That 1) Approve the recommended procurement routes set out in Annex A for the required support and construction services, approve the carrying out of those recommended procurement processes and to delegate to the Director of Economy and Place (in consultation with the Director of Governance or her delegated officers) the authority to take such steps as are necessary to procure, award and enter into the resulting contracts. 2) Approve the recommendation for officers to develop and pursue a public engagement strategy which incorporates the provisions of physical distancing. 3) Approve the landscaping principles, specifically the commitment to provide a net gain in tree planting, bio-diversity and habitats following the strategy developed by the Environment Agency. Reason: To enable the project to move forward in an efficient and cost effective manner, providing for a quicker overall delivery programme for the scheme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
1. At the February 2020 Executive meeting, Members gave approval to merge the proposals for the York Outer Ring Road (YORR) junction upgrades and dualling projects into a single programme (‘the scheme’) of planning and delivery. It is important at this time to seek three critical decisions to ensure that momentum is maintained throughout the remainder of the lockdown period, and that a rapid start up to development work on the scheme is in place to ensure that there is no pause due to the Covid-19 virus.
2. The first project critical decision being sought is for approval of the proposed delivery and procurement strategy. A review and options appraisal has been carried out leading to the production of a strategy which best meets the needs of the scheme to ensure efficient delivery and value for money.
3. The second project critical decision is about the approach to public engagement. The project team are seeking endorsement to pursue and develop a public engagement strategy which complies with the guidance concerning physical distancing whilst maintaining the integrity of the process.
4. Finally, the third project critical decision is about seeking a commitment to a net gain in tree planting and woodland areas following the principles recently set out and being promoted by the Environment Agency. This needs to be considered at this early stage in order to be incorporated into the design and land take requirements. Recommendations
5. The Executive are requested to:
1) Approve the recommended procurement routes set out in Annex A for the required support and construction services, approve the carrying out of those recommended procurement processes and to delegate to the Director of Economy and Place (in consultation with the Director of Governance or her delegated officers) the authority to take such steps as are necessary to procure, award and enter into the resulting contracts.
2) Approve the recommendation for officers to develop and pursue a public engagement strategy which incorporates the provisions of physical distancing.
3) Approve the landscaping principles, specifically the commitment to provide a net gain in tree planting, bio-diversity and habitats following the strategy developed by the Environment Agency.
Reasons: to enable the project to move forward in an efficient and cost effective manner to enable a quicker overall delivery programme for the scheme.
Background
Delivery and Procurement Strategy
6. The amalgamation of the Junction Scheme and the Dualling proposals has provided a step change in the scale of the project. It is appropriate at this time to review the supply chain and services now required.
7. The project team, alongside colleagues from Procurement and Legal Services, have taken the opportunity to take a step back and consider the best way to deliver the scheme from this point up to and including the construction stage.
8. The project team have considered the contracts that are already in place in respect of the junction improvements and whether it is appropriate to extend the existing arrangements to cover the scheme. In doing so, consideration has been given to what work has been carried out, what the value of the current contracts are, what the potential value of the contracts will be going forward and the performance of the current contractors.
9. Finally, the project team carried out an options appraisal of the available procurement routes in respect of each service required, including those currently under contract. The results of the options appraisal are set out in Annex A - Recommended Procurement Routes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.