CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
City of York Council

Capital Outturn Report 2007/08

Approved Committee 2 papers

Children and Young People's Services and Advisory Panel approved this item on Tuesday 10 June 2008. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

Members received a report which informed them of the final outturn position of the 2007/08 Capital Programme and sought approval for the addition of any new schemes to the 2008/09 - 2010/11 Capital Programme. The outturn of the 2007/08 Children’s Services Capital Programme was £12.897m, financed from £11.370m of external funding, resulting in a net cost to the Council of £1.527m. Budget slippage into 2008/09 was £4.134m. This was comprised of £4.714m of slippage on schemes from 2007/08 to 2008/09, which was reduced by “reverse” slippage on schemes from 2008/09 to 2007/08 of £0.580m. Advice of the Advisory Panel That the Executive Member be advised: (i) To note the capital programme outturn for 2007/08, as shown in Annex A of the report; (ii) To approve the additions and amendments to the capital programme, set out in the report and summarised in Annex A; (iii) To approve the scheme reprofiling and slippage set out in the report and summarised in Annex A; (iv) To agree the revised capital programme, as shown at Annex A of the report, subject to the approval of the Executive; (v) Forward the Panels thanks to Officers for all their work on the capital programme. Decision of the Executive Member
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Children and Young People's Services and Advisory Panel

Summary

1 This report is to:

• inform Members of the final out-turn position of the 2007/08 Capital Programme.

• advise Members of changes to existing schemes and reprofiling of expenditure to allow the more effective management and monitoring of the Capital Programme

• inform Members of any slippage in budgets between financial years

• inform Members of any new schemes and seek approval for their addition to the 2008/09 and 2010/11 Capital Programme.

Background

2 The original capital programme for the financial year 2007/08 was approved at Council on 21 February 2007. Since then, a number of amendments to the programme have been approved as part of the 2006/07 out-turn report, at the Urgency meeting of 3rd July 2007 and following the two monitoring reports. This results in a current approved Children’s Services capital programme for 2007/08 which shows gross capital expenditure of £17.239m with £15.277m of other funding which gives a net capital programme cost to the authority of £1.962m.

3 The table below details the approved changes to the 2007/08 capital programme since the original programme was approved in February 2007.

Table 1- Current Approved Children’s Services Capital Programme 2007/08

Gross Other Net Spend Funding Spend £m £m £m Original Capital Programme 2007/08 16.485 16.225 0.260 Slippage and Adjustments from the 2006/07 2.368 2.052 0.316 Outturn report Amendment at Urgency Meeting 0.798 0.244 0.554 Monitor 1 Adjustments 0.488 0.109 0.379 Monitor 2 Adjustments (2.900) (3.353) 0.453 Current Approved Capital Programme 2007/08 17.239 15.277 1.962 Consultation

4 Not applicable.

Options and Analysis

5 The outturn of the 2007/08 Children’s Services Capital Programme is £12.897m, financed from £11.370m of external funding, resulting in a net cost to the Council of £1.527m.

6 Budget slippage in to 2008/09 is £4.134m. This is comprised of £4.714m of slippage on schemes from 2007/08 to 2008/09, which is reduced by “reverse” slippage on schemes from 2008/09 to 2007/08 of £0.580m.

7 The schemes where there are significant variances between the current approved capital budget for 2007/08 and the final outturn are discussed in paragraphs 8 to 32 below.

Devolved Capital 8 This scheme represents the devolved capital which has been allocated to schools in 2007/08, net of any contributions which the schools have agreed towards LA led schemes.

Fulford Secondary Targeted Capital (Scheme Cost £3.489m) 9 This scheme is now complete with only the retention payment on Phase 1 outstanding. This is still being finalised but is expected to be within the remaining budget. The outstanding budget needs to be slipped into 2008/09.

Huntington Secondary (Scheme Cost £5.674m) 10 The major scheme for the provision of new Teaching and Performing Arts blocks is complete with the new facilities in full use. As reported previously to EMAP, there has been an overspend on the overall scheme, which has been funded from corporate resources. Property Services are currently negotiating a final account and are pursuing some outstanding claims which may result in an improvement to the previously reported figures. Further details will be reported when the negotiations are concluded. The final retention has not yet been settled, therefore an amount of £105k is required to be slipped into 2008/09.

Integrated Children’s Centres (Overall Scheme Cost (£4.871m) 11 The schemes at the five new Children’s Centres are progressing well, although there have been further minor delays at some of the sites, which, although they have not significantly altered final completion dates, have resulted in a reduction in expenditure prior to 31 March 2008 necessitating further slippage of £1,475k above that which was approved at Monitor 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 35 KB Download
PDF
Capital Outturn Report 2007/08Report 60 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 18 attended
CF
Councillor Christina FunnellChair, apologies
JB
Councillor Jenny BrooksVice-Chair, in the Chair, present
AD
Councillor Andy D'AgorneCommittee Member, present
JG
Councillor Julie GunnellCommittee Member, apologies
DM
Councillor Dave MerrettCommittee Member, present
CR
Councillor Carol RuncimanCabinet Member, present
RW
Councillor Richard WatsonCommittee Member, apologies
IW
Councillor Irene WaudbyCommittee Member, apologies
KA
Councillor Keith AspdenSubstitute, present as substitute
JL
Councillor Janet LookerSubstitute, present as substitute
JB
Mr John BaileyCo-opted Statutory Member, apologies
DS
Dr David SellickCo-opted Statutory Member, apologies

All 18 on the meeting page

On this subject at York

Search all
  1. Capital Outturn Report 2007/08This decision
  2. Capital Programme Outturn 2025/26 and Revisions to the 2026/27 - 2029/30 ProgrammeApproved
  3. Capital Programme Outturn 2024/25 and Revisions to the 2025/26 - 2029/30 ProgrammeApproved
  4. Capital Programme outturn (17:11)Noted
  5. Capital Programme Outturn 2022/23 and Revisions to the 2023/24-2027/28 Programme (18:59)Noted
  6. Capital Programme Outturn 2022/23 and Revisions to the 2023/24-2027/28 Programme (18:59)Approved

More from York Children and Young People's Services and Advisory Panel

All decisions
MeetingDecisionOutcome
12 Mar 2009 MinutesThat the minutes of the last meeting of the Executive Member for Children and Young People’s Services and Advisory Pa... Approved Open
12 Mar 2009 Local Authority Governor AppointmentsAdvice of the Advisory Panel That the Executive Member be advised to appoint or re-appoint the Local Authority Govern... Decided Open
12 Mar 2009 Admission arrangements and admission limits for primary and secondary schools in York from September 2010Advice of the Advisory Panel That the Executive Member be advised (i) That the City of York co-ordinated schemes and ... Approved Open
12 Mar 2009 School Term Dates and Holidays 2010/2011Advice of the Advisory Panel That the Executive Member be advised that the pattern of school terms and holidays for 2... Approved Open
12 Mar 2009 Young People's Services: Service Asset Management PlanThat this item be deferred. REASONS: (i) The plan was to be updated in the light of current discussions around the My... Deferred Open