Neighbourhood Services Capital Programme Monitor 2
ApprovedExecutive1 paper
Decision Session - Executive Member for Neighbourhoods and Housing. approved this item on Tuesday 17 November 2009. Below is the council's own wording, with the papers it was decided on.
That the Executive Member for Neighbourhood Services approves: (i) The slippage of the Boroughbridge Road/Poppleton into 2010/11 (ii) Bringing forward the Crichton Avenue, Skeldergate Bridge and Saxford Way schemes into 2009/10. REASON: To enable the effective management and monitoring of the Councils capital programme. That the Executive Member for Neighbourhood Services approves: (i) The slippage of the Boroughbridge Road/Poppleton schemes into 2010/11 (ii) The bringing forward of the Crichton Avenue, Skeldergate Bridge and Saxford Way schemes into 2009/10. REASON: To enable the effective management and monitoring of the Councils capital programme.
Word for word from the decision York published for this meeting.Source: democracy.york.gov.uk
Report to Decision Session - Executive Member for Neighbourhoods and Housing.
Meeting of Executive Member Decision 17 November 2009 Session – Neighbourhood Services Report of the Director of Neighbourhood Services
NEIGHBOURHOOD SERVICES CAPITAL PROGRAMME MONITOR 2 Summary 1. The purpose of this report is to:
• Inform the Executive Member of the likely outturn position of the 2009/10 Capital Programme based on the spend profile and information to September 2009;
• To notify of any resulting changes to the programme;
• Inform the Executive Member of any slippage and associated funding to be slipped between the relevant financial years to reflect this.
Background 2. The 2009/10 – 2013/14 capital programme was approved by Council on 26th February 2009. The current approved capital programme for 2009/10 is £4.657 m, financed by £2.248 m of external funding*, leaving a cost to the Council of £2.409 m. Table 1 illustrates the movements from the original budget to the currently approved position. Gross External Capital Budget Funding* Receipts £m £m £m
Original Budget 4.657 2.248 2.409 Approved by Council at 26 Feb 2009 Additions/reductions 1.780 1.780 0.000 approved at monitor 1 Slippage approved at (0.008) 0 (0.008) monitor 1 Current Approved 6.429 4.028 2.401 Capital Programme *External funding refers government grants, non-government grants, other contributions, developer’s contributions and supported capital expenditure. Table 1 Current Approved Capital Programme
3. The capital receipts column above implies receipts generated from the sale of Council assets will be used to fund the difference between the gross budget less all other specified funding sources. Due to the current economic climate not being favourable to achieving maximum receipt value from asset disposals, consideration will be given to the use of prudential borrowing to fund the capital programme as a temporary measure. When the economic climate returns to a more favourable state assets will be sold with the receipts being applied to finance the programme thus replacing the temporary borrowing.
Consultation 4. The capital programme was developed under the Capital Resource Allocation Model (CRAM) framework and agreed by Council on 26th February 2009. Whilst the capital programme as a whole is not consulted on, the individual scheme proposals do follow a consultation process with local Councillors and residents in the locality of the individual schemes.
Summary of Key Issues 5. Against the current approved budget of £6.429m, there is a predicted outturn of £5.179m, a net decrease of £1.250m.
6. The net decrease is composed of: • Slippage of £1,000k into 2010/11 on the A19 scheme within the Structural Maintenance. • Slippage of £100k into 2010/11 on the EcoDepot Gatehouse/Reception scheme. • Slippage of £150k into 2010/11 on the Boroughbridge Road scheme with Structural maintenance and bring forward the schemes for Crichton Avenue, Skeldergate Bridge and Saxford Way with funding of £150k therefore a nil effect on funding. 7. Table 2 highlights scheme specific information:
Gross Neighbourhood 2009/10 2010/11 2011/12 Total Para Services Capital Ref Programme £m £m £m £m Current Approved Capital 6.429 4.226 5.555 16.210 Programme Re-profiling: Structural Maintenance (1.000) 1.000 0 0 EcoDepot gatehouse (0.100) 0.100 0 0
Revised Capital 5.329 5.326 5.555 16.210 Programme Table 2 Capital Programme Forecast Outturn 2009/10 – 2011/12
8. The main highlights of this report are:
• Slippage of £1,000k into 2010/11 on the A19 scheme within the Structural Maintenance scheme. • Slippage of £100k into 2010/11 on the EcoDepot gatehouse/reception scheme. • Slippage of £150k into 2010/11 on the Boroughbridge Road scheme with Structural maintenance and bring forward the schemes for Crichton Avenue, Skeldergate Bridge and Saxford Way with funding of £150k therefore a nil effect on funding.
Scheme Specific Analysis Air Quality Management 09/10 Budget: £50k (DEFRA Grant) 09/10 Forecast: £50k
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Decision Session - Executive Member for Neighbourhoods and Housing. at York and we tell you when its next papers are published, before the meeting rather than after it.
Update on Private Sector Strategy.That the Executive Member noted the overall progress made to date in delivering the Private Sector Housing Strategy. ...
Achieving the Decent Homes Standard.(i)That the Executive Member noted that the Council has met the decent homes standard in line with the Governments De...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.