed improvement measures and to help to develop those measures. e) To progress the scheme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City 29th October 2007 Strategy and Advisory Panel
Report of the Director of City Strategy
FULFORD ROAD CORRIDOR
Summary 1. This report outlines the results of a multi-modal transport feasibility study of the A19 Fulford Road corridor, covering the length from Skeldergate Bridge and Tower Street in the north to the Designer Outlet (just south of the A19 / A64 interchange) in the south together with the associated feeder roads.
2. It identifies the current transport related issues along the corridor and the pressures the corridor will face in the future. It notes that the corridor is already congested at peak periods and, without intervention, there will be significant worsening of conditions in the future.
3. A package of improvement measures are proposed and agreement is sought that these should form the basis of the improvement strategy for the corridor and be developed and taken forward for public consultation.
4. A presentation will be given at the meeting to explain in detail the effects on the corridor. This will include plans of the proposed improvement measures detailed in this report.
5. The report notes that the proposed measures will impact on parking at some locations and, in particular, that continuous cycle facilities are not proposed as there are locations where the removal of on-street parking could have a significant effect on the local area. The report seeks members views on the cycling strategy for the northern end of the corridor.
6. The report also notes that the proposed measures will only address traffic congestion in the short term as there is no long term engineering solution. It identifies that other citywide traffic management measures will be required after 2011 if the proposed engineering measures are to be successful in the future. Members will need to consider this report in the light of air pollution monitoring results that indicate a potential breach of the air quality objective for nitrogen dioxide on a section of the Fulford Road corridor.
Background 7. A study of this corridor was undertaken in 1999 by Colin Buchanan and Partners to identify a package of measures that could be implemented along this corridor. The objective of that work was to improve public transport and non-motorised transport, to reduce congestion, and to improve journey times, air quality and the physical environment.
8. That study identified a package of measures which included extensive bus lanes and bus priority measures in the northbound direction together with sections of cycle lanes in both directions. However the council was not able to progress any of the recommendations at that time due to significant opposition received, which mainly focused on the loss of on-street car parking and the increased severance the measures would have caused.
9. Additional studies have been carried out primarily looking at crossing facilities and bus stop locations on Main Street, Fulford. The outcome has been upgrading of the signalised crossing near Prospect Terrace and an additional refuge island crossing north of Fordlands Road. A decision on an additional crossing near Elliot Court was deferred pending the outcome of the Corridor Study.
10. In addition to the above improvements, modifications have recently been made to the signals at the Hospital Fields Road and Broadway junctions to benefit pedestrians and reduce delay times.
11. A Fulford Road Corridor Study carried out by the Halcrow Group, which also encompassed Fulford Road and Fishergate Gyratory Cycle Route Studies, was commenced in 2005. That study aimed to address the relevant transport related issues along the corridor. It was subsequently put on hold pending a formal decision on the proposed Germany Beck and University expansion developments which would have both had impacts on the corridor.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.