City of York Council
Executive, Thursday 16 June 2022 at 5.30pm

York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)

Noted Executive 4 papers

Executive noted this item on Thursday 16 June 2022. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

(i) That it be noted that a planning application for the proposed scheme is about to be submitted. (ii) That the general progress and ongoing work on the scheme be noted. Reason: To be informed on the progress of the scheme and take this into consideration for future decision-making. (iii) That Option 1 be approved; that is, for the project team to identify, procure and undertake utility diversionary works within the existing highway in connection with the scheme, and where possible, in advance of the main works programme. Reason: To comply with the provisions of the NRSWA 1991, and to maximise the opportunity to eliminate or reduce delay risks and resultant prolongation claims on the main construction programme. (iv) That authority be delegated to the Director of Transport, Environment and Planning, in consultation with the Director of Governance or her delegated officers, to procure and take all necessary steps to implement the diversions of the Statutory Undertakers’ apparatus, as required on the Scheme. Reason: So that the Director of Transport, Environment and Planning is authorised to take such steps as are necessary to engage and negotiate with Statutory Undertakers for the efficient and timely delivery of utility diversions on the proposed scheme. (i) That it be noted that a planning application for the proposed scheme is about to be submitted. (ii) That the general progress and ongoing work on the scheme be noted. Reason: To be informed on the progress of the scheme and take this into consideration for future decision-making. (iii) That Option 1 be approved; that is, for the project team to identify, procure and undertake utility diversionary works within the existing highway in connection with the scheme, and where possible, in advance of the main works programme. Reason: To comply with the provisions of the NRSWA 1991, and to maximise the opportunity to eliminate or reduce delay risks and resultant prolongation claims on the main construction programme. (iv) That authority be delegated to the Director of Transport, Environment and Planning, in consultation with the Director of Governance or her delegated officers, to procure and take all necessary steps to implement the diversions of the Statutory Undertakers’ apparatus, as required on the Scheme. Reason: So that the Director of Transport, Environment and Planning is authorised to take such steps as are necessary to engage and negotiate with Statutory Undertakers for the efficient and timely delivery of utility diversions on the proposed scheme.
Word for word from the decision York published for this meeting. Source: democracy.york.gov.uk

Follow this further

Built from York's papers

What the report saysPro

Report to Executive
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Equalities Impact AssessmentAppendix A 15 pages Download
PDF
View as HTML (7./2) 105 KBAppendix 105 KB Copy on its way
PDF
View item 7. as HTML 109 KBReport 109 KB Copy on its way
PDF
York Outer Ring Road (YORR): Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling: Update on Progress and Proposed Utility Diversions (6:32 pm)Report 14 pages Download

At this meeting

Whole meeting

On this subject at York

Search all
  1. York Outer Ring Road (YORR) - Proposed A1237 (Rawcliffe to Little Hopgrove) Dualling - Update on Progress and Proposed Utility Diversions (6:32 pm)This decision
  2. Major Projects (Station Gateway and York Outer Ring Road Business Case)Approved
  3. York Outer Ring Road (YORR) – Phase 1 Dualling – Evaluation of the Consultation Process and Resolution to Submit a Planning ApplicationNoted
  4. York Outer Ring Road Phase 1 Dualling - Resolution in principle to promote a Compulsory Purchase Order and associated Side Roads Order.Noted
  5. York Outer Ring Road Phase 1 Dualling - Procurement Strategy, Approach to Public Engagement and LandscapingApproved
  6. York Outer Ring Road Improvements – Dualling from A19 Rawcliffe to A64 HopgroveNoted

More from York Executive

All decisions
MeetingDecisionOutcome
3 Nov 2026 Minutes (4:46pm)That the Minutes of the Executive meeting held on 6 October 2026 be approved and signed as a correct record. Approved Open
3 Nov 2026 Capital Programme Monitor Update 2 Report (4:47pm)Resolved (unanimously) that Executive: i. In relation to the overall programme: · Recommended to Full Council the adj... Noted Open
3 Nov 2026 Q2 2026-27 Finance and Performance Monitor (4:47pm)Resolved (unanimously) that Executive: i. Noted the finance and performance information. ii. Noted that work will con... Noted Open
3 Nov 2026 Treasury Management Quarter 2 Prudential Indicators (4:47pm)Resolved (unanimously) that Executive: · Noted the 2026/27 Treasury Management activity up to the period ending 30th ... Noted Open
3 Nov 2026 Medium Term Financial Strategy Update (4:47pm)Resolved (unanimously) that Executive: · Agreed the Medium Term Financial Strategy as outlined in this report · In re... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies