Executive - for meetings from 03/06/00 to 26/04/11, Tuesday 23 September 2008 at 2.00pm

Outer Ring Road Improvement Options

Approved Executive 5 papers

Executive - for meetings from 03/06/00 to 26/04/11 approved this item on Tuesday 23 September 2008. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

(i) That the submission of an Access York Phase 2 bid for funding to the Regional Transport Board based upon a package of citywide measures and the Option B2 improvements to the Outer Ring Road (at grade improvements to all roundabouts from Wetherby Road to Strensall Road), for a total outturn cost of approximately £42m, be approved; (ii) That the requirement for preparatory costs of approximately £500k and a local contribution of approximately £5m if the scheme was approved by the Regional Transport Board and the Department for Transport be noted. REASON:(i) To enable funding to be obtained for improving the transport provision in York; (ii) To enable the commitment to be include in future budgetary considerations.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive - for meetings from 03/06/00 to 26/04/11

Executive 23 September 2008

Report of the Director of City Strategy

Outer Ring Road Improvement Options Summary 1. This report provides the results of a study into the projected performance of the Outer Ring Road and provides options for improvements to be included in a proposed Access York Phase 2 bid to the Regional Transport Board (RTB) for its inclusion in the Regional Funding Allocation (RFA) programme.

2. Members are asked to approve a recommended option for upgrading the Outer Ring Road and to approve the submission of the Access York Phase 2 bid to the RTB by 10 October.

Background Drivers for the Report

3. The Council were informed on 14 August 2008 that detailed bids to the RTB for funding of transport schemes up to 2018/19 must be submitted by 10 October. Less detailed bids which identify problems and possible solutions for delivery after 2013/14 have to be submitted in full by 7 November. It is anticipated that the RTB will make its decision early in 2009 and issue advice to Ministers by February 2009 with a response expected later in 2009. Clearly acceleration of the timescales has been a challenge but officers are confident that a bid can be made in time.

4. Limited funds are currently available for allocation in the Regional Transport Programme equivalent to approximately £400m including 20% overprogramming mostly available towards the end of the 2018/19 period. It is known that the Authorities within the Leeds City Region are proposing to submit bids well in excess of the funds which are available. It is therefore likely that the funding will be substantially oversubscribed suggesting that a lower value bid which fits well with Regional polices will have more chance of success. Evaluation Criteria

5. To ensure that a successful bid is submitted for funding to the RTB it is essential that the key evaluation criteria which will be used to assess the proposal are understood. The following criteria will be used in the evaluation of the bid by the RTB

• Transport National Transport Policy using the Department for Transport objectives in the Towards a Sustainable Transport System guidelines

Regional Transport Strategy which includes an objective to improve accessibility to York City Centre

The Local Transport Plan which has the objectives to reduce congestion and increase use of public transport and improve accessibility for non-car modes.

Economic Growth

The Regional Spatial Strategy identifies the housing and employment growth for York.

• Financial

Value for Money criteria are provided by the DfT transport appraisal guidelines.

Affordability is determined by the Regional Transport Board against to other regional priorities.

• Environmental

Contribution to Climate Change

Visual/Environmental/Ecological/Archaeological Impact

• Deliverability

RTB Delivery Programme and Project Risk Register

6. The bid will need to satisfy the following questions:

• Does the scheme fit with National, Regional and Local Policy? • Is the scheme good value for money? • Does the scheme address the desired traffic objectives (ORR & Citywide travel times and congestion)? • Is accessibility improved? • Is the scheme affordable? • Is the environmental impact of the scheme acceptable? • Are there other Lowest Cost Alternative schemes? • Is the scheme deliverable to the required timescale with minimum risk?

Adopted Transport Strategy

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Outer Ring Road Improvement OptionsAppendix 1 48 KB Download
PDF
Outer Ring Road Improvement OptionsAppendix 2 19 KB Download
PDF
Outer Ring Road Improvement OptionsAppendix 3 22 KB Download
PDF
Outer Ring Road Improvement OptionsAppendix 4 90 KB Download
PDF
Outer Ring Road Improvement OptionsReport 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
AW
Councillor Andrew WallerChair, present
SG
Councillor Steve GallowayCommittee Member, present
SG
Councillor Susan GallowayCommittee Member, present
CJ
Councillor Ceredig Jamieson-BallCommittee Member, apologies
AR
Councillor Ann Reid MBECommittee Member, present
CR
Councillor Carol RuncimanCommittee Member, present
CV
Councillor Christian VassieCommittee Member, present
RM
Councillor Richard MooreAttendee, in attendance

On this subject at York

Search all
  1. Outer Ring Road Improvement OptionsThis decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)Noted
  4. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  5. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  6. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved

More from York Executive - for meetings from 03/06/00 to 26/04/11

All decisions
MeetingDecisionOutcome
26 Apr 2011 MinutesThat the minutes of the Executive meeting held on 12 April 2011 and the Executive (Calling In) meeting held on 5 Apri... Approved Open
26 Apr 2011 Final Report Arising from Carers' ReviewThat the following be agreed as the Executive’s response to the recommendations of the Carers’ Review Task Group: Tas... Agreed Open
26 Apr 2011 Minutes of Working GroupsThat the minutes be noted and that the specific recommendations made by the Local Development Framework Working Group... Noted Open
12 Apr 2011 MinutesThat the minutes of the Executive meeting held on 29 March 2011 and of the Executive (Calling In) meetings held on 21... Approved Open
12 Apr 2011 Final Report arising from the Edible York Ad Hoc Scrutiny ReviewThat the recommendations of the Ad Hoc Scrutiny Committee be supported and approved, subject to the following amendme... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies