Members received a report which outlined the details of the Local Competition carried out, the affordability of the final solution and the arrangements in place for contract administration and monitoring, and sought to gain Executive Member approval to proceed with contract award of the Design and Build contract and the delivery of the new Joseph Rowntree School. The report presented the following options for consideration: · Option 1 – To approve the decision to proceed with award of the Design and Build contract to Carillion to deliver the new Joseph Rowntree School; · Option 2 – To refuse the appointment of Carillion to deliver the new Joseph Rowntree School. Advice of the Advisory Panel That the Executive Member be advised: (i) To appoint Carillion as the Design and Build contractor for the Joseph Rowntree New School project. (ii) To support the progression of the project towards achieving a BREEAM (Building Research Establishment Environmental Assessment) rating of “very good” together with high CO2 reductions. Decision of the Executive Member
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Children and Young People's Services and Advisory Panel
Meeting of Executive Member for Children & 10 June 2008 Young People’s Services and Advisory Panel Report of the Director of Learning, Culture and Children’s Services
Joseph Rowntree New School – Final Business Case
Summary 1. This report outlines the details of the Local Competition carried out, the affordability of the final solution and the arrangements in place for contract administration and monitoring, and seeks to gain Member approval to proceed with contract award of the Design and Build contract and the delivery of the new Joseph Rowntree School.
Background 2. Joseph Rowntree School is a Voluntary Controlled 11-18 specialist Technology College supported by the Joseph Rowntree Housing Trust.
3. The major objectives of the project are to transform education at Joseph Rowntree School by:
• The replacement of Joseph Rowntree School on the existing school site. • Retaining the current net capacity of 1320. • Creating a DCSF demonstration school for Science that reflects the vision for science developed in participation with Project Faraday. • Including provision for a 20 place Autism Unit. • Achieve a BREEAM (Building Research Establishment Environmental Assessment) rating of ‘very good’. • Achieve at least a 60% target for carbon reduction, sufficient for Zero Carbon School funding from DCSF, with the longer term aspiration for a carbon zero school. • Provide a specialist teaching space for the 14-16 Hair and Beauty Diploma. • Support the school to deliver, in the long term, their chosen 14-19 Diploma subjects.
4. The project is a Phase Two One School Pathfinder Project for the Building Schools for the Future programme. The scheme comprises a total new build to replace the Joseph Rowntree School on the existing school site. 5. Joseph Rowntree School is an 11-18 specialist Technology College with a net capacity of 1320. The opening date for the new school building is 01st March 2010.
ANALYSIS
6. This section of the report describes the details of the Local Competition carried out.
7. The Scheme is a Single School Project and includes a design and construction project for the new build project for Joseph Rowntree School.
8. The report demonstrates that the process followed to appoint a Design and Build contractor:
• was in compliance with the standard procedures and processes established by Partnership for Schools (PfS) for the National Framework; • allowed for a sufficiently robust analysis of the proposed solutions of the two bidders; and • was well resourced and CYC’s costs of the procurement process have been minimised and documented.
Short-listing Two Bidders
9. The Preliminary Invitation to Tender (PITT) was sent out to all Partnership for Schools Framework Panel Members on 20th July 2007.
10. Two Panel Members returned a PITT submission, these were:
• Carillion
• Willmott Dixon
11. The principal supply chain members for the two short listed bidders were:
Carillion:
Architect and Design Coordinator – Bond Bryan Consulting Engineers and Environmental Advisers – Buro Happold Landscape Architects – Anthony Walker and Partners
Willmott Dixon:
Architect and Design Coordinator – Aedas Consulting Engineers and Environmental Advisers – Waterman Structures M&E Consultants - Operon
12. Both bids were scored by an evaluation team. The Partnership for Schools Framework had originally procured the six Framework Panel Members on a 60:40 Cost:Quality basis. The PITT responses were evaluated in accordance with the following weightings in order to focus the emphasis on the ability of the design team to meet the Vision for Educational Transformation :
Category Overall Weighting (%) Design 60 Works 20 Handover 10 Pricing 10 Total 100
13. Subsequent to the scoring, both bidders were invited to present to a full evaluation panel. The Project Technical Advisers, Mott MacDonald, advised the evaluation panel.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children and Young People's Services and Advisory Panel at York and we tell you when its next papers are published, before the meeting rather than after it.
Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern...
School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.