Advice of the Advisory Panel That the Executive Member for City Strategy be advised to : a) Approve the revised proposals as shown in Annex F (in accordance with Option Two above) for implementation in the 2007/08 capital programme; b) Request that Officers report back to an Officer In Consultation (OIC) meeting to authorise the installation of a Vehicle Activated Sign at the north-western entry point to the village (on the Wetherby side), should the monitoring of traffic speeds determine this to be necessary, following the introduction of measures in accordance with Recommendation a) above. c) Request that Officers report back to an OIC meeting to authorise the installation of ‘five-bar’ gate arrangements at the two other entry points to the village (on the York and Askham Richard sides), should this be considered appropriate after assessing the success of this measure on the Wetherby Road approach. Decision of the Executive Member for City Strategy Resolved : That the advice of the Advisory Panel be accepted and endorsed. Reasons : (a) To retain a form of effective traffic calming outside the primary school in order to maintain low vehicle speeds, thereby creating a safer environment for school children and village residents. (b) To enable further steps to be taken to reduce traffic speeds on the approach to the village from the Wetherby direction, should the speed monitoring exercise indicate that average approach speeds are excessive. (c) To enable further steps to be taken to reduce traffic speeds on the approaches to the village from the York and Askham Richard directions, should Officers consider that the ‘five-bar’ gate arrangement has had a positive effect at the Wetherby approach to the village.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Meeting of Executive Members for City 29 October 2007 Strategy and Advisory Panel
Report of the Director of City Strategy
RUFFORTH SCHOOL SAFETY ZONE AND ASSOCIATED SPEED MANAGEMENT MEASURES Summary 1. Following monitoring and consultation, approval is requested to make permanent the two temporary chicanes on the B1224 Wetherby Road, which act as traffic calming measures to slow speeds in advance of the existing School Safety Zone. In addition, to further help reduce the speed of traffic approaching the school from the north-west, approval is sought to extend the existing 30mph speed limit on Wetherby Road.
2. The report also seeks authority to implement a number of other minor signing improvements in the vicinity of the School Safety Zone.
Background 3. In 1999/2000, a study of the traffic problems within the village of Rufforth highlighted concerns regarding traffic speeds. In response, the study report recommended improvements to the 30mph speed limit signing, and that a School Safety Zone should be installed outside the school.
4. In December 2000, the Planning and Transport (North-West Area) Sub- Committee approved a package of measures to improve road safety outside Rufforth Primary School. As part of this, a 20mph School Safety Zone was proposed, covering the section of the B1224 Wetherby Road outside the school. The measures sought to highlight the presence of the school, reduce vehicle speeds, and to make it easier for people to cross the road. The measures included a speed table crossing point directly outside the school’s pedestrian entrance. The scheme was implemented in February 2001. Around this time, some minor improvements to the 30mph speed limit signing at the entry points to the village were also carried out.
5. Soon after the School Safety scheme was installed, residents adjacent to the speed table complained of excessive noise and vibration when large vehicles crossed over the table, affecting their quality of life and raising concern regarding damage to their properties. In response to these concerns, it was agreed that the speed table should be removed and replaced with two pairs of speed cushions, one at either side of a dropped crossing point. This work was carried out in June 2001. 6. Shortly after these amendments were made, a small amount of comment was received, which covered a mix of views. Some living near the scheme said that traffic speeds had increased, and that noise and vibration remained an issue if large vehicles did not straddle the cushions as intended. Other residents were in favour of additional traffic calming measures to reduce traffic speeds through the village. Most residents commented on the need to reduce the amount of heavy vehicles travelling through the village.
7. In response to these ongoing concerns, noise and vibration surveys were conducted, and a report on the findings was produced by the Council’s Environmental Protection Unit in September 2003. The results showed that traffic noise was actually lower than at a control site in the village, away from the traffic calming scheme. They also showed that vibration was not at the high levels necessary to cause structural damage to nearby property. However, vibration did reach levels that are recognised to be perceptible by residents whilst in their properties. The problem is thought to be exacerbated in this particular location because of the relatively high percentage of heavy goods vehicles passing by, which cause the most noticeable effects, and the proximity of some buildings to the carriageway (some being as close as 1.5 metres from the road).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.